i. 111 days delay in handing over of project site to start the work.
ii. 402 days delay in Casting of civil structure of Plant room
iii. 540 days delay in First floor Civil works i.e Structure work, Block works and false ceiling
work.
iv. 226 days delay in providing the trench to install the chilled water pipe in between building and
plant room.
v. 540 days delay in providing the civil work clearance in aero bridge area at first floor level.
vi. 402 days Delay in providing the Area clearance for water softener installation.
vii. Due to all the above delay from the construction part the project has been delayed 500 days.
viii. The EOT was approved by AAI vide letter number-AAI/CL/Engg (E)/HVAC-BMS/2020/034
dated 18.03.2020.
Got the Extra Items & Deviation items approval as per the CPWD DSR-2018.
Successfully close the final account for the job..