Professional Documents
Culture Documents
EGYPT
ENGINEERING DEPARTMENT
MECHANICAL SECTION
1.Engineering
2.Execution
3.Test & Commissioning
1.Engineering 3
1.1 Chillers
Case:
Installing the chiller water headers @ the same level or lower than
chiller inlet & outlet causes air pockets & damages chiller coils in the
long run.
Recommendation:
The chilled water headers into & out of the chillers levels shall be
above the chillers to avoid the following:
A- Creating air pockets within the chiller coil.
B- Poor maintenance space.
4
5
1.2 Cooling Towers (CTs)
1.2A Condenser Water Header
Case:
Condenser water header feeding CTs installed higher or @ the same levels
of cooling tower inlets.
1- Condenser water high drain volume.
2- CT high flooding.
3- High make-up volume.
4- High chemical consumption.
Recommendation:
The condenser water header feeding CT from the condenser water pump
must be lower than the CT to avoid the above mentioned issues.
6
7
Recommendation:
In some congested areas, the daily tanks are located in a level higher
than the generator, that lead to fuel dripping from the generator
injectors causing the generator to stop working, so it is
recommended to place the daily tanks in same level of the generator.
14
15
16
1.6 CHW External Networks.
Case:
Buried networks flushing taking too long & not being effective.
Recommendation:
For external buried networks it is recommended to install wash
out valves at the end of CHW path to collect any scales or dirt &
improve external CHW flushing.
17
18
19
Recommendation:
For public toilets exhaust , it is
recommended to replace door undercut
with door louver or supply air at lavatory
area to avoid bad smell & high toilet
temperatures.
24
1.11 Duct Risers
Case:
Low air flow rates & balancing issues @ the lowest floor.
Recommendation:
For duct risers , it is recommended to make lowest branch
connection with the riser by take off with plug instead of
elbow to facilitate cleaning the riser in case of any dirt.
25
End Cap
RECOMMENDED
Not Recommended
29
Recommendation:
During start up & commissioning activities , the VSD setting is required to be
set in a way the secondary CHW flow to be equal or lower than the primary
flow , to avoid:
1. A-Secondary flow circulation through the load loop with high flow rates &
circulation through the chillers will be decreased. causing the load CHW
temp & space temp to be elevated.
2. B-Chillers may be stopped due to low primary CHW flow.
51