IMPLEMENTATION OF SURYA

REGIONAL BULK WATER SUPPLY


SCHEME FOR WESTERN SUB REGION
OF MUMBAI METROPOLITAN REGION
(MMR)

11 August 2022

1
Surya Regional Water Supply Scheme

 Present water supply & treated Bulk Water Supply distribution from this scheme to Mira-Bhayander
and Vasai-Virar City Municipal Corporations are:

Proposed Supply from Surya


Sr. No. Beneficiaries
RWSS (MLd)

a. Vasai Virar City Municipal Corporation (VVCMC) 170

b. Mira Bhayander Municipal Corporation (MBMC) 218

c. 44 villages in Palghar District 15

TOTAL 403 (MLd)

Recently it is also agreed to provide 10 MLD of bulk water supply to Palghar Municipal Council by reducing
5MLD each from both the ULB’s quota.

2
Layout of Surya Regional Water
Kawadas
Pickup Weir
Surya Dam Supply Scheme
WTP & PS • Source : Surya Dam
NH – 8 Ghol Junction
Medhwankhind Tunnel (L • Intake : Kawadas Weir
= 1.7km,Dia 2.85m ID)
Surya River
• WTP : Suryanagar
NH-8

Pipeline • BPT: Suryanagar

• Raw & Clear Water Pumping


Vaitarna River
Main Intake to BPT :
D = 2235 mm, L= 2.3 kms
MBR at
Kashidkopar
(38 ML) • Gravity Main BPT to
Kashidkopar Junction :
D = 2235 mm, L= 55.5 kms
Vasai-Virar City Tansa River
• Gravity main from
Tungareshwar WLS Tunnel (L =4.8Km, Kashidkopar to Chene MBR:
Dia:2.85m )
D= 1829 mm , L = 22.8 km

Total Length of Gravity Main:


86.05 kms (including tunnel
Mira Bhayandar City MBR at Chene (45 ML) length)
Award of Contract

• Bid was invited on DBMOT basis due on 09.02.2017

• The lowest bid of M/s. Larsen & Toubro Ltd. with 17.54 % below the estimated
cost of Rs. 1611 Cr. i.e. for amounting to Rs. 1329.01 Cr. was accepted.

• Work order placed to M/s. Larsen & Toubro Ltd. on 04.08.2017

• Contract period – 34 months

• Operation & Maintenance period included in contract – 8 years from the date of
commissioning.
Bid Details:-

• Accepted Tender Cost:- 1329.01 Cr.


• Project Contractor’s :- M/s. Larsen & Toubro Construction, Chennai
• Project Consultants:- M/s. STC Consortium
• Contract period:- 34 months
• Date of Award of Contract :- 04.08.2017
• Date of Completion :- 03.06.2020
• Covid-19 Extension - I :- up to 04.12.2020
• Further Extension – II :- up to 15.04.2023
KEY COMPONENTS
Intake 707 MLd Upstream of Kawadas Weir
Raw Water Pumping Main 2.235 km 2235mmɸ
WTP 418 MLD Scope for Augmentation by 150 MLD
Clear Water Pumping Main 0.08 km 2235mmɸ
BPT (at WTP Premises) 1.08 ML
Clear Water Gravity Main
BPT to Kashidkopar 55.520 km 2235mmɸ (185 MLD)
Kashidkopar to Chene 22.845 km 1829mmɸ (218 MLD)
Tunnels
Length Diameter
Mendhwankhind 1.7 km 2.85 m
Tungareshwar 4.5 km 2.85 m
Vasai Creek Crossing 0.9 km 2.0 m
Kaman Creek Crossing 0.268 km 2.0 m
Master Balancing Reservoirs
Kashidkopar (VVCMC) 38 ML
Chene (MBMC) 45 ML
Cumulative Physical Progress
% of Cumulative Work Target for
S. No Activity Total Scope Unit
done Progress Testing & Commissioning

1 INTAKE STRUCTURE 1 No. 90% Oct-22

2 WATER TREATMENT PLANT 1 No. 82% Oct-22

3 TUNNEL - MENDHWANKHIND 1700 Rmt. 100% July-22

4 MS PIPELINE-2235 MM DIA 57870 Rmt. 92% (52978 Rmt) Oct-22

5 Kashidkopar MBR-38 ML 1 No. 23% Oct-22

6 TUNNEL – TUNGARESHWAR 4435 Rmt. 27% (1202 Rmt) Apr-23

7 MS PIPELINE-1829 MM DIA 22845 Rmt. 19% (4300 Rmt) Apr-23

8 Chene MBR-45 ML 1 No. 35% Apr-23


INTAKE STRUCTURE 3D Model

7
SITE PROGRESS - INTAKE
WATER TREATMENT PLANT 3D Model

9
SITE PROGRESS - WTP

10
SITE PROGRESS - PIPELINE
SITE PROGRESS – MENDHVAN TUNNEL (Completed)
SITE PROGRESS – TUNGARESHWAR TUNNEL
SITE PROGRESS – AT KASHIDKOPAR MBR
SITE PROGRESS – AT CHENE MBR
16