Surya Regional Water Supply Scheme of

MMRDA

Under AMRUT Yojana

Date :- 03.06.2021
Components Sanctioned Under AMRUT for VVCMC

Total
Fund
Expenditure
Total Received
Sr. No Components incurred
Cost under
component
AMRUT
wise

1 Intake Structure 14.04 5.72

Gravity Main from BPT to Kashidkopar


2 Junction (Pipe diameter of 2235 mm*12.5 353.18 306.19
mm with total length of 55.520 kms)

Gravity Main from Kashidkopar Junction to


3 Kashidkopar MBR (Pipe diameter of 1829 10.05 7.35
mm*12.5 mm with total length of 2 kms)

4 MBR at Kashidkopar (38ML Capacity) 21.76 0.35

Total 399.03 168.48 319.61


Project components Under AMRUT Yojna for VVCMC

Sr. No. Component Progress


1. Intake Works at - Earthworks of Intake structure is completed
Kawadas - Base Raft of Intake structure is constructed
- Construction of Sump wall concreting with
slip form method is in progress

Procurement made
1. Vertical Turbine Pumps (Six nos.)
2. Sluice Gates
3. Inlet Piping
4. All required Valves
5. Electrical Transformers

Total Physical Progress :- 35%


Total Cost Incurred:- 5.72 Crs
SITE PROGRESS - INTAKE

Intake location at
Kawadas

Aerial View
Intake Works
Project components Under AMRUT Yojna for VVCMC

Sr. No. Component Progress


2. Gravity Main from BPT - Total laying of pipeline completed – 27.5 kms
to Kashidkopar Junction - Sectional Hydro testing of pipeline length
(55.520kms) completed – 4.5 kms
- Inside Cement motor lining of pipeline
completed– 31 kms

Procurement made
1. All types of valves
2. Dismantling joints
3. Flange Adapters

Total Physical Progress :- 42 %


Total Cost Incurred:- 306.19 Crs.
SITE PROGRESS – MS Pipeline – 2235 mm OD
(Scope: 55.520 kms)

MS pipe laying activities of 2235 mm


within RoW of NHAI
MS PIPELINE PHOTOGRAPHS
Project components Under AMRUT Yojna for VVCMC

Sr. No. Component Progress


3. Gravity Main from - Fabrication of total length of pipeline is
Kashidkopar Junction to completed
Kashidkopar MBR - Pipes are stacked in storage yard at Boisar
(2 kms, Dia 1829mm) - Laying activities of pipeline in this stretch has
not started
- Laying activities of 1829 mm of pipeline is in
progress from Ghodbunder Junction to
Kashidkopar Junction
- Overall Pipeline laid of same dia – 2.6 kms

Procurement made
1. All types of valves
2. Dismantling joints
3. Flange Adapters

Total Physical Progress :- 5%


Total Cost Incurred:- 7.35 Crs.
SITE PROGRESS – MS Pipeline – 1829 mm OD
(Scope: 20.845 kms)
MS PIPES STORED IN YARD
Project components Under AMRUT Yojna for VVCMC

Sr. No. Component Progress


4. MBR at Kashidkopar - Works of construction of MBR cannot be
(38 ML) started due to severe opposition of villagers for
shifting of MBR subject to safety concern of
villages downstream
- The revised proposal of shifting of MBR site is
submitted to forest department and is in
process of approval
Procurement made
1. Valves
2. Dismantling joints

Total Cost Incurred :- 0.35 Crs.