Professional Documents
Culture Documents
2水准测量的成果处理11
2水准测量的成果处理11
HPC=HA+R1
R4
R2
R1
R3
C
B
HPC=HB+R3
RLA
In order to obtain the elevation of point B
(HB) , staff reading R2 must be subtracted
[səb‘trækt]( 减去 ) from the elevation of the
collimation level , so
HB=collimation level-R2=(HA+ R1)- R2= HA+
(R1-R2)
In this case ,the direction of leveling is
from A to B and R1is called a back sight
reading (BS) .
Since reading R2 is taken with the level
facing in the direction from A to B, it is called a
fore sight reading (FS), the height change
between A and B, both in magnitude
['mægnɪtjuːd] and sign, is given by the
difference of the staff reading taken at A and
B.
Since R1 is greater( 大于 ) than R2 in this
case, (R1 - R2) is positive and the base of the staff
(尺底) has risen in moving from A to B.
because (R1 - R2) is positive , so it is known
as a rise.
now ,The level is moved to a new position I 2 ,
so that the elevation of point C can be found.
At position I2 ,Reading R3 is first taken
with the staff at point B ,Reading R3 is called a
back sight reading and the fore sight R 4 is
taken with the staff at C.
HPC=HA+R1
R4
R2
R3
C
B
HPC=HB+R3
at point B, both a FS and a BS have been
recorded consecutively, each from a different
instrument position and point B is called a
turning point (TP).
From the staff reading taken at I2, the elevation
of C is calculated from
HC=HB+(R3-R4)
The height difference between B and C is
given both in magnitude and sign by (R3-R4),
in this case , (R3-R4) is negative [‘negətɪv] (
负的 ) since the base of the staff has fallen
from B to C. this time, the difference of the
staff reading is known as a fall (下坡) .
from the above, it can be seen that when
calculating a rise or fall, this is always given by
(back sight-fore sight).
If this is positive, a rise is obtained and if
negative, a fall is obtained.
In practice , when the instrument has been
set up, a BS is the first reading taken and it is
always to a bench mark. conversely [‘kɑnvɝsli] ,
a FS is the last reading taken at an instrument
position . Any reading taken between the BS and
FS from the same instrument position are known
as instrument sights (IS)( 中视 )
A more complicate leveling process is
shown in cross-section( 断面图 ) and plan (
平面图) in fig 4-19, in which an engineer
has leveled between two TBMs ( 水准点 ) to
find the elevation of points A to E. The
readings could have been taken with any
type of level and the field procedure to
determine the elevation is as follows.
(1) The level is set up at some conveninent
position I1,and a BS of 2.191m is taken to
TBM1, the foot of the staff being held on the
TBM and the staff held vertically.
( 2 ) The staff is then moved to points A
and B in turn and readings are taken.
These are intermediate [,ɪntə‘miːdɪət]
sights( 中视 ) of 2.505m and 2.325m
respectively.
( 3 ) owing to the nature of the ground ,
in order to reach D , A change point must
be used. therefore, a change point is chosen
at C (TP1)and the staff is moved to C and a
FS of 1.496m taken.
(4)When the staff remains at C, the instrument is
moved to another positions I2. a BS of 3.019m
is taken from the new level position to the staff
at turning point C.
(5) The staff is moved to D and E in turn and
reading of 2.513m(IS) and 2.811m(FS) are
taken where E is another TP2.
(6) Finally, the level is moved to I3, a BS of
1.752m taken to E and a FS of 3.824m taken
toTBM2.
The finally staff position is at a TBM, it is
most important that all leveling field work must
start and finish at a bench mark (始于和结
束) ,otherwise it is not possible to detect
errors in the leveling .( important)
前进方向 h5=+0.118
h4=+0.385
1.422 1.304
h1=-0.543 h3=+0.946 1.820 1.435
BMB
h2=+0.120 1.822 0.876
1.134 1.677
1.444 1.324 TP4
BMA TP3
TP2
TP1
Staff reading
初始归化
HPC (
Point No BS IS FS 高程 PL
m)
(m) (m) (m) (m)
A 2.505
B 2.325
C ( TP
3.019 1.496
1)
D 2.513
E ( TP
1.752 2.811
2)
TBM2 3.824
6.962 8.131
检核
fh =初始最后点 RL -已知最后点 RL = 48.704 - 48.710 =- 0.006m
Staff reading
改正后
初始归化
HPC ( 改正值 归化高
Point No BS IS FS 高程 PL
m) (m) 程 RL
(m) (m) (m) (m)
(m)
0.006
6.962 8.131
检核
During all leveling field work and at anyone
instrument position, we must follow a principle ”
step by step checked”.
Check method includes two kinds:
(1)
图形:水准测量实施与记录对照图
h5=+0.118
前进方向 h4=+0.385
1.422 1.304
h3=+0.946 1.820 1.435
h1=-0.543 h2=+0.120 BMB
1.822 0.876
1.134 1.677 1.444 1.324 TP4
BMA TP3
TP2
TP1
BMA 1.134
1
TP1 1.677 -0.543
TP1 1.444
2
TP2 1.324 +0.120
TP2 1.822
3 TP3 0.876 +0.946
表 2-2 双面尺法水准测量记录表
测站 点号 水准尺数
读数 高差 平均高差 高程 备注
后视 前视
1 BMC 1211(1) 0.625 (0.0000) 20.000
5998(2)
TP1 0826(3) 0.725 0.625
5273(4)
2 TP1 1554 1.243 (-0.001)
6241
TP2 0311 1.144 1.2435
5097
3 TP2 0398 -1.125 (0.001)
5158
BMD 1523 -1.024 -1.1245 20.744
6210
§4.5 assessment of leveling precision
3 BM
4
BMB
2.A connecting levelling route 3
BMA 2
1
1 、 A connecting leveling route( 附合 )
Leveling is carried out from a starting point
BMA , and then connecting into another point
BMB, the elevation of BMA and BMB are
known, the leveling route is called a connecting
leveling route as shown in Fig, 4-20.
A connecting levelling route
2
BMB
3
BMA 2
1
Theoretically [,θiə'rɛtɪkli] , the sum of
measuring every section height differences in a
route (hi) should equal to difference of
elevations between two bench marks( 水准
点 )of known, that is
Because of measuring errors, so
, the misclosure [,mis'kləuʒə] (闭
合差) for levelling is given by (4-9)
BM
3
4
4
How to calculate the the misclosure for this
leveling route??
Obviously, the misclosure in levelling(fh ) can
be written by fh =∑hi (4-10)
three types of leveling routes
1
BMA P
3 BMA
4
BMB
2.A connecting levelling route 3
BMA 2
1
3. An open-ended leveling route
Since lack of (缺乏) inner [ɪnə] checking
condition (内部的检查条件) for an open-ended
levelling route, so it is necessary to measure and
return to measure (往返观测) point p of
unknown( See Fig.4 - 22).
An open-ended levelling route
BMA
How to calculate the the misclosure for this
levelling route??
Therefore, the misclosure for levelling is given
by
to return
types of leveling routes:
open-ended leveling route
3 BM.A
4 BM.B
connecting leveling route 3
BM.A 2
1
Because the misclosure can assess [ə'ses] the
quality or precision of the levelling , it is usual to
check that the misclosure must be less than some
specified [‘spesifaid](规定的 ) value ,the
specified [‘spesifaid] value is called the
allowable misclosure ( 容许误差 ).
On construction sites (在建筑工地) and
other engineering projects, leveling is usually
carried out over short distances and it can
include a lot of instrument positions , the error
will increase!!
For this type of work, the allowable misclosure
for leveling is given by
fh-allowable
the units of the allowable misclosure is
millimetres (毫米) , m is a constant [‘kɒnst(ə)nt]
(常数) with units of millimetres and n is the
numbers of instrument positions (测站数) .
For construction leveling, the value of m
frequently used is +5 mm.
fh-allowable
When the misclosure [,mis‘kləuʒə] (闭合差)
obtained is compared with the allowable
misclosure and the misclosure is greater than the
allowable value, the leveling is rejected (不合格
的) and the leveling has to be repeated.
If the misclosure is less than the allowable
value, the misclosure should be equal
distributed (平均分配) [dɪ'strɪbjʊtɪd]
to every station positions, it is detail
discussed in the next section.
When assessing [ə'ses] the precision of any
levelling by this method, it may be possible for a
site engineer (现场工程师) to use a value of
m based on site conditions.
For example, for setting out earthwork
excavations( 对于放样土方开挖 ) the value of m
might be +30 mm ,but for setting out steel and
concrete structures (对于放样钢和混凝土结
构) , the value of m might be +3 mm.
Values of m may be specified [‘spesifaid] as
tolerances in contract ['kɒntrækt] documents (
合同文件) or where they are not given, may
simply be chosen by an engineer based on
experience.
4.6 Calculations of levelling
Because the errors always exist during levelling
process , when the number of the instrument
station increase, the errors also increase. although
the error is qualified ['kwɒlɪfaɪd] ( 合格 ) in each
station, but for the whole levelling route, the
errors value is possible greater than the allowable
value. So it is necessary for us to calculate the
levelling route misclosure at indoor.
For levelling, our aim is to calculate these
unknown points elevation .
But how to calculate unknown point
elevation??
Calculation process:
f h h测 h理
formula :
f h h测 h理 h测 ( H 终 H 始 )
three types of leveling routes
3.An open-ended levelling route
.A loop levelling route 2
1 2
1
BM
3 BM
4
BM2
2.A connecting levelling route 3
BM1 2
1
2. calculate allowable misclosure [,mis'kləuʒə]
国家四等水准测量
Ordinary levelling
mountain :
f h容 6 n mm
mountain :
f h allowable 12 n mm
f h容 40 L mm flat : f h容 20 L mm
flat :
H1 H A h1 v1;H 2 H1 h2 v2;
the open-ended levelling route :
H 2 H 1 h平 H 1 ( h 往 h 返 ) / 2
Example 4 -1 It is gives a practical example for a
connecting levelling route as shown in Fig. 4-23.
The point A and point E are the two temporary
[‘temp(ə)rərɪ] bench marks( 临时性水准点 )point,
their elevations: HA =89.763m,HB =93.504 m. The point
B, C and D are three unknown points ,we will determine
their elevations, the measuring height differences( 高
差 ) and numbers of instrument set-ups in every section
note in Fig. 4 - 23.
It is now desired to calculate elevations of unknown
points 1, 2 and 3.
B h2=-1.835
h1=+2.691
C h4=-0.827
n1=5 n2=5 h3=3.754
D HE = 93.504 m
HA =89.763m
n3=6 n4=3
Solution
The results in the field book have been
arranged and filled in Table 4-3 , and then
calculations should be carried out according to
the columns [‘kɔləm] (栏目) in the table.
(1) The sum of measuring height difference of
each section is calculated by
∑h = +2. 691-1.835+ 3.754- 0.827 = + 3.783
(2) The height difference of two known points is
HE - HA= 95.504- 89.763 =+3.741m
(3) The misclosure [,mis'kləuʒə] of levelling (fh)
is calculated by formula (4 -9) , that is
fh =∑h- (HE-HA) =+0.042m
hi-adj =hi-mea + vi
h1-adj = h1-mea + v1=+2. 691 - 0. 011 = + 2. 680m
Check condition:
(7) The adjusted elevation of points B to D are computed
point-by-point from starting point A.
Adjusted
measuring corrections
Numbers of height
height of height
point station difference H(m)
difference hi difference
setup hi - adj ( m
(m) vi ( m )
)
A ( TBM
89.763
1)
5 + 2.691 - 0.011 + 2.680
B 92.443
C 90.597
D 94.338
f h h测 h理 h测 ( H 终 H 始 )
2. calculate allowable misclosure [,mis'kləuʒə]
国家四等水准测量
Ordinary levelling
f 12 n mm
mountain :
f h容 6 n mm
mountain :h allowable
H1 H A h1 v1;H 2 H1 h2 v2;
the open-ended levelling route :
H 2 H 1 h平 H 1 ( h 往 h 返 ) / 2
Precise leveling
Precise leveling includes four grades ,the first
grade 、 the second grade, the third grade ,the
fourth grade leveling.
If the grade of leveling is higher, the error is
smaller and the accuracy is higher.
Following ,we will study the third grade
and fourth grade leveling.
( 一 ) applies : this method is suitable for flat area
during elevation control survey
(2) the accuracy of main technical requirements:
Table 1-3, the technical requirements in every instrucment station
(index 指标 )
( hred±0.100m )
要求 : Ⅲ 等≤ ±3mm, Ⅳ 等≤ ±5mm
what sign??
( 8 ) The average elevation difference =
Up Up dire
reading reading ctio The
se (m) (m) n K+ 黑 average
ct -红 elevation 备注
io fore sight (m
n Back sight distance m) differenc
distance ( m ) black Red
(m) face ( face (
(m)
m) m)
d(m) ∑di ( m )
rod1 (1
(1) (4) (3) (8)
# 4)
已知水准
rod2 (1
(2) (5) (6) (7) 点 BM1 的
# 3) ( 18 )
高程
back =30.867m 。
(1 (1 (1
Down
Down
readin Middle reading
reading
g(m
(m)
)
Back Fore
staff Up staff
Up
readin
reading direc
g
(m) tion
(m)
The
fore sight K+ 黑 average
sect Back sight -红 elevatio
distance 备注
ion distance ( m ) (m n
(m)
及 blackfa Red m) differen
ce face c (m)
尺 (m) (m)
号
d(m) ∑di ( m )
B-
2.837 0.381 2.661 7.35
rod1#
BM1 rod1#
F-
| 2.489 0.058 0.120 4.908 K1=4.687
rod2#
TP1 rod2#
back- K2=4.787
Down
Down
readin Middle reading
reading
g(m
(m)
)
Back Fore
staff Up staff
Up
readin
reading direc
g
(m) tion
(m)
The
fore sight K+ 黑 average
sect Back sight -红 elevatio
distance 备注
ion distance ( m ) (m n
(m)
及 blackfa Red m) differen
ce face c (m)
尺 (m) (m)
号
d(m) ∑di ( m )
B-
2.837 0.381 2.661 7.35 -2
rod1#
BM1 已知水准点
F-
| 2.489 0.058 0.120 4.908 -1 2.4415 BM1 的高程
rod2#
TP1 =30.867m 。
back-
34.8 32.3 2.441 2.542 -1
图
表
:
四
等
水
准
测
量
记
录
表
4.6 Calculations of levelling
一、 Height of collimation method (视线高法)
In using the height of collimation method,
the height of collimation is calculated from the
reading taken to a staff station of known elevation.
When the instrument is shifted, the height of
collimation will be changed. Table 4 -1 shows the
field book. for the levelling shown in Fig. 4-19.
The calculations in Table 4 -1 are using the
height of collimation method. The method is based on
the HPC calculated for each instrument position.
The computational steps are as follows.
(1)1f the BS reading taken to TBM1 is added to
the RL of this bench mark, then the HPC for the
instrument position I1will be obtained. This will
be 49. 873 + 2. 191 = 52. 064m and this is
entered in the HPC column on the same line as
the BS (2. 191).
(2)To obtain the initial reduced levels of A, B and
C the staff readings to those points are now
subtracted from the HPC. The relevant
calculations are
RL of A - 52.064 -2.505 = 49.559m
RL of B = 52.064 -2.525 = 49.739m
RL of C = 52.064 -1.496 =
50.568m .
(3) At point C, a change point, the instrument is moved
to position I2 and a new HPC is established. This
collimation level is obtained by adding the BS at C to
the RL found for C from I1..
For positionI2, the HPC is 50.568 + 3.019
=53.587m. The staff readings to D and E are now
subtracted from this to obtain their reduced levels.
(4) The procedure continues until the Initial RL of TBM2
is calculated. With the initial RL column in the table
completed, the following check can be applied.
∑BS -∑FS = LAST initial RL - FIRST RL .
that is
6. 962 -8. 131 =48. 704 - 49. 873=- 1. 169
Obviously, in this case the misclosure of
levelling is the difference between last initial RL
obtained from observations (48. 704m) and its known
value (48. 710m). Therefore the height misclosure fh can
be written :
fh = Last initial RL-Last known RL
= 48. 704 - 48. 710= -0. 006m
After the checking, the misclosure is distributed
according to apply an equal, but cumulative, amount of
the misclosure to each instrument position, the sign of
the adjustment being opposite to that of the misclosure.
Since there is a misclosure of -0. 006m
in this example a total adjustment of +0. 006m
must be distributed. As there are three
instrument positions, +0. 002m is added to the
reduced levels found from each instrument
position. The distribution is shown in the
adjustment column, in which the following
cumulative adjustments have been applied: Levels
A, B and C +0.002 m, levels D and E + (0.002 +
0.002) = +0.004m and TBM2 + (0.002 +
0.002+0.002) = +0.006m.
No adjustment is applied to TBMl since
this is temporary bench mark. The adjustments
are applied to the Initial RL values to give the
Adj ( adjusted) RL values in Table 4 -1.
4.6.2 The rise and fall method
If the level of one of the two points is known,
the level of the other can be found by adding the
level of known point and the height difference of the
two points. In levelling of one instrument position,
when the backsight reading greater than the
foresight reading, the height difference is positive, it
indicates a rise, but when the backsight reading less
than the foresight reading, the height difference is
negative, it indicates a fall.
The reduced levelof all points can be
obtained by continuously adding a rise ( or a fall) ,
this is called a rise and fall method.
Table 4-2 shows all the records for the levelling
shown in Fig. 4-19. All calculations will be carried
out by a rise and fall method.
( 1) From the TBMl to A there is a small fall. A BS of
2.191 m has been recorded at TBMl and an IS of 2. 505m
at A. So, for the fall from TBMl to A, the height
difference is given by (2.192 -2.505)=-0.314m. The
negative sign indicates a fall. -0.314m must be filled in
the relevant position of column named height difference.
(2) The procedure is repeated and the height difference from
A to B is given by (2. 505-2.325) = +0.180m.
The positive sign indicates a rise. +0.180m must be
filled in the relevant position of column named height
difference.
(3)The rise from B to C up to TPl is (2. 325-1.496) =
+0.829 m. The height change from C to D is (3.019-
2.513) = +0.506m. These data must be filled in the
relevant position of column named height difference.
(4) Such calculation is repeated until the height differences
of ever)r segment are calculated, and then check on the
arithmetic must be applied.
This check is