Professional Documents
Culture Documents
FORCE MAJEURE
”A contractual provision allocating the risk if performance
becomes impossible or impracticable, especially as a result of an
event or effect that the parties could not have anticipated or
controlled.”
- Blackstone’s dictionary
The legislators have to some extent dealt with this concept
as is clear from Section 32 of the Indian Contract Act, 1872
dealing with contingent contracts.
LEGAL Section 32 of the Indian Contract Act, 1872 reads as
PROVISION follows:
IN THE
INDIAN "32. Enforcement of contracts contingent on an event
happening –Contingent contracts to do or not to do
CONTRACT anything if an uncertain future event happens, cannot be
ACT, 1872 enforced by law unless and until that event has happened.
If the event becomes impossible, such contracts become
void."
“56. Agreement to do impossible act
Contract to do an act afterwards becoming impossible or unlawful.—
A contract to do an act which, after the contract is made, becomes
impossible, or, by reason of some event which the promisor could not
prevent, unlawful, becomes void when the act becomes impossible or
SECTION 56
unlawful. OF THE
Compensation for loss through non-performance of act known to be INDIAN
impossible or unlawful.—Where one person has promised to do
something which he knew, or, with reasonable diligence, might have
CONTRACT
known, and which the promisee did not know, to be impossible or ACT, 1872
unlawful, such promisor must make compensation to such promisee
for any loss which such promisee sustains through the non
performance of the promise.”
Satyabrata Ghosh v. Mugneeram Bangur
This case is related to sale of land and the question before the court was certain
supervening events which affected the material part of it and would those events
and Adani Power Ltd. (“Adani”) on the one hand and the electricity regulators on
the other was adjudicated upon finally by the Supreme Court by ruling in favour
of the latter.
Held: The Supreme Court has held that when
DECISION OF a force majeure event is relatable to a clause
THE SUPREME
COURT IN BOTH (express or implied) in a contract, it is
THE CASES
governed by Section 32 of the Act whereas if
a force majeure event occurs dehors the
contract, Section 56 of the Act applies.
1. Events should render the performance of the contract
impossible
OF INVOKING
“FORCE 4. The incident would have happened not because of the party’s
default but only because of the supervening event
MAJEURE”
5. Condition precedent
6. Duty to mitigate
Externality- the cause is not created
by the defaulting party's fault;
TESTS THAT Unpredictability- The cause must be
FORCE inevitable and unforeseeable; and
MAJEURE Irresistibility- The cause must make
MUST PASS execution of the contract wholly
impossible.
1.Destruction of subject matter
GROUNDS ON 2.Death or incapacity for personal service
WHICH THE 3.Non- existence or non- occurrence of a particular
DOCTRINE OF state of things
FRUSTATION 4.Intervention by legislative or executive authority
CAN BE 5.Intervention of war
ESTABLISHED
6.Change of circumstances of particular state of things.
DOCTRINE OF
FORCE MAJEURE FRUSTRATION
clauses typically constitute force majeure events and thereafter add “and such other acts or events
Conditions which would have be fulfilled for such force majeure clause to
event.
What happens if
the force majeure The parties would have to ascertain in light factors:
clauses are not
nature of the contract
included?
the nature of event
whether Section 56 of the Contract Act can be
applied to such contract so as to discharge the
parties from their contractual obligations.
1. Temporary suspension of contract
2. Termination of contract
PANDEMIC = In this case, it was held that the inability of a party to deliver an
ACT OF GOD aircraft on time due to a pandemic causing a dearth of pilots
fell within the catch-all residuary wording of a force majeure
clause.
CAUSATION
AND
MITIGATION
The force majeure event must have a direct
Sri Ananda Chandra
impact on the non-performance and the
Behera v. Chairman,
party seeking to rely on the force majeure
Orissa State Electricity
Board
event is also under duty to mitigate and/or
explore alternate means of performance.
The absence of a direct causal link between Covid-19
INSTANCES
pandemic and the non-performance.
WHEN
PERFORMANCE When employees of an organization in the service industry
OF CONTRACT have to isolate themselves at home.
NOT AFFECTED
Any non-performance due to an economic downturn or other
BY COVID 19
PANDEMIC general business conditions resulting from the Covid-19
pandemic.
Bombay High Court’s Order passed in Rural Fairprice Wholesale
Ltd. & Anr. vs IDBI Trusteeship Services Ltd. & Ors. on 3 April
2020
COVID 19 In this case, the HC recognized the market situation pursuant to the
THROUGH COVID-19 and observed that the share market had collapsed due to
JUDICIAL LENS COVID-19, therefore, it was a fit case to restrain the bank from acting
upon the sale notices and a direction to withdraw any pending sale
orders for the pledged shares.
Bombay High Court’s Order passed in Standard Retail Pvt. Ltd vs
Gs Global Corp And Ors.
Developers The petitioner failed to make the weekly revenue payment to the respondent after
the declaration of the Covid-19 pandemic and the consequent lockdown
Limited v South restrictions.
Delhi Municipal As a result of this lockdown, the petitioner could not generate any revenue from
the toll and thus he defaulted on making any payment to the respondent.
Corporation & Vide the order dated March 2020, the petitioner was asked to pay the arrears in
Ors. three monthly installments and not to default in the future weekly payments.
Thereafter, the petitioner approached the Delhi High Court and claimed that
because of the force majeure which is the Covid-19 pandemic, the performance of
contact had become impossible.
There was an office memorandum by the Ministry of Finance which
MEP stated that any disruption due to the spread of the coronavirus in China
Infrastructure or in any other country will be covered in the clause of ‘force majeure’.
Developers Limited
v South Delhi The circular also stated that the coronavirus pandemic may be considered
Municipal a natural calamity and the force majeure clause may be invoked in case
Corporation & of disruption of business.
Ors.
dated Held: A force majeure clause instantly comes into effect once it has been
12.06.2020 acknowledged by the other party. Accordingly, in such circumstances,
the need to explicitly invoke the force majeure clause does not arise.
Force-majeure or doctrine of frustration cannot be applied as a
general principle, the application will depend upon the facts and
circumstances of each case.