Unfit to Fit – < Unix> Current Status
Current status of Unfit Cis
Cat A Cat B Total
54 193 247

Reasons for CI being unfit


      Remediation Options

# Unfit reason Count Option 1 Dependency Option 2 Dependency

OS upgrade
Target version:
SLES11 SP4
Outdated OS version SLES12 SP5
 1 (SUSE+RHEL) 71 RHEL 7.9 Downtime approval NA  NA 

1. Procurement of
new hardware
1. Downtime approval 2. Downtime
2. Application compatibility in Hardware approval 
 2 Old Hardware 24  Migrate to Esxi virtualized platform refresh   
1. Procurement of new hardware
 3 No redundancy 232  Set up cluster 2. Downtime approval  NA  NA

Copyright © 2020 Accenture. All rights reserved. 2


Unfit to Fit – < Tower Name> Remediation plans

Proposed approach for Remediation


Phase Target CI
# Target CI details count Option Selected Timelines Remarks

OS upgrade – SP migration (Target OS
version: SLES11 SP4, SLES12 SP5 & Application owners will be requested
1 Please refer excel  71 RHEL 7.9) 2 hrs./server to provide downtime for OS upgrade 

Discussion will be initiated with Chris


Leiner and Andreas Gschneidner
for this project – TIBCO & MES
Virtualization -> Provision VM on servers will be targeted as
Please refer excel  Simplivity and migrate application from virtualization has already been done
 2   33  physical to virtual  3 bd/server  for few in same category 

Those servers will be targeted for


which virtualization is not an ideal
Please refer excel  solution e.g., standby DB servers &
 3   18 Hardware refresh  10 bd/server RapidMiner systems

Copyright © 2020 Accenture. All rights reserved. 3