Professional Documents
Culture Documents
COMPUTER APPLICATIONS IN
ENGINEERING
Presented by
Tom Joseph MUKASA RSU(QS), MRICS, FISU
Contact Information:
C/O P.O. Box 3085, Kampala
Tel. 0755 979936
E-mail: tjmukasa79@yahoo.com
INTRODUNCTION
Once you have created and defined your project plan, including the start, and end
date. And when your resources will be working on the project you can start, mapping
out a schedule of the tasks, that need to be completed and when they will need to be
performed.
For each task, you'll need to capture the specific details that, both collectively and
individually will have an effect on your Project Timetable.
These include, when a task must be completed? how long a task will take to
complete? how much time a resource can work on that task? how tasks are related to
each other, in terms of start and end dates and so on.
In this lesson, you'll create a project schedule in Microsoft project that contains, all
the tasks, that need to be performed throughout the duration of your project.
CREATING A TASK-BASED
SCHEDULE 2
GENERAL INTRODUCTION
CREATING A TASK-BASED
SCHEDULE 3
2.1.01 MANUALLY SCHEDULED vs AUTO SCHEDULED
TASKS
When scheduling new tasks in Microsoft Project, you are given two
options: Manually Scheduled and Auto Scheduled. By default, all new tasks that
you enter into a project plan will be manually scheduled, which gives you complete
control of the task’s start date, end date, and duration. However, you can also choose
to have new tasks auto scheduled, which automatically calculates the start date, end
date, and duration for the task based on relationships to other tasks, calendar dates,
and other assorted factors.
Using the manually scheduled option is the most useful when you have a simple
project or are just getting started with a project plan. But as your project plan grows
more complex, you may want to switch to the auto scheduled option. Microsoft
Project allows you switch between these modes whenever you’d like, either for
individual tasks or for all tasks in the project plan. There may be some cases where
you need some tasks to be manually scheduled and others auto scheduled, based on
your project’s specifications.
To change whether new tasks that you add to a project are manually scheduled or
auto scheduled, you can select the New Tasks button in the status bar at the bottom
of the project file window.
CREATING A TASK-BASED
SCHEDULE 4
2.1.01 MANUALLY SCHEDULED vs AUTO SCHEDULED
TASKS
To change whether existing tasks are manually scheduled or auto scheduled, you
can select the appropriate command from the Tasks group on the Task tab of the
ribbon.
CREATING A TASK-BASED
SCHEDULE 5
2.1.02 THE TASK ENTRY BOX
The default Gantt Chart view in Microsoft Project contains the Task
Entry table at the left, which is the main area where you can view,
enter, and modify your project’s tasks.
CREATING A TASK-BASED
SCHEDULE 6
2.1.02 THE TASK ENTRY BOX
The Task Entry table contains information for each of the tasks
entered in columns from left to right.
Task Entry Table Column Description
Row Number Displays the row number of
the task in the Gantt Chart,
which also corresponds to
the Task ID number for that
task.
Indicators Displays icons that show
the status of the task and
pertinent information about
the task. For instance, if a
task has a note associated
with it, a note indicator will
appear in this column.
CREATING A TASK-BASED
SCHEDULE 7
2.1.02 THE TASK ENTRY BOX
The Task Entry table contains information for each of the tasks
entered in columns from left to right.
Task Entry Table Column Description
Task Mode Shows whether the task is a
manually scheduled or auto
scheduled task.
Task Name Displays a brief description
of the task and the work to
be done. Short, action-
oriented task names are
recommended, such as
“secure permit.”
CREATING A TASK-BASED
SCHEDULE 8
2.1.02 THE TASK ENTRY BOX
The Task Entry table contains information for each of the tasks
entered in columns from left to right.
Task Entry Table Column Description
Duration Displays how long a task
will take to complete. By
default, Microsoft Project
displays the duration in
days, but you can specify
minutes, hours, weeks, or
even months as the unit of
time.
Start Displays the date when the
task is supposed to begin.
CREATING A TASK-BASED
SCHEDULE 9
2.1.02 THE TASK ENTRY BOX
The Task Entry table contains information for each of the tasks
entered in columns from left to right.
Task Entry Table Column Description
Finish Displays the date when the
task is supposed to be
completed.
Predecessors Displays the Task ID(s) of
any other tasks on which
the task is dependent upon
for completion.
CREATING A TASK-BASED
SCHEDULE 10
2.1.03 THE TASK INFORMATION DIALOG BOX
When you open a task from the Gantt Chart view, the Task Information dialog box
displays.
You can view and modify all of the information for the task from the six tabs within the
dialog box.
CREATING A TASK-BASED
SCHEDULE 11
2.1.03 THE TASK INFORMATION DIALOG BOX
You can view and modify all of the information for the task from the six
tabs within the dialog box.
Tab Description
General On the General tab you can view and
modify the task’s name, duration, schedule
mode, start date, and finish date. This
information corresponds to the fields in
the Task Entry table.
Predecessors A predecessor is a task that must be
started or completed before another task
can begin. On the Predecessors tab you
can view all of the task’s predecessors,
including their task ID, name, and type.
CREATING A TASK-BASED
SCHEDULE 12
2.1.03 THE TASK INFORMATION DIALOG BOX
You can view and modify all of the information for the task from the six
tabs within the dialog box.
Tab Description
Resources On the Resources tab you can view, enter,
or modify the resources assigned to the
task, including the resource’s name, the
assignment owner, the number of
assignment units allocated to the task, and
the costs associated with the resource.
Advanced On the Advanced tab you can view, enter,
or modify supplemental information about
the task, including its deadline, any
constraints that might affect the task, the
task type, the calendars or work
breakdown structure that the task is
associated with, whether to mark the task
as a milestone,
CREATING and more.
A TASK-BASED
SCHEDULE 13
2.1.03 THE TASK INFORMATION DIALOG BOX
You can view and modify all of the information for the task from the six
tabs within the dialog box.
Tab Description
Notes On the Notes tab, you can view, enter or
modify any further information for the task
that may be useful, in the form of a text
note.
Custom Fields On the Custom Fields tab, you can view,
enter, or modify any custom data fields that
have been created and associated with the
task.
CREATING A TASK-BASED
SCHEDULE 14
2.1.04 TASK DURATIONS
In the Task Information dialog box, the Duration field shows the amount of time it will
take to complete the specific task. In most cases, you will know how long it is going to
take to complete the task, so you would enter this amount in the Duration field. The
default unit of time for task duration is days, but if needed, you can also enter the
duration in minutes, hours, weeks, or months.
CREATING A TASK-BASED
SCHEDULE 15
2.1.05 DURATION Vs WORK
In project management, the concepts of duration and work are not the same
thing. Duration is the total number of work periods (excluding holidays or
other nonworking periods) required to complete a schedule activity or work
breakdown structure component. Usually expressed as workdays or
workweeks. Sometimes incorrectly equated with elapsed time. Contrast with
effort.* Work is the amount of time it will take to complete the task (the
duration), multiplied by the level of effort that will be given to the task by the
resources assigned to it. For example, if the task “secure work permit” has a
duration of 3 days and the resource “Jack” will give 50% of effort to the task,
then the work for the task is 1.5 days.
For tasks with a fixed amount of work, then, you can decrease the duration of
the task by increasing the effort level through more resources. For instance, if
the task “perform quality testing” has a duration of 6 days and a single quality
controller is assigned to the task with 100% effort level, assigning another
quality controller to the same task with 100% effort level would reduce the
duration to 3 days.
CREATING A TASK-BASED
SCHEDULE 16
2.1.06 DEPENDENCIES
CREATING A TASK-BASED
SCHEDULE 17
2.1.06 DEPENDENCIES
CREATING A TASK-BASED
SCHEDULE 18
2.1.06 DEPENDENCIES
CREATING A TASK-BASED
SCHEDULE 19
2.1.07 LAG TIME
You can add lag time between tasks by opening the Task Information dialog box for
the successor task, and on the Predecessors tab, entering a positive value in
the Lag field for the predecessor task.
CREATING A TASK-BASED
SCHEDULE 20
2.1.08 LEAD TIME
You can add lead time between tasks by opening the Task
Information dialog box for the successor task, and on the Predecessors tab,
entering a negative value in the Lag field for the predecessor task. (In short,
negative lag is technically lead.)
CREATING A TASK-BASED
SCHEDULE 21
2.1.08 LEAD TIME
CREATING A TASK-BASED
SCHEDULE 22
2.1.09 TASK CONSTRAINTS
CREATING A TASK-BASED
SCHEDULE 23
2.1.09 TASK CONSTRAINTS
CREATING A TASK-BASED
SCHEDULE 24
2.1.10 DEADLINES
CREATING A TASK-BASED
SCHEDULE 25
2.1.10 DEADLINES
You can set a deadline for a task on the Advanced tab of the Task
Information dialog box, by selecting the appropriate date from
the Deadline field.
CREATING A TASK-BASED
SCHEDULE 26
HOW TO CREATE A PROJECT SCHEDULE
CREATING A TASK-BASED
SCHEDULE 27
2.1.11 How to Create a Project Schedule
CREATING A TASK-BASED
SCHEDULE 28
2.1.11 How to Create a Project Schedule
Define Task Relationships Add Lead Time
To change the relationship type between a To add lead time to linked tasks:
task and its predecessor: Double-click the successor task in the Task
Double-click the successor task in the Task Entry table.
Entry table. In the Predecessors tab of the Task
In the Predecessors tab of the Task Information dialog box, enter a negative value
and the unit of time in the Lag column, for
Information dialog box, select the
example, -1 day to set a lead time of one day.
predecessor task relationship you want to
change and select the appropriate relationship Set a Constraint on a Task
type. To set a constraint on a task:
Add Lag Time Double-click the task to open the Task
Information dialog box.
To add lag time to linked tasks:
In the Advanced tab, select the desired
Double-click the successor task in the Task constraint type, and in the Constraint date box,
Entry table. enter or select a date for the constraint.
In the Predecessors tab of the Task Set a Deadline for a Task
Information dialog box, enter a positive value To set a deadline for a task:
and the unit of time in the Lag column, for
Double-click the task to open the Task
example, 1 day to set a lag of one day. Information dialog box.
In the Advanced tab, enter or select a date for
the deadline.
CREATING A TASK-BASED
SCHEDULE 29
2.1.12 ACTIVITY - Creating a Project Schedule
Scenario enter the following tasks in the first four
Now that you have begun your project plan in rows:
Microsoft Project, you want to add some tasks to Determine sales objectives
it. Your project will have several phases, and you Define launch timing and publicity
will add a few tasks in the first phase of the work. objectives
You know how long each task should take, so you Identify budget requirements
can add duration values to the plan at this time.
Obtain launch budget approval
You will also link the tasks in the correct
sequence and address special considerations (lag Add durations for each task.
and lead time, constraints, and deadlines) where In the Duration field for each task, enter the
they will apply. following values:
Open For the Determine sales
the Trey_Slide_Presenter_Tasks.mpp project objectives task, enter 3 days
plan file. For the Define launch timing and
Set Microsoft Project so all new tasks are publicity objectives task, enter 3
automatically scheduled. days
On the Status Bar at the bottom of For the Identify budget
the Gantt Chart, left-click New Tasks: requirements task, enter 1 week?
Manually Scheduled, and change it to New For the Obtain launch budget
Tasks: Auto Scheduled. approval task, enter 1 week
Add the following tasks in the Gantt Chart.
In the Task Entry pane, in the Name field,
CREATING A TASK-BASED
SCHEDULE 30
2.1.12 ACTIVITY - Creating a Project Schedule
Link the tasks in a Finish-to-Start relationship. for Task 4, Obtain launch budget
Select all of the tasks you just entered. approval, by selecting the task name,
In the Schedule group of the Task tab on
then selecting the Information button in
the ribbon, select Link the selected the Properties group of the Task tab.
tasks. In the Predecessors tab of the Task
Change the relationship between Tasks 1 and Information dialog box, select Identify
2 to Start-to-Start. budget requirements, and in the Lag
column type 1d for a 1-day lag.
Open the Task Information dialog box
for Task 2, Define launch timing and Add a lead time between Tasks 2 and 3.
publicity objectives, by selecting the Open the Task Information dialog box
task name, then selecting for Task 3, Identify budget
the Information button in requirements, by selecting the task
the Properties group of the Task tab. name, then selecting
In the Predecessors tab of the Task
the Information button in
Information dialog box, the Properties group of the Task tab.
select Determine sales objectives and In the Predecessors tab of the Task
in the Type field, select Start-to-Start Information dialog box, select Define
(SS). launch timing and publicity objectives,
Add a lag time between Tasks 3 and 4. and in the Lag column type -2d for a 2-
day lead.
Open the Task Information dialog box
CREATING A TASK-BASED
SCHEDULE 31
2.1.12 ACTIVITY - Creating a Project Schedule
Set a constraint for Task 3. Information dialog box, set
Open the Task Information dialog box the Deadline to 8/19/16
for Task 3, Identify budget Save the file
requirements, by selecting the task as My_Trey_Slide_Presenter_Tasks
name, then selecting
the Information button in
the Properties group of the Task tab.
In the Advanced tab of the Task
Information dialog box, change
the Constraint type to Start No Earlier
Than, and set the Constraint
date to 8/2/16
Set a deadline for Task 4.
Open the Task Information dialog box
for Task 3, Identify budget
requirements, by selecting the task
name, then selecting
the Information button in
the Properties group of the Task tab.
In the Advanced tab of the Task
CREATING A TASK-BASED
SCHEDULE 32
2.2.01 USER-CONTROLLED SCHEDULING
There may be instances, when you want to have a greater amount of
control over your project schedule. When you want to forgo any of the
automatic calculations in Microsoft project is capable of performing, for your
schedule tasks. Or maybe you don't know, the specific details of your tasks,
such as start and end dates or duration's. Instead, you just know that there
are certain tasks that need to be completed in those dates and time frames
have yet to be determined.
In any case, you still want to capture the task within the project schedule, so
you have a general idea of the overall organization of the project.
User control scheduling in Microsoft project gives you the ability to craft the
project scheduling using vague, estimated tasks and still have an organized,
easy-to-understand schedule that you can use to execute your plan.
CREATING A TASK-BASED
SCHEDULE 33
2.2.01 USER-CONTROLLED SCHEDULING
Microsoft Project enables you to utilize user-controlled scheduling, in
which you can enter tasks in manually scheduled mode, with or without
specific task information for durations, start dates, or end dates. Instead,
you can enter this information as text—rather than specific dates or units of
time—in order to create a schedule that is more a documentation of
estimations and assumptions, instead of a date-based plan.
CREATING A TASK-BASED
SCHEDULE 34
2.2.02 ESTIMATED DURATIONS
When crafting a user-controlled schedule, you may be unsure of the
task’s true duration. When this is the case, you can mark the task’s
duration as Estimated. To do so, you would enter your best guess
at how long it is going to take to complete the task, and then select
the Estimated checkbox or type a question mark after the value of
the duration. A duration that has been estimated will be shown with
a question mark following the number in the Duration column.
CREATING A TASK-BASED
SCHEDULE 35
2.2.03 Manually Scheduled Summary Tasks
With user-controlled scheduling, Microsoft Project allows you to
manually define the duration of a summary task, rather than
calculating it automatically based on the relationships and durations
of the subtasks. However, by manually scheduling your summary
tasks, it is possible that the duration of the subtasks could be less
than or greater than the duration of the summary task. If so,
Microsoft Project will display a blue or red bar beneath the Gantt bar
for the summary task, warning you of the inconsistency.
CREATING A TASK-BASED
SCHEDULE 36
2.2.04 Warnings and Suggestions
When creating a user-controlled schedule, you may want to use the warnings and
suggestions that Microsoft Project can display to notify you of any potential
problems in your schedule. From the Inspect command drop-down, you can
choose to do one of the following for your tasks:
Show Warnings: displays a warning icon in the Indicators field or some other
visual notification (such as a red squiggle) for tasks that have problems that may
potentially affect the project’s finish date.
Show Suggestions: displays a suggestion icon in the Indicators field or some
other visual notification (such as a green squiggle) for tasks that have potential
minor issues or where optimizations could be made to improve the schedule.
Show Ignored Problems: displays a half-shaded warning icon in
the Indicators field for tasks that have warnings or suggestions that have been
previously noted and ignored.
When you select the Inspect Task command for the indicated task, more
detailed information about the task—including information about the warning or
suggestion—is displayed in the Task Inspector pane at the left side of the
window.
CREATING A TASK-BASED
SCHEDULE 37
2.2.04 Warnings and Suggestions
CREATING A TASK-BASED
SCHEDULE 38
2.2.05 How to Create a User-Controlled Schedule
CREATING A TASK-BASED
SCHEDULE 39
2.2.05 How to Create a User-Controlled Schedule
By default, Microsoft Project sets all tasks to On the status bar at the bottom of
the manually-scheduled mode. Here are the the Gantt Chart, left-click the New
general steps you will perform to change the Tasks button and select Auto Scheduled.
scheduling mode of tasks. Change the Default Project Setting So All
Change the Scheduling Mode for a Task New Projects Are Auto-Scheduled
To change a task from manually-scheduled To change the scheduling mode for all new
to auto-scheduled, and the reverse, follow projects:
these steps while in the Gantt Chart view: Select the File tab, then Options, and
Select the name of the task you wish to then Schedule Options.
change. Click the drop-down arrow next
From the Tasks group on the Task tab of to Scheduling options for this project,
the ribbon, change the mode to the and select All new projects.
scheduling mode you want the task to Beneath this, change New tasks
adopt, either Manually Schedule or Auto created to Auto Scheduled, and
Schedule. click OK to close Project Options.
Change the Scheduling Mode for All New
Tasks
To change the scheduling mode for all new
tasks:
CREATING A TASK-BASED
SCHEDULE 40
2.2.06 Activity – Creating a Project Plan with User-
Controlled Scheduling
Scenario named New_Widget_Project from
You are becoming more familiar with the Create a Project Schedule folder.
user-controlled-scheduling, and you Note that some of the fields have data in
want to experiment with it before them and others do not, and that some
applying it to the Trey Slide Presenter fields have text instead of dates or
project. You remember that by default all numbers. This is a feature of Manually
tasks in Microsoft Project are set to Scheduled tasks.
Manually Scheduled, which means that Link the tasks.
when you add a new task, Microsoft Select the first task name in the
Project does not set dates and durations Task Entry table, hold the Shift key
for it. The Project Management Office and select the last task name.
(PMO) at Trey Research has created a In the Schedule group of the Task
small file for you to work with. The tasks tab select the Link the Selected
are presently Manually Scheduled, and tasks button. The duration and
some of the tasks should become Auto dates fields will then be populated,
Scheduled. You also want to change the but the tasks will still be Manually
default setting in Microsoft Project so all Scheduled.
new projects are Auto Scheduled.
Open the file
CREATING A TASK-BASED
SCHEDULE 41
2.2.06 Activity – Creating a Project Plan with User-
Controlled Scheduling
Change the scheduling mode of the Design to New Tasks: Auto Scheduled.
task. Add a new task at the end of the project.
Select the Design task name, and in In the first blank row of the Task
the Properties group of the Task tab Entry table, enter the
select Information. name Production
In the General tab, change Change the default scheduling mode for all
the Schedule Mode to Auto new projects to Auto Scheduled.
Scheduled. The color of the Gantt bar Select the File tab, then Options, and
will change to a different shade of then Schedule Options.
blue.
Click the drop-down arrow next
Change the scheduling mode of the to Scheduling options for this
Marketing task in the same manner, and project, and select All new projects.
note that the values in
Beneath this, change New tasks
the Duration and Date fields have
changed. created to Auto Scheduled, and
click OK to close Project Options.
Change the scheduling mode for all new
tasks to Auto Scheduled. Save the file
as My_New_Widget_Project and close it.
On the Status Bar at the bottom of
the Gantt Chart, select New Tasks:
Manually Scheduled and change it
CREATING A TASK-BASED
SCHEDULE 42
2.3.01 Create and Modify Project Task Structure
Once you've created a task base schedule, by adding all the necessary tasks in
details. You need a way, to group and organize those tasks in a manner, this is easy
to understand and manage.
Many of your tasks are really larger task that can be broken up into smaller ones, or
they are smaller tasks, that can be rolled up into one larger task.
Within Microsoft Project, you can organize your task into a hierarchical structure, that
helps you easily track the large significant points, within your project schedule.
CREATING A TASK-BASED
SCHEDULE 43
2.3.02 Summary Tasks and Subtasks
In the Gantt Chart view, summary tasks are displayed in bold text in
the task list at the left and with brackets in the Gantt Chart at the
right. Subtasks are indented underneath their summary task. The
summary task can be expanded to show its subtasks using the
arrows to the left of the task name, which makes it easier to switch
between a high-level view of just the larger tasks and a more
detailed view of all of the related tasks.
CREATING A TASK-BASED
SCHEDULE 44
2.3.02 Summary Tasks and Subtasks
CREATING A TASK-BASED
SCHEDULE 45
2.3.02 Summary Tasks and Subtasks
You can create new summary tasks in the Task Entry table using
the Insert Summary Task command from the Insert command
group on the Task tab. For existing tasks, you can change them to
summary tasks using the Outdent Task command or change them
to subtasks using the Indent Task command (from
the Schedule command group on the Task tab).
It is important to note that grouping tasks under a summary task
does not automatically create dependencies among the subtasks.
You must still link subtasks manually in order to create dependent
relationships between them.
Additionally, changing the duration of a summary task will not
always automatically change the duration of the subtasks. However,
changing the duration of the subtasks will change the duration of the
summary task accordingly.
CREATING A TASK-BASED
SCHEDULE 46
2.3.03 The Project Summary Task
Every new project that you create automatically contains a project summary task,
which is the main objective of the project plan. All new tasks that you add to the
project will be subtasks of the project summary task.
By default, the project summary task is hidden for new projects. However, if you want
to see the project summary task, you can unhide it in the Gantt Chart view by
selecting the Format contextual tab, and checking the Project Summary Task check
box in the Show/Hide command group. Then, the project summary task appears as
the first task in the task list and Gantt chart.
Note: The project summary task is sometimes referred to as “Task 0.”
CREATING A TASK-BASED
SCHEDULE 47
2.3.04 Outline Numbers
Every new project that you create automatically contains a project summary task,
which is the main objective of the project plan. All new tasks that you add to the
project will be subtasks of the project summary task.
By default, the project summary task is hidden for new projects. However, if you want
to see the project summary task, you can unhide it in the Gantt Chart view by
selecting the Format contextual tab, and checking the Project Summary Task check
box in the Show/Hide command group. Then, the project summary task appears as
the first task in the task list and Gantt chart.
Note: The project summary task is sometimes referred to as “Task 0.”
CREATING A TASK-BASED
SCHEDULE 48
2.3.04 Outline Numbers
When you are working with a complex project that has multiple summary tasks and
subtasks, you might find it helpful to see the outline numbers that Microsoft Project
can automatically assign to each task. Microsoft Project uses a decimal hierarchy
numbering scheme to show the sequence and level of the summary tasks and their
subtasks.
By default, outline numbers are hidden, but you can unhide them in the Gantt
Chart view by selecting the Format contextual tab and checking the Outline
Number checkbox in the Show/Hide command group.
CREATING A TASK-BASED
SCHEDULE 49
2.3.05 Milestone Tasks
You can create a new milestone using the Insert Milestone command in the Insert
command group on the Task tab, or you can insert a new task in the Task
Entry table and set the duration to zero and Microsoft Project will automatically
change it to a milestone task. You can convert an existing regular task into a
milestone by viewing the task’s information and checking the Mark task as
milestone check box on the Advanced tab of the Task Information dialog box. In
this case, the milestone task will retain its duration and resources.
CREATING A TASK-BASED
SCHEDULE 50
2.3.06 Task Notes
As needed, you can use the Notes tab of the Task Information dialog box to
capture important information about a task that might be useful.
CREATING A TASK-BASED
SCHEDULE 51
2.3.06 Task Notes
There are three ways you can add notes for your task:
You can type text directly into the Notes field.
You can copy text or graphics from a source document (such as Microsoft®
Word®, Excel®, or PowerPoint®) and paste them into the Notes field.
A task that has notes associated with it will be indicated by a note icon in
the Indicators column in the task list.
CREATING A TASK-BASED
SCHEDULE 52
2.3.07 How to Create a Work Breakdown Structure
CREATING A TASK-BASED
SCHEDULE 53
2.3.07 How to Create a Work Breakdown Structure
Here are the general steps you will use to In the Task Entry table, replace the
create a work breakdown structure. All of text <New Summary Task> with your
the steps assume that you are in the Gantt desired name for the summary task.
Chart view. Indent Tasks
Rearrange Tasks To indent tasks so they are subtasks of
To rearrange tasks on the task list: a Summary Task:
Select the task(s) you want to move. In the Task Entry table, select the task
Drag and drop the task(s) to their new numbers or task names of the tasks that
location. you want indented.
Insert a Summary Task In the Schedule group of the Task tab,
To insert a summary task: select the Indent Task button.
In the left pane, select the row(s) of one
or more tasks that you want to become
subtasks of the new summary task.
On Task tab of the ribbon, select Insert
Summary Task.
CREATING A TASK-BASED
SCHEDULE 54
2.3.07 How to Create a Work Breakdown Structure
CREATING A TASK-BASED
SCHEDULE 55
2.3.08 Activity – Creating a Work Breakdown Structure
Indent tasks so they are subtasks of a Show the Project Summary Task.
summary task. On the ribbon, select
Select the tasks named Identify the Format tab.
budget requirements and Obtain In the Show / Hide group, select
launch budget approval. the Project Summary Task check
In the Schedule group of box.
the Task tab, select Indent Task. Save the file
Add text to a task note. as My_Trey_Slide_Presenter_Tasks_a
Select the Engineering task. .mpp
In the Properties group of
the Task tab, select Information.
In the Notes area on the Notes tab,
enter Engineering has its own set
of plans that it will follow and
select OK.
CREATING A TASK-BASED
SCHEDULE 57
2.3.09 Schedule Options
Throughout your project planning, you may need to add tasks to your project plan to
account for the work that needs to be completed—especially if you used a template
as a basis for your plan and now you need to modify it to include your project’s
specific details. Before you insert any new tasks into an existing task list, it’s a good
idea to modify the schedule options for the project to ensure that new tasks are
properly scheduled.
You can access these options by selecting the File tab, and then
selecting Options on the Backstage; in the Project Options dialog box, select
the Schedule tab. In the New tasks created field, make sure that Auto
Scheduled has been selected in order to automatically calculate the task’s
parameters in the schedule. Then, make sure that the Autolink inserted or moved
tasks check box is checked, so that Microsoft Project will automatically manage the
dependencies between the tasks for you.
CREATING A TASK-BASED
SCHEDULE 58
2.3.09 Schedule Options
CREATING A TASK-BASED
SCHEDULE 59
2.3.10 Insert Tasks
You can insert new tasks directly in the Task Entry table in the Gantt
Chart. The key is to select the task directly below the point where you want
to place the new task; then, select the Insert Task command from
the Tasks command group on the Task tab and the new task will be
inserted directly above the task you selected. By default, the new task is
named <New Task> and you can rename it with a more descriptive title
directly in the Gantt Chart or in the Task Information dialog box.
If the task that you selected when adding the new task was part of a path,
the new task will be automatically inserted into the path. The selected task
will become the successor of the new task, and the task that was previously
the predecessor of the selected task will now become the predecessor of
the new task.
Other than that, the new task will not inherit any other characteristics of the
selected task. You will still need to set the task duration, assign resources to
it, and make any other adjustments to the task information as is appropriate.
CREATING A TASK-BASED
SCHEDULE 60
2.3.11 Insert Task Options
In addition to adding a task to the task list, there are other options that you
can choose from the Insert Task command drop-down while in the Gantt
Chart view:
Select Recurring Task to insert a repeating task, such as a task that you
want to occur on a certain day each month.
Select Blank Row to insert blank rows into your task list to separate tasks
from one another.
Select Import Outlook Tasks to convert a task that was created in
Microsoft Outlook into a Microsoft Project task.
CREATING A TASK-BASED
SCHEDULE 61
2.3.12 Inactive Tasks
An inactive task is a task that is no longer needed in the project plan, but it does not
affect resource availability or the project schedule. When you make a task inactive,
the task stays in the task list but the text is greyed out and crossed out in
strikethrough format.
You can mark a task as inactive either in the Task Information dialog box or by
selecting the Inactivate command from the Schedule command group on
the Task tab.
It is a best practice to inactivate tasks, rather than delete them, to ensure that
your project plan accurately reflects all of the original tasks in the schedule
while accounting for any changes that were made as the project moved from
the planning phase into execution.
CREATING A TASK-BASED
SCHEDULE 62
2.3.13 The Update Project Dialog Box
If and when a delay occurs in your project, it is likely that you will
need to reschedule tasks in the project plan. Fortunately, Microsoft
Project can automatically reschedule any remaining work based on
the changes you make to a task or tasks. To do so, select the tasks
you need to reschedule, and use the Update Project command to
specify when you want to reschedule the uncompleted work for
those tasks.
For example, you may have an unforeseen power outage that stops
all work being done on the hardware systems for a software system
upgrade. You can select the tasks that are affected in the project
plan, and then specify the date after which that work can resume in
the Reschedule uncompleted work to start after field in
the Update Project dialog box.
CREATING A TASK-BASED
SCHEDULE 63
2.3.13 The Update Project Dialog Box
CREATING A TASK-BASED
SCHEDULE 64
2.3.14 Splitting Tasks
When you assign a resource to a task in the project plan, Microsoft Project
assumes that person will be working on that task until it is complete. In
reality, however, this is not always the case: the assigned resource may
need to work on a task in two or more chunks of time. This is called splitting
a task.
In Microsoft Project, you can manually split a task by selecting the Split
Task command from the Schedule command group on the Task tab. Then,
in the Gantt chart, select the task bar for the task that needs to be split and
drag the split piece to the date in the future when the second chunk of work
will be performed. Microsoft Project will connect the two halves of the split
task with a dotted line in the Gantt chart.
CREATING A TASK-BASED
SCHEDULE 65
2.3.14 Splitting Tasks
CREATING A TASK-BASED
SCHEDULE 66
2.3.15 The Move Command
If you need to move certain tasks forward or backward in your project schedule or
reschedule a task when resources are available, you can easily do so using
the Move command. Simply select the task that needs to be changed, and then
select how it should be moved or rescheduled from the Move command drop-down
from the Tasks command group on the Task tab.
CREATING A TASK-BASED
SCHEDULE 67
2.3.16 HOW TO MODIFY A WORK BREAKDOWN
STRUCTURE
CREATING A TASK-BASED
SCHEDULE 68
2.3.16 HOW TO MODIFY A WORK BREAKDOWN
STRUCTURE
Here are the general steps you will use to Insert a New Task into an Existing Task
modify a work breakdown structure. List
Set Schedule Options for Automatic To insert a new task into an existing task
Management list:
To set the scheduling options so that Select the task below the row where you
Microsoft Project helps you manage the want to insert the new task.
schedule for modified and inserted On the Task tab, Insert Task.
tasks: In the Task Entry table, update the
In the File tab, select Options. fields for the new task as needed.
In the Project Options dialog box, Mark a Task Inactive
select the Schedule tab. To mark an existing task as inactive:
In the Scheduling options for this Select the task that you want to mark
project section, in the New tasks inactive.
created drop-down list, ensure
that Auto Scheduled is selected, and In the Schedule group of the Task tab,
ensure that the Autolink inserted or select Inactivate.
moved tasks check box is checked. In the Task Entry table, verify that the
task appears crossed out.
CREATING A TASK-BASED
SCHEDULE 69
2.3.16 HOW TO MODIFY A WORK BREAKDOWN
STRUCTURE
Mark a Task Inactive Manually Split a Task
To mark an existing task as inactive: To control how a task is split:
Select the task that you want to mark inactive. Select the task that you want to split. Ensure
In the Schedule group of the Task tab, that you can see the task in the Gantt chart
select Inactivate. pane and set the zoom level so that you can
In the Task Entry table, verify that the task see the entire task.
appears crossed out. In the Schedule group on the Task tab,
select Split Task.
Reschedule Incomplete Work
In the Gantt Chart pane, select the place in
To reschedule incomplete work:
the bar for the task where you want to create
Select the tasks for which you want to the split, then drag the split bar to the new
reschedule incomplete work. starting date.
In the Status group of the Project tab, Move a Task
select Update Project.
To move a task:
In the Update Project dialog box, select
the Reschedule uncompleted work to start Select the task that you want to move.
after radio button and then select the date on In the tasks group of the Task pane,
which you want the work to resume. select Move.
Select the Selected Tasks radio button, and In the menu, select how you want to move the
Select OK to apply the changes and close task.
the Update Project dialog box.
CREATING A TASK-BASED
SCHEDULE 70
2.3.17 ACTIVITY - MODIFYING A WORK BREAKDOWN
STRUCTURE
To complete this lab, you must first Schedule folder.
download the following data Insert a new task into the existing task
file: Trey_Slide_Presenter_Tasks_b(1).mpp list.
Scenario Select the Phase 3 - Execution task
Your team has made progress on the Work name.
Breakdown Structure, by adding durations and In the Insert group on the Task tab,
links to the tasks. You need to make some select Task.
changes to your Work Breakdown Structure, Note: The new task will appear
as it is still a work in progress. You will add a immediately above the task Phase 3 –
new task in the middle of the project, mark a Execution, and it will be linked in
task inactive because you do not think you will a Finish-to-Start relationship with Plan
need to perform it, split a task into two team staffing to support sales
separate pieces, and move a task forward by a goals and Evaluate market and refine
day. You also want to learn how to reschedule messaging.
incomplete work, although you will not need to Replace the <New Task> placeholder
do this until the project is underway. with the text Detailed Planning
Open the file. Complete
Open the file Set the Duration to 0 days, to make the
named Trey_Slide_Presenter_Tasks_b( task a milestone.
1).mpp from the Create a Project
CREATING A TASK-BASED
SCHEDULE 71
2.3.17 ACTIVITY - MODIFYING A WORK BREAKDOWN
STRUCTURE
Mark the Define internal communication presentation task.
needs task as inactive. In the Tasks group of the task tab,
Select the Define internal select Move Task, and then select Move
communication needs task. Task Forward 1 day.
On the Schedule group on the Task tab, Save the file
select Inactivate. The task name and as My_Trey_Slide_Presenter_Tasks_b(1).m
associated Gantt bar will have a strikeout pp
line through them, and the linking of the Reschedule incomplete work.
tasks will be updated to reflect that this Select the Define sales
task will not be done. presentation task.
Manually split the Obtain launch budget In the Schedule group of the Task tab,
approval task to have a one-day delay that select 50%. The Gantt bar for the task
will occur two days after the task begins. will be dark blue for 2 days (50% of the
Select the Obtain launch budget duration).
approval task. In the Status group of the Project tab,
In the Schedule group of the Task tab, select Update Project.
select Split task. In the Update Project window, select
In the Gantt Chart pane, select the place Reschedule uncompleted work to start
in the bar where the split will after and enter 8/25/2016. The task will
occur, Friday 8/12/2016. then appear with a one-day split.
Move the Define sales presentation task. Close the file and do not save changes.
Select the Define sales CREATING A TASK-BASED
SCHEDULE 72
2.4 MANAGING MULTIPLE PROJECTS
There may be times, when you need to manage multiple projects that
are dependent on each other. Perhaps, the task in the project plan
directly affect tasks in another project plan.
CREATING A TASK-BASED
SCHEDULE 73
2.4.01 LINKED PROJECTS
CREATING A TASK-BASED
SCHEDULE 74
2.4.02 MASTER PROJECTS AND SUBPROJECTS
CREATING A TASK-BASED
SCHEDULE 75
2.4.02 MASTER PROJECTS AND SUBPROJECTS
CREATING A TASK-BASED
SCHEDULE 76
2.4.03 INSERT SUBPROJECT OPTIONS
When you select the Insert Subproject command, the Insert Project dialog
box opens.
CREATING A TASK-BASED
SCHEDULE 77
2.4.03 INSERT SUBPROJECT OPTIONS
From here, you will navigate to and select the file that you want to insert as a
subproject, and then choose from one of three options for establishing a link
between the subproject and master project files.
Option Description
Link to Establishes a two-way link between the
project and Insert subproject and the master project.
Changes made in either file will be updated
in the other file.
CREATING A TASK-BASED
SCHEDULE 78
2.4.03 INSERT SUBPROJECT OPTIONS
From here, you will navigate to and select the file that you want to insert as a
subproject, and then choose from one of three options for establishing a link
between the subproject and master project files.
Option Description
Insert Does not establish a link between the
subproject and master project. Instead, a
copy of the subproject data is simply
inserted into the master project file, and
changes made in either file will not be
updated in the other file.
CREATING A TASK-BASED
SCHEDULE 79
2.4.04 DEPENDENCIES BETWEEN LINKED PROJECTS
When subprojects are linked to a master project, you can establish dependencies
between the tasks of the subprojects or between the tasks of the master project and its
subprojects. These relationships are established exactly as they are done for an
individual project, using the Link the Selected Tasks command. However, if you link
tasks between tasks in different projects, it is important to remember that changes you
make to a linked task will affect its successors—even if those successors exist in
another project file.
CREATING A TASK-BASED
SCHEDULE 80
2.4.05 HOW TO LINK PROJECT PLANS
CREATING A TASK-BASED
SCHEDULE 81
2.4.05 HOW TO LINK PROJECT PLANS
Here are the general steps you will take Create a Dependency Between
to link projects to one another. Tasks in Different Subprojects
Insert a Subproject into a Master To create a dependency between tasks
Project in different subprojects:
To insert a subproject into a master project: Make sure both subprojects are inserted
into the master project.
Make sure you are in a task-related
view. Expand both subprojects to display the
tasks comprising each project.
In the Insert group of the Project tab on
the ribbon, select the Insert Select the task in one subproject that
Subproject button. you wish to be the predecessor.
Navigate to the location of the While holding the Ctrl key, select the
subproject file and select it to insert it. task in the other subproject that you
wish to be the successor.
In the Schedule group of the Task tab
on the ribbon, select the Link the
Selected Tasks button.
CREATING A TASK-BASED
SCHEDULE 82
2.4.06 ACTIVITY - LINKING PROJECT PLANS
You have decided to use a contractor for the Set the Task Mode so all new tasks are
engineering phase of your Trey Slide Presenter auto scheduled.
project, and the Trey Research PMO has made On the Status Bar below the Gantt
available a Microsoft Project file that contains the Chart, select New Tasks: Manually
steps to select such a contractor. You want to Scheduled and change it to New
incorporate these steps into your project, and you Tasks: Auto Scheduled.
decide to create a master project that includes two Show the Project Summary Task.
sub-projects, the slide presenter project and the
On the ribbon, select
contractor selection project.
the Format tab.
Create a new blank project and set it up In the Show/Hide group, select
for your use. the Project Summary Task check
From the New page, select Blank Project. box.
Set the project’s scheduling mode and start Save the file in the a folder, and name
date. it My_Trey_Slide_Presenter_with_Cont
From the Project tab on the ribbon, ractor(1).mpp
CREATING A TASK-BASED
SCHEDULE 83
2.4.06 ACTIVITY - LINKING PROJECT PLANS
Insert the first subproject into the master the Project tab, select Subproject.
project. From the Create a Project
Select the Task Name cell in the first Schedule folder, insert the
blank row below the Project file Contractor_Selection(1).mpp.
Summary task. Select
CREATING A TASK-BASED
SCHEDULE 84
2.4.06 ACTIVITY - LINKING PROJECT PLANS
CREATING A TASK-BASED
SCHEDULE 85
2.5 SUMMARY
The most important components of any project plan are the specific tasks,
that must be completed in order to achieve the desired outcome for a
project. As the project manager it's your responsibility, to create and
manage these tasks, and organize them into a structured time-bound
schedule, that is achievable.
In this module, you have performed all the tasks necessary to create a task
balanced schedule.
You created a project schedule made up of tasks in their relevant details.
You created and modified at work breakdown structure as a way to organize
your tasks in a manageable manner and you linked related project plans to
help you manage multiple projects simultaneously.
By performing all these tasks in Microsoft project, you'll be able to create a
project schedule, that reflects the specific parameters of your project tasks
and time frames to help ensure a successful execution and completion.
CREATING A TASK-BASED
SCHEDULE 86
2.6 MODULE ASSESSMENT TEST 2
Complete the following multiple choice assessment questions to test your knowledge
about the concepts you just learned.
Complete the following multiple choice assessment questions to test your knowledge
about the concepts you just learned.
# QUESTION ANSWER PASS FAIL
(1) (0)
3 Which of the following terms refers to the latest
possible time by which a task, phase, or project
must be completed?
A. Duration
B. Constraint
C. Deadline
D. Milestone
4 What is the name of the Microsoft Project feature
that allows you to enter tasks with or without
specific task information for durations, start dates,
or end dates, in order to create a schedule that
documents estimations and assumptions for a
project?
A. Manually Scheduled Tasks
B. Auto Scheduled Tasks
C. User-Controlled Scheduling
D. User-Defined SchedulingCREATING A TASK-BASED 88
SCHEDULE
2.6 MODULE ASSESSMENT TEST 2
Complete the following multiple choice assessment questions to test your knowledge
about the concepts you just learned.
# QUESTION ANSWER PASS FAIL
(1) (0)
CREATING A TASK-BASED
SCHEDULE 89
2.6 MODULE ASSESSMENT TEST 2
Complete the following multiple choice assessment questions to test your knowledge
about the concepts you just learned.
# QUESTION ANSWER PASS FAIL
(1) (0)
7 When you are inserting a subproject into a master
project, which of the following options would you
select to establish a two-way link between the two
projects, so that changes made to the subproject
will be reflected in the master project and vice
versa?
A. Link the Selected Tasks
B. Link to project and Insert
C. Link to project and Insert Read-Only
D. Insert
8 Which of the following terms refers to a specific
point in your project, such as important
deliverable or end of a phase?
A. Milestone
B. Summary task
C. Deadline
D. Linked task CREATING A TASK-BASED
SCHEDULE 90
2.6 MODULE ASSESSMENT TEST 2
Complete the following multiple choice assessment questions to test your knowledge
about the concepts you just learned.
# QUESTION ANSWER PASS FAIL
(1) (0)
CREATING A TASK-BASED
SCHEDULE 92