Surya Regional Water Supply Scheme of

MMRDA

Under AMRUT Yojana

Date :- 03.06.2021
Components Sanctioned Under AMRUT for MBMC
Total
Fund
Expenditure
Sr. Total Received
Components incurred
No Cost under
component
AMRUT
wise
Gravity Main from Kashidkopar Junction to
1 Chene MBR (Pipe diameter of 1829 148.28 100.00
mm*12.5mm with total length of 20.845 kms)
2 MBR at Chene (45 ML Capacity) 21.10 0.32
Raw water Pumping station Machinery
(Mechanical works, pumps valves and
3 31.30 8.65
equipment + Electrical Works in Sub-Station
(132 kV / 6.6 KV) and 6.6 kV /415 V)
Clear Water Pumping main (Pipe diameter of
4 2235mm*16mm with total length of 0.315 kms) 2.98 1.42
+ Water hammer control device for CWPM
5 BPT at Surya Nagar (1.035 ML Capacity) 1.09 0

Total 204.75 56.272 110.39


Note:- 4th Instalment for MBMC is received in the month of May 2021, yet to be updated in the total funds
Project components Under AMRUT Yojna for MBMC
Sr. Component Progress
No.
1. Gravity Main from - Fabrication of total length of pipeline is
Kashidkopar Junction to completed
Chene MBR (Pipe - Pipes are stacked in storage yard at Boisar
diameter of 1829 - Laying activities of pipeline in this stretch has
mm*12.5mm with total not started
length of 20.845 kms) - Laying activities of 1829 mm of pipeline is in
progress from Ghodbunder Junction to
Kashidkopar Junction
- Total Pipeline laid – 2.6 kms

Procurement made
1. All types of valves
2. Dismantling joints
3. Flange Adapters

Total Physical Progress :- 35 %


Total Cost Incurred:- 100 Crs
SITE PROGRESS – MS Pipeline – 1829 mm OD
(Scope: 20.845 kms)
MS PIPES STORED IN YARD
Project components Under AMRUT Yojna for MBMC

Sr. Component Progress


No.
2. MBR at Chene - Tree felling activities have been completed
(45 ML Capacity) - Being a forest area of SGNP, the matter of
dumping of excavated soil is been looked into
- The quarry identified by forest dept. for
dumping of excavated soil has private access
road in possession of Hon. High court
- Process of seeking permission from Hon. High
court is in progress

Procurement made
1. Valves
2. Dismantling joints

Total Cost Incurred :- 0.32 Crs.


Tree Cutting Completed at Chene MBR

Tree Cutting Completed Chene MBR


Project components Under AMRUT Yojna for MBMC
Sr. Component Progress
No.
3. Raw water Pumping Procurement made :-
station Machinery
(Mechanical works, pumps 1. V.T. Pump
valves and equipment + 2. Electrical Motor
Electrical Works in Sub- 3. Dual Plate Check Valve
4. Butterfly Valve with Electrical Actuator
Station (132 kV / 6.6 KV)
5. Sluice Valve
and 6.6 kV /415 V)
6. Air Valve
7. Sluice Gates
8. Stop Log Gates
9. Screens
10. HT Transformer (35%)

Total Physical Progress :- 43 %


Total Cost Incurred:- 8.65 Crs
Inspection of Valves & Actuators
Inspection of Sluice Gates & Actuators
Inspection of Dismantling Joints & Flange Adapters
Final Inspection of HT Transformers
Project components Under AMRUT Yojna for MBMC
Sr. Component Progress
No.
4. Clear Water Pumping - Fabrication of total length of pipeline is
main (Pipe diameter of completed
2235mm*16mm with - Pipes are stacked in storage yard at Boisar
total length of 0.315 kms) - Laying activities of pipeline in this stretch has
+ Water hammer control not started
device for CWPM
Procurement made
1. All types of valves
2. Dismantling joints
3. Flange Adapters

Total Physical Progress :- 40 %


Total Cost Incurred:- 1.42 Crs
Project components Under AMRUT Yojna for MBMC

Sr. Component Progress


No.
5. BPT at Surya Nagar (1.035 - BPT being a part of Water treatment plant,
ML Capacity) its construction will be started after
completion of initial works of piping with
erection of adjoining structures of WTP.

- Excavation activities of BPT are likely to


commence from the month of June 2021

Total Cost Incurred :- 0.32 Crs.


SITE PROGRESS - WTP
Name of Contractor :- M/s. L&T Ltd. Name of PMC :- M/s. STC Consortium Contractual End Date:- 15-Apr-2023

Excavation and Concreting works in Progress at WTP


SITE PROGRESS - WTP
Name of Contractor :- M/s. L&T Ltd. Name of PMC :- M/s. STC Consortium Contractual End Date:- 15-Apr-2023

Excavation and Concreting works at WTP