Professional Documents
Culture Documents
Linlin ZHANG
Department of Accounting
Beijing Jiaotong University
Cost Behaviour and Estimation
• Objectives
·Discuss why organizations need to estimate costs
·Identify different cost patterns
·Illustrate simple and multiple regression analysis
·Discuss account analysis and the engineering method
·Identify and discuss the effects of learming curves on cost
behavior
Cost Behaviour and Estimation
Cost Behaviour and Estimation
Cost Behaviour and Estimation
Cost Behaviour and Estimation
Cost
• direct and indirect costs ; period and product costs; relevant and irrelevant costs;
avoidable and unavoidable costs; sunk costs; opportunity costs; incremental and marginal
costs.
Cost pools
Cost object
Cost assignment Cause and effect
Cost driver
Cost patterns
Cost function
Relevant range
Cost Behaviour and Estimation
• We shall see that the cost collection system typically accounts for
costs in two broad stages:
Step costs
A cost that increases in steps as the amount of the cost driver volume increases
As activity increases to the next range, total cost steps up to the next level
Mixed costs
A mixed cost is a cost that has fixed and variable elements, such as a
contract mobile phone bill
Cost Behaviour and Estimation
Activity
Cost Behaviour and Estimation
Account analysis
Engineering method
Cost Behaviour and Estimation
Month Total Co sts Units
Examples January $ 6,720 1,280
February 7,260 1,810
March 7,270 1,620
April 11,060 2,830
May 12,580 3,630
June 8,660 2,610
July 8,580 2,460
August 9,550 2,640
September 13,050 3,620
October 11,060 2,840
Nove mbe r 7,320 1,820
December 7,370 1,650
January 6,790 1,260
February 7,480 1,850
March 6,990 1,710
April 11,400 2,940
Cost Behaviour and Estimation
Scatter graph
Cost Behaviour and Estimation
High-low estimates
Cost Behaviour and Estimation
Regression Analysis
A statistical method used to create an equation relating
dependent (or Y) variables to independent (or X)
variables
Data from the past are used to estimate relationships
between costs and activities
300
250
200
350
300
250
300
250
200 Outlier
350
300
250
400
350
300
250
Regression with
200 low R2 (close to 0)
The high value for R2 tells us that there is a very close match between the
calculated line and the actual data.
It also means that we have explained 93% of the variability of total costs.
We have a residual variability of 7% - whether this is significant will depend
on the circumstances and the costs associated with finding the other 7%.
Cost Behaviour and Estimation
• The intercept term should be used with caution to estimate fixed cost
Technologies
Cost Behaviour and Estimation
Regression analysis – Key considerations continued
• The intercept is likely to be outside the relevant range of observations as it
occurs at an activity level of zero
• It cannot be always assumed that the cost estimation errors are normally
distributed, independent and with constant variation.
• Objective: Relate costs and activity in the form of the general cost
equation: TC = F + VX
Divide the total variable costs for each cost driver activity by the total
number of cost driver units to obtain variable cost per unit
Divide the fixed costs by the number of time periods in the data
• Direct labour
− Analyze the kind of work performed
− Estimate the time required for each labour skill for each unit
− Use local wage rates to obtain labour cost per unit
• Direct material
− Material required for each unit is obtained from engineering drawings and
specification sheets
− Material prices are determined from vendor bids
• Overhead costs
− Obtained in a similar manner using a step-by-step analysis of the work
involved
Cost Behaviour and Estimation
Engineering Method
Advantages of the engineering approach
• Detailed analysis results in better knowledge of the entire process
• The method is used to estimate costs of new activities
• The three cost estimation methods all have benefits and drawbacks
• Regression and account analysis rely on past data
• The engineering method relies on present data
• No single method is best for all situations
• Better results are often obtained by use of several of the methods.
For example….
− Engineering estimates and account analysis may lead to the
establishment of logical, causal relationships between variables
− Regression provides a cost equation for the data points with statistical
measures of fit
− Relevance of the causal (not casual!) relationships is critical to the
success of the chosen method.
Cost Behaviour and Estimation
Effect of learning on cost behaviour
The example assumes that the first unit takes 100 hours to produce....
Cumulative Cumulative Total Cumulative Total
number of average time time average time per time
units per unit at unit at 60%
produced 80% learning learning
The example assumes that the first unit takes 100 hours to produce....
Cumulative Cumulative Total Cumulative Total
number of average time time average time per time
units per unit at unit at 60%
produced 80% learning learning
The example assumes that the first unit takes 100 hours to produce....
Cumulative Cumulative Total Cumulative Total
number of average time time average time per time
units per unit at unit at 60%
produced 80% learning learning
Total
number of average time time materials manufacturing overhead cost
units per unit at cost labour costs costs (at (£’000s)
produced 90% learning (at £25 per £15 per
hour) hour)
1 3,000 3,000 80,000 75,000 45,000 200
2 2,700 5,400 160,000 135,000 81,000 376
4
8
y = 3000 x 2 -0.152
The question states that the first unit takes 3000 hours to produce....
Cumulative Cumulative Total Direct Direct Variable
Total
number of average time materials manufacturing overhead cost
units time per cost labour costs costs (at (£’000s)
produced unit at 90% (at £25 per £15 per
learning hour) hour)
1 3,000 3,000 80,000 75,000 45,000 200
2 2,700 5,400 160,000 135,000 81,000 376
4 2,430 9,720 320,000 243,000 145,800 708.8
8 2,187 17,496 640,000 437,400 262,440 1,339.84
Note the difference in the per-unit average cost £200 for the first and £167.5 when
there are 8 units produced.
Cost Behaviour and
Estimation
Summary