Topic 8
LEARNING OUTCOMES
• After completing this chapter, you should be able to:
1. Apply lag relationships to project activities.
2. Construct and comprehend Gantt charts.
3. Recognize alternative means to accelerate projects, including
their benefits and drawbacks.
4. Understand the trade-offs required in the decision to crash
project activities.
5. Develop activity networks using Activity-on-Arrow techniques.
6. Understand the differences in AON and AOA and recognize the
advantages and disadvantages of each technique.
OUTLINE
• Optimasi Jadwal: Menerapkan Leads, Lags dan Crashing
• Membangun Jaringan Aktivitas dengan teknik Activity on Arrow
PMBOK Core Concepts
Project Management Body of Knowledge (PMB0K) covered in this chapter includes:
1. Plan Schedule Management (PMBoK 6.1)
2. Define Activities (PMBoK 6.2)
3. Sequence Activities (PMBoK 6.3)
4. Precedence Diagramming Method (PMBoK 6.3.2.1)
5. Leads and Lags (PMBoK 6.3.2.3)
30 R 36
Wiring
6
31 S 33 33 T 36 36 U 42
Plumbing HVAC Under construction
2 3 6
30 R 36 Lag 3
Wiring
6
34 S 36 36 T 39 39 U 45
Plumbing HVAC Under construction
2 3 6
Source: Pinto (2016)
Start to Start Lag
Logic must be
maintained b
y both
30 R 36 forward and
Wiring backward pas
s.
6
Lag 3
33 T 36 36 U 42
31 S 33 HVAC Under construction
Plumbing 3 6
2 Source: Pinto (2016)
Start to Finish Lag
• Least common type of lag relationship
• Successor’s finish dependent on
20 W 26 predecessor’s start
6
Lag 3
18 X 20 20 Y 23 23 Z 29
2 3 6