Professional Documents
Culture Documents
Microsoftr Office Project 2007-Linking Project Tasks
Microsoftr Office Project 2007-Linking Project Tasks
Microsoft Office
®
Dependency links
Dependency links
You can use four
types of task
dependencies (or
links) to define the
relationships between
tasks in your Project
plan.
1. Start-to-Start (SS).
2. Finish-to-Start (FS).
3. Finish-to-Finish (FF).
The minute that both “Lay the Carpet” and “Install the Lights” are
finished, you can start on “Paint the Walls.”
Editing will finish when the writing finishes. And because the two tasks
overlap, the overall duration is 12 days.
Next, press the CTRL key and select the task that will be
the successor of the task that you have already
selected.
1. Use your mouse to drag across the tasks from top to bottom,
and then click Link Tasks.
2. Hold the CTRL key, click the lower task, click the task that
appears higher in the task list, and then click Link Tasks.
3. Hold the Shift key while clicking each task, and then click Link
Tasks.
Tasks are linked in the order in which you selected them when you use
the CTRL key.
This shortens the overall duration to 9 days without affecting the start
date of the Project plan.
In Project, you can build in a delay between the finish of one task and the start of
another. Or you can make one task overlap with another.
1 For delay, use lag time. This accounts for something that
must happen between two tasks, such as waiting for a
shipment of supplies to arrive.
2 For overlap, use lead time. If a task can start a week
before the previous one is finished, a lead time of seven
days gets that second ball rolling.
For the “Edit Manual” task, you’d enter 3 in the Lag field on the
Predecessors tab in the Task Information dialog box, and then
click OK.
3. Add a task.
1. “Lay the Carpet” Start-to-Start to “Paint the Walls” with a lead time
of three days.
2. “Lay the Carpet” Start-to-Finish to “Paint the Walls” with a lag time
of three days.
3. “Lay the Carpet” Start-to-Start to “Paint the Walls” with a lag time of
three days.
This schedules “Lay the Carpet” to start first and “Paint the Walls” to
start three days later.
The tasks are linked by their finish dates, but “Select Pictures” will finish
one week before “Presentation” does.
Editing will start 6 days after the start of writing. Writing and editing will
overlap for 9 days and then editing will continue for another 3 days,
making the overall duration 18 days. Well planned!