You are on page 1of 175

SOUTHERN REGIONAL POWER COMMITTEE

BANGALORE

Minutes of the 32nd Meeting of


Protection Coordination Sub-Committee
of SRPC held on 29.05.2014
1 Introduction
The 32nd Meeting of Protection Coordination Sub-Committee (PCSC) was held on 29th
May 2014 in the Conference Hall of Southern Regional Power Committee, Bangalore.
The list of participants of the PCSC meeting is enclosed as Annexure - I.

Shri S. R. Bhat, Member Secretary i/c, SRPC welcomed the Members and the Participants
to the 32nd Meeting of the Protection Coordination Sub-Committee.

MS i/c briefed the members about the communication addressed to Hon'ble CERC in
respect of Phase-I of implementing recommendations of Protection Audit; based on
inputs received from the utilities. He also reminded the Members about the time line for
implementation of activities relating to Phase-II of the same i.e. 1st Sep, 2014. Bimonthly
report in this regard needed to be submitted to Hon'ble CERC. He urged the constituents
to kindly submit the inputs at the earliest, for further necessary action.

MS i/c also informed the Members about the completion of "Transmission line patrolling
guidelines" that had been prepared in consultation with the stake holders. The same had
been submitted to Hon'ble CERC and also posted in the SRPC website for compliance.

He observed that the load relief under UFR was lower than actually desired as observed
through average values visible through SCADA. Members were kindly requested to make
arrangements to ensure the desired load relief under UFR schemes, enabling the grid in a
secure manner.

MS i/c also informed the forum regarding the Sub Group meeting held on 28th May 2014
at SRPC to discuss issues raised by KSEB on account of SPS modifications of Sholapur-
Raichur 765 kV line proposed by NLDC. Many issues had been discussed and resolved
after deliberations. He proposed a Sub Committee to study and review the existing df/dt
settings – rate of decay, quantum of relief, contingency to be considered etc. Members
were informed about the Task Force report on "Power System Analysis under
Contingencies”. The issues addressed in the report needed to be deliberated in the next
PCSC meeting so as to decide the road map to accomplish the tasks given in the report.

MS i/c informed about the two Sub Group meetings of PCSC held in the month of May
2014. One meeting was held at NTECL-Vallur on 19th May 2014 in respect of pollution
related trippings of the lines in Vallur area (North Chennai); another meeting at MAPS-
Kalpakkam in respect of Unit-1 hunting observed on 20th May2014.

2 Confirmation of the Minutes of the 31st PCSC Meeting held on 29th April 2014
The Minutes of the 31st PCSC meeting were confirmed since no comments had been received
from the constituents.

3 Grid Disturbances (GD) in the Southern Region

3.1 Grid Disturbance at SEPL Unit-1, 2 & 3 on 22-04-2014

(i) Date and Time of event 22-04-2014 at 5:27 hrs


(ii) Location Simhapuri, Nellore ,AP
Plant and/or Equipment 400 kV SEPL Substation, SEPL
(iii)
directly involved
Running unit-1, 2&3 at SEPL tripped.
Reported Disturbance / Krishnapatnam-Nellore (AP) tripped at 5:27
(iv)
Fault
on Zone-2, Y-B-E fault.
(v) Generation Loss 450 MW
(vi) Duration of interruption 1 Hour 17 Minutes to 3 hour 20 Minutes
(vii) Category GD 1

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 2
Single Line Diagram

Deliberations:
• The following were noted about the trip event:
o Krishnapatnam – Nellore 1 (AP-Manubolu) line tripped in Zone-2 E/F at
Manubolu end only; carrier aided trip did not operate.
o At SEPL end, back up e/f protection operated and running units 1, 2, 3 tripped.
• SRLDC explained that as the generating units at Krishnapatnam are not in service there
is no source (i.e. V and I signals) to drive the distance relays at Krishnapatnam end
hence the tripping at one end only i.e. Manubolu; SRLDC informed that similar event
had taken place on 25th May2014 @ 17:03 hrs.
• KPCTL suggested for using "weak-infeed" logic for the line.
• SRLDC suggested that at SEPL, it is better to have IDMT characteristics for DEFR than
DMT and the relay has to be coordinated with zone-2 settings of the other lines.
• In the Meeting, it was agreed that AP may consider implementing "weak-infeed" or
other suitable logic in respect of Krishnapatnam-Nellore (AP - Manubolu) lines.

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 3
3.2 Grid Disturbance at BTPS Substation on 01-05-2014

(i) Date and Time of event 01-05-2014 at 21:28 hrs


(ii) Location Bellary, Karnataka
Plant and/or Equipment Running units-1&2 of BTPS ,KPCL
(iii)
directly involved
On observation, it was found that HV
Reported Disturbance / bushing of GT-B phase has flashover and got
(iv)
Fault fired resulting in failure of lightning arrestor
and bus post insulator stacks.
(v) Generation Loss 458 MW
(vi) Duration of interruption 14 Hours to 14 days.
(vii) Category GD 1

From the FIR, the following was noted:


• JSW line had tripped in Zone-1 fault.
• Other lines had tripped in Zone-4.

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 4
Single Line Diagram

Deliberations:

KPCL:
• B-phase bushing of GT of unit-1 got flashover and resulted in heavy neutral current
flowing in unit-2.
• Due to blast over the bushing, the lines were hand-tripped by the operator.
• On JSW line carrier was received from Jindal end.
JSW:
• BTPS-JSW line is a LILO line of 11 km length.
• Line auto reclosed at JSW end and normal carrier was sent to other end.
• Existing line settings are provided by KPTCL.
SRLDC:
• SRLDC agreed that the B-phase fault was cleared in time.
• Due to the fact that the line is short, POR (permissible over reach) scheme could be
implemented for distance protection.
• JSW end of BTPS-JSW line should have tripped in Zone-2 instead of Zone-1 and this
aspect needed review.
Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 5
• KPCL informed that no zone-4 tripping though the same had been mentioned in FIR.
Due to this contradiction, KPCL was requested to submit a detailed report pertaining to
the incident.

KPTCL:
• The time settings of PD (Pole Discrepancy) relay and A/R relay had to be checked and
reviewed at BTPS.

Recommendations
• KPCL was requested to submit the detailed analysis report of the incident within a
week's time.
• KPCL was requested to check & review the time settings of PD (Pole Discrepancy)
relay and A/R relay and the same shall be informed to PCSC forum.

3.3 Grid Disturbance at 400kV NLC TPS Substation on 15.05.2014

(i) Date and Time of event 15-05-2014 at 22:16 hrs


(ii) Location NLC TPS II , TamilNadu
Plant and/or Equipment 400kV NLC TPS II Substation, NLC
(iii)
directly involved
As reported bus bar protection got operated
Reported Disturbance / at Neyveli TS2-Exp due to failure string
(iv)
Fault insulator of Y-Phase quadruple bus and
failure of Pantograph isolator.
(v) Generation Loss Nil
(vi) Duration of interruption 1 Hour 4 minutes
(vii) Category GD 1

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 6
• From the FIR, it was noted that there was operation of bus bar protection of both buses
1 & 2 due to failure of string insulators that caused the quadruple bus conductors to fall
on the tubular bus bars of Pugalur-2 line and TS-2 tie line bay.
• The operation had also resulted in tripping of Pugalur-2 line, TS-2 tie line, GT1, and
GT2.
• There was also a tripping of TS-2 Expn – Trichy line due to suspected power swing
phenomenon.

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 7
Single Line Diagram

Deliberations:
SRLDC:
• Though the fault was cleared in time, tripping of TS2 – Trichy line on account of power
swing is not a desired operation.
• The programme for disc insulator replacement needed to be given to the forum.
• Disc insulators had to be replaced positively before COD of the generating unit.
NLC:
• NLC displayed photographs of the switchyard with the affected component.
• Line between TS2 Expn. and TS2 is a very small line of 1.3 km length.
• Around 5,200 disc insulators have arrived for replacement in the yard.
• Disc insulator replacement programme would be finalized after discussing with M/s
BHEL.

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 8
SRPC:
• BHEL could be impressed upon for expeditious replacement of disc insulators in the
affected area for early restoration.
Recommendations
• NLC was requested to take up the replacement of the disc insulators issue with M/s
BHEL expeditiously.

4 Grid Incidences (GI) in the Southern Region


The Grid Incidences that had occurred during March - April 2014 were discussed in the PCSC
meeting. The details (deliberations and recommendations) of the Meeting are enclosed
herewith as Annexure - II.

5 Compliance Measures with regard to orders of Hon’ble CERC

5.1 Petition No. 146/MP/2013 with I.A. 36/2013 Order Dt 20.02.2014

Petition No. Order Description Report to be Periodicity of


Order/ROP submitted Reporting to
Date by CERC
respondents.
Petition No. Accordingly, we direct To SRPC/ Phase I :
146/MP/2013 the respondents to SRLDC by 01.06.2014
with I.A. implement the works as
36/2013 mentioned in Phase-I and Phase II :
Phase-II by 1.5.2014 and Bimonthly status
O: 1.9.2014 respectively. report
20.02.2014
Petition No. Commission's directions SRPC/ As and when
146/MP/2013 and ensure compliance of SRLDC non-compliance
with I.A. Regulations 5.2 (r) of the occurs.
36/2013 Grid Code and report
instances of non- Could be done
O : 20.02.2014 compliance to the on monthly
Commission. basis.

Petition No. Provisions of Regulation SRPC/ As and when


146/MP/2013 5.2(e) of the Grid Code SRLDC action plan for
with I.A. and CEA Grid Standards. revival to be
36/2013 finalized.

O : 20.02.2014

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 9
Petition No. On this issue, we direct SR 01.06.2014
146/MP/2013 all RPCs to formulate Constituents
with I.A. patrolling
36/2013 protocol/guidelines by
1.6.2014.
O : 20.02.2014

Deliberations:
• In the PCSC meeting, timely compliance of the above was highlighted. Periodicity of
Reporting was also discussed and the constituents were requested to submit the progress of
implementation to SRPC and SRLDC as specified in the Hon'ble CERC Order dated 20th
February, 2014.
• Issue regarding non-furnishing of FIR/Trip Analysis Report, EL, DR, etc. was highlighted.
SRPC had taken up the issue under Clause 1.5 of IEGC vide letter dated 05.05.14 and
21.05.14. It was pointed out that the above reports were to be uploaded on SRLDC web
application within 24 hours as mandated in IEGC/CEA Regulations.
• It was informed to the PCSC forum that the Phase I Compliance status had been submitted to
Hon'ble CERC vide SRPC letter dated 26th May14 (Annexure III).

5.2 Petition No. 167/ Suo- Motu / 2012

Petition No. Order Description Report to be Periodicity of


Order/ROP submitted Reporting to
Date by CERC
respondents.
Petition No. RPCs shall ensure that SR As and when
167/Suo- the approved philosophy Constituents
Motu/2012 is adopted by all users.

O : 22.02.2014
Petition No. We direct ISTS licensees PGCIL & To be collected
167/Suo- to submit details of ISTS
Motu/2012 updated distance Licensee
protection relay setting of latest by
O : 22.02.2014 all inter-regional lines 04.04.2014
with POSOCO & RPCs.

Petition No. The Commission directs SLDCs To be followed


167/Suo- all SLDCs to
Motu/2012 install/activate sound
recording system in their
O : 22.02.2014 control rooms within
three months from the
date of issue of this
order.

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 10
Deliberations:
• In the PCSC meeting the timely compliance of the above was highlighted.
• Periodicity of Reporting was discussed and the constituents were requested to submit the
progress of implementation to SRPC and SRLDC as specified in the Hon'ble CERC Order
dated 22.02.2014.

5.3 Petition No. 263/MP/2012

Petition No. Order Description Report to be Periodicity of


Order/ROP submitted Reporting to
Date by CERC
respondents.
Petition No. SRLDC and SRPC of Certified -
263/MP/2012 implementation of copy sent to
quantum of relief by SR
O : 19.12.2013 AUFR as per table above constituents
and proper functioning of
df/dt relays within one
month of issuing this
order.
Petition No. SLDCs are directed to CERC Before
263/MP/2012 map these relays on the 19.04.2014
SCADA system within
O : 19.12.2013 three months of issuance
of this order.

SRPC/SRLDC shall
submit a compliance
report in this regard
within four months of
issuing this order.

Deliberations:
• In the PCSC meeting the timely compliance of the above was highlighted.
• The periodicity of Reporting was discussed and the constituents were requested to submit the
progress of implementation to SRPC and SRLDC as specified in the Hon'ble CERC Order
dated 19.12.2013.

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 11
6 Implementing / Reviewing the Special Protection Schemes (SPS)

6.1 Review of SPS : 765 KV Raichur Sholapur-Line modified logic- KSEB agenda

The issues raised by KSEB regarding implementing the 765 KV Raichur - Sholapur SPS
modified logic had been discussed in detail in the Sub Group meeting of PCSC held on
28.05.2014. The Minutes of the Sub Group meeting is enclosed as Annexure IV.

6.2 SPS for Kolar Hosur Line

Logic:
Contingency: One of 400 kV Kolar-Hosur D/C line trips and
flow on other Circuit > 850 MW
Action: Back down 500 MW import at HVDC Kolar and Shedding load in Tamil
Nadu as per Trip Signal 2.

Deliberations
• It was informed that the SPS had been discussed in the OCC meeting.
• SRTS-II, PGCIL informed that the SPS would be implemented after discussing the financial
issues of SPS in the Commercial Sub Committee.
• KSEB requested SRLDC to furnish the details of Loads identified for tripping while
implementing the SPS.

6.3 SPS for PGCIL 400 KV Mysore and 400 KV Kalavindapattu S/S

Deliberations (as discussed in 94th OCC)


• It was informed that the above SPS issues had been discussed in the 94th OCC.
• It was agreed in the 94th OCC meeting to implement the SPS for Mysore ICTs by
PGCIL and the quantum of relief would be given by SRLDC.
• Loading would be considered as 110% for alarm and 130% for trip. The ratio (flow on
Kadakola - Kaniampetta & Drawal from Mysore ICTs) of loads to be shared between
Karnataka and Kerala would be finalized by SRPC secretariat based on the one year
data.
• The issue of extending the signal to Kaniampetta needed to be examined by PGCIL in
coordination with KPTCL/KSEB.
• In respect of the implementation of SPS for Kalavindapattu ICTs, TANTRANSCO had
pointed out that the loadings of ICTs were not as projected by PGCIL and needed
review. After deliberations, it was agreed that TANTRANSCO and SR-II PGCIL would
furnish the loading pattern of Kalavindapattu ICTs to assess the need for SPS.

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 12
6.4 SPS for Kudankulam Nuclear Power Station
Ø The issue was discussed in detail in the 29th PCSC and in the Special meeting held at SRPC
on 17.03.2014.
Deliberations
• KKNPP informed that instruction had been given to the operators in the control room to
carry out manual ramp down at the rate of 50 MW/minute. It would take around 5 to 6
minutes for 300 MW ramp down.
• SRLDC desired that ramp down be carried out automatically through soft logic.
Recommendation:

Ø The PCSC forum recommended for early implementation of automatic ramping of


KKNPP units.

7 Single Phase Auto Reclosing Facility for KKNPP Lines


The issue was discussed in the OCC, PCSC meetings and the Special Meeting held at
SRPC on 17th March 2014.
Deliberations
• It was informed that KKNPP had agreed in earlier Meetings to implement 3-phase auto
reclose with synchro check feature.
• KKNPP informed single phase auto reclose feature is under implementation in Rajasthan
Atomic Power Station in NR.

PCSC Deliberations
Ø The PCSC forum advised NPCIL, KKNPP to implement the Single Phase Auto Reclose
Scheme at the earliest and the same be communicated to the forum with in a week's
time.

8 Status of Pending Protection issues


Pending protection issues were discussed in the 32nd PCSC Meeting and follow up details are
enclosed as Annexure –V.

9 Phasing of Implementation of Protn. Audit Recommendations


The implementation of the Protection Audit recommendations needed to be as per the Hon'ble
CERC directions (covered under item 5.1).

10 Tripping Incidents in the Southern Region


Tripping incidents that had occurred in the Southern Region during the month of April - May
2014 were discussed in the PCSC. The PCSC forum requested the constituents to submit
/update the tripping details to SRLDC at the earliest.

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 13
11 The issue of quantum of df/dt relief in SR
In the 29th PCSC meeting SRLDC informed that the df/dt settings in the Southern Region
would be revised from the month April 2014 due to Synchronization of SR with NEW Grid.

Deliberations
• SRLDC proposed for the following df/dt settings in the SR.
• Stage-1 : 49.9Hz & 0.1 Hz/sec
• Stage-2 : 49.9Hz & 0.2 Hz/sec
• The detail as submitted by SRLDC / POSOCO is enclosed herewith as Annexure VI.
• The PCSC forum decided to discuss the issue in detail in Sub Group meeting / the next
PCSC.
12 Submission of completed dynamic study data
All SLDCs were requested to direct the embedded IPPs connected at 220 kV and above voltage
level to submit completed dynamic study format to SRPC, Secretariat.

Deliberations
• The pending units would be circulated in the agenda of the 33rd PCSC.

13 Informing configuration changes to PCSC forum


It was agreed in the PCSC forum that if any change in the system configuration ( i.e. addition
of Generating Units, Capacitors, Reactors, LILO etc) are to be highlighted and brought to
attention of PCSC forum during the PCSC Meetings . This would enable utilities to review
their protection settings if any change in the adjoining utilities to have better protection
coordination in the Southern Region.
All the constituents were requested to send the change in the configuration in their system if
any to the PCSC forum on a monthly basis.

14 Sub Group Meetings held at NCTPS Vallur and at MAPS,NPCIL


The Minutes of the Protection Sub Group Meeting t held at NCTPS, Vallur on 19th May 2014 is
enclosed herewith as Annexure VII.
Minutes of the Protection System Analysis (Expert) Group Meeting held at MAPS,NPCIL on
20th May 2014 is enclosed herewith as Annexure VIII.

15 Date & Venue of the next Meeting


The 33rd PCSC meeting would be conducted on 01.07.2014 (Tuesday) at SRPC
Bangalore.

*****

Minutes of the 32nd Protection Coordination Sub Committee Meeting held on 29.05.2014 Page 14
ANNEXURE I (1/5)
ANNEXURE I (2/5)
ANNEXURE I (3/5)
ANNEXURE I (4/5
ANNEXURE I (5/5)
ANNEXURE II (1/16)

I. Details of Grid incidents:


SN Details of Event Date & Reason 32nd PCSC Deliberations & Category
Time Recommendations
Tripping of HVDC 21-04-2014 Mal operation of LBB of Tie *
Gazuwaka pole-1 at 22:40 hrs breaker (Gazuwaka end) of HVDC
1 and 400kV Gazuwaka pole-1 and 400kV GI-2
Jeypore-Gazuwaka Jeypore-Gazuwaka line-1 caused
line-1 the tripping

*32nd PCSC Deliberations


• From the disturbance report it is noted that the east bus voltage went up to 407 kV and to control it Q50 CB of CWC23 filter bank was opened
manually which resulted in IDMT E/F protection operation of the filter.
• Next, BFR (Breaker Failure Relay) protection of Q50 CB of CWC23 filter operated and that led to opening of Q52 and Q50 CBs of CWD20 dia.

1
ANNEXURE II (2/16)

But, BFR of Q50 CB of CWD20 dia also operated that led to opening of Q51 CB of CWD20 dia and sending DT to remote Jeypore-I end for
tripping the line.
PGICL:
• Insulators are being cleaned once in six months.
• Even after opening the CBs Q50 and Q51 of CWD 20 dia, current conduction was there for 500 msec due to pollutants in the area, which could
have resulted in LBB operation of the Q50 CB.
SRLDC:
• When was the filter banks of the pole cleaned last time?
• A detailed report from PGCIL is required for analysis of the event.
NTPC:
• LBB (BFR) should also give re-trip command to the breaker.
PCSC Recommendations :
• PGCIL shall submit a detailed report on the tripping incident by 6th June, 2014.

Tripping of 400kV 24-04-2014 Line-1 Tripped at Satenapalli end APTRANSCO:


Srisailam- at 17:50 hrs due to the mal-operation of Main-
• The relay rebooting problem was there and
Satenapalli line- II distance relay and tripped at
the cards were changed.
1&2 Srisailam end on time delayed
over current protection. SRLDC:
2 • O/C protection to be enabled as back up for GI-2
Line-2 tripped at Srisailam end
bus bar (BB) protection till numerical BB
due to operation of residual over
is installed.
current protection
• For single phase auto reclose (AR), O/C
protection need not pick up and its operat-
ing time has to be increased.
400kV JSW-Guttur 29-04-2014at Y-phase to earth fault had On account of transient fault, JSW-Guttur line
3 line 15:38 hrs occurred in line. Reason for non/ was tripped at Jindal end by distance GI-2
unsuccessful auto reclose along
2
ANNEXURE II
with reason for operation of DEFR protection and at Guttur end by DEFR.
at Guttur needs further
SRLDC:
investigation
• Operation of DEFR not desired for
transient fault.
• Auto reclose (AR) not operating for DEFR
is a correct & desired operation.
• Un-matching magnitude of fault current of
11KA @ JSW end and 1.6 kA at Guttur
end could not be possible.
KPCL:
• Due to high fault resistance (i.e. 140 ohm
primary), the current was less (i.e. 1600A)
which could not invoke distance protection
(21).
• DMT with 1.5 sec (which is more than
zone-3 timing) is adopted for DEFR; had
IDMT been adopted, it would not have
tripped.
JSW:
• Fault current was 11 kA at Jindal end and
distance protection along with auto
reclose acted on the JSW-Guttur line.
400kV 22-04-2014 400kV Nellore (PG)-NPS line-2 • It was noted that 400 kV Nellore (PG) –
Krishnapatnam- at 5:27 hrs tripped on Zone-2. 400kV Bus-1 at NPS – 2 line tripped at Nellore (PG) end by
Nellore(AP) and Nellore tripped due to operation of LBB operation (of bus sectionalizer CB
4 400kV Nellore LBB of bus coupler breaker. with APTRANSCO system) and at NPS GI-2
(PG)-NPS line-2 end in zone-2 after receipt of DT.

3
ANNEXURE II
APTRANSCO:
• O/C and LBB did not operate at AP end.
• The bus sectionalizer CB is belonging to
AP.
SRLDC:
• Though CB tripped, it could not be
found in the event logger.
• PGCIL is required to revise the zone-2
settings at NPS.
PCSC Recommendation
Ø Both APTRANSCO and PGCIL have
to submit a detailed report by
10.6.2014.
Ø PGCIL is requested to revise the zone-
2 settings at NPS.
400KV 22-04-2014 Tripped at Nellore (A.P) end only SRLDC:
Krishnapatnam- at 5:27 hrs on Y-Phase to Ground fault.
• On the two feeders of Krishnapatnam-
Nellore(A.P) line-1
Manubolu (Nellore(AP)) implementing
5 GI-2
“weak-in feed logic” or energizing both the
feeders would be an appropriate action to
avoid one end tripping.
Tripping of 400kV 02-05-2014 Broken conductor feature in main- KPTCL:
NCTPS-Vallur 2 distance relay operated which
• Broken conductor detection and protection
line-2 resulted in tripping of line
is managed by undercurrent sensing
6 principle by electromagnetic relay or GI-2
negative phase sequence (NPS) sensing
principle by electromagnetic and
numerical relays.
• KPTCL employs only alarm for broken

4
ANNEXURE II
conductor protection.
• For generating stations, instead of line
NPS, generator NPS could be employed for
broken conductor detection.
TANTRANSCO:
• NPS setting is 20% and 5 sec time delay.
NTECL:
• NPS is not enabled at Vallur.
SRLDC:
• The practice of having only alarm for
broken conductor protection has to be
reviewed.
Tripping of 400kV 03-05-2014 Y-B phase fault had occurred in SRLDC:
Raichur(PG)-Gooty at 16:52 hrs 400kVRaichur-Gooty line-2.
• POR scheme is already there.
line-1&2, 400kV Distance protection over-reached
Raichur- • Time stamps of events in SOE sent to
at Raichur TPS end for 400kV
SRLDC is appeared to be incorrect.
Raichur(PG) line-1 Raichur-Raichur (PG) line-1 and
At Gooty end for 400kV Raichur- • SOE of Raichur is not being sent to
Gooty line-1. SRLDC.
• Even after 20 days of issuing notice,
7 PGCIL has not yet replied on testing the GI-2
lines.
PGCIL:
Gooty 1 & 2 lines were tested and corrected
on 11.5.2014 and Raichur lines would also be
tested .

5
ANNEXURE II
400kV 04-05-2014 Line tripped at Krishnapatnam end SRLDC:
Krishnapatnam- at 4:53 hrs only. D.R/ E.L were not furnished
• On the two feeders of Krishnapatnam -
Nellore line-2
Manubolu implementing “weak-infeed
8 GI-2
logic” or energising both the feeders
would be an appropriate action to avoid
one end tripping.
400/220kV ICT-2 05-05-2014 ICT-2 tripped on operation of over SRLDC:
at Satenapalli at 12:25hrs flux protection. D.R and E.L not
• Over flux protection should trigger the DR
furnished
and APTRANSCO should do wiring for
9 GI-2
DR triggering.
• DR and EL reports are to be submitted by
APTRANSCO
Tripping of 400kV 05-05-2014 Y-phase to earth fault had **
Kudankulam- at 23:47 hrs occurred near to Kudankulam. R-
Madurai line and B-Pole of breaker tripped
750ms after tripping of Y-Pole
10 GI-2
breaker at Madurai. The carrier
aided protection at Madurai end
and healthiness of PLCC link
needs to be tested
**
32nd PCSC Deliberations & Recommendations
• It is noted that there was a Y-phase to earth fault near KKNPP end and the line tripped in Zone-1 at KKNPP and Zone-2 in Madurai
end.
• Despite sending carrier from KKNPP, Madurai end did not receive it and without auto reclosing tripped in Zone-2.
NPCIL:
• There was no fault on the Madurai – Kudankulam line.
• After successful implementation of auto reclose for one and half breaker scheme at Rajasthan Atomic Power Plant, the same
would be implemented at KKNPP.

6
ANNEXURE II
PGCIL:
• If pressure in the CB is less than 32 kg/cm2, then there would be a lock out; if it is about 30.5 kg/cm2 then it would give auto
reclose lock out.
• There was a problem with pressure switch of the circuit breaker on the Madurai-Kudankulam line and it has been rectified.
SRLDC:
• Power plant like NLC’s TS2 has implemented auto reclose feature on the evacuating lines.
• The schedule for completing auto reclose feature at Rajasthan Atomic Power Plant and then at KKNPP shall be intimated by
NPCIL before next PCSC meeting.

Recommendations
Ø NPCIL is requested to inform the PCSC forum regarding the implementation schedule of auto reclose feautre at Rajasthan Atomic
Power Plant and KKNPP.

220kV 13-05-2014 Tripped at Chittoor end only on R- • ICT is in radial mode and at the tail end no GI-2
Chittoor - at 15:26 hrs Phase to ground, Zone-3 fault. (LV source to feed the fault.
11 Tiruvalum Rph CT of 100MVA-3 blasted at
Tiruvalum) TANTRANSCO:
220kV 14-05-2014 Reason to be furnished • At 110 kV system at Tiruvalum, there is no GI-2
Chittoor - at 11:23 hrs bus bar protection implemented.
12
Tiruvalum
APTRANSCO:
220kV 16-05-2014 Tripped at Chittoor • O/C setting of the line is 208 MW. GI-2
Chittoor - at 10:45hrs end due to operation
Tiruvalum of Over Load relay SRLDC:
• Delayed clearance of fault needs
13 explanation.
• As CT is on the bus side, the bus bar
protection should have operated.
• On 28.5.2014 there was a lock out of CB at

7
ANNEXURE II
Tiruvalum. Code was issued at 4.00 PM to
trip Chittoor- Tiruvalum line but until 7.00
PM the code was not executed. Without
tripping the line and continuing to feed the
load is not correct operation.

• TANTRANSCO shall furnish details for


non-execution of the code and direct its
operators to adhere to the code issued by
SRLDC.

II. Over voltage tripping


The following Over voltage Tripping incidents were discussed in the 32nd PCSC

Date &
S. No. Element Reason/ Deliberation
Time
400kV Srisailam-Mamidipally line 20-04-2014 @ 02:36hrs Line tripped on over voltage at Srisailam. No D.R
1 furnished

400kV Kaiga-Guttur line-2 04-05-2014 at 00:05 hrs Overvoltage operated at Guttur. No D.R furnished.
2

PGCIL:
• DR is not there and so events are not validated.
• Wiring to trigger DR for DT from remote end is to be done at KGS end.
KGS:
16 times DT was received from remote end and the line tripped on O/V during the month of May-2014.
KPTCL:

8
ANNEXURE II
The numerical relay on the line is Areva P437. Timing and pickup ratio in the relay would be tested.

3 400kV Srisailam-Mamidapalli-2 04-05-2014 at 00:14 hrs Line tripped on over voltage at Srisailam.

4 400kV Srisailam-Sarenapalli-2 04-05-2014 at 00:14 hrs Line tripped on over voltage at Srisailam.
400kV VTPS-Satenapalli line-2 04-05-2014 at 17:54 hrs Over voltage protection at VTPS end. D.R not
5
furnished
6 400kV Kaiga-Guttur line-1 05-05-2014 at 18:03 hrs Overvoltage operated at Guttur. No D.R furnished.

7 400kV Vijayawada-Gazuwaka line-1 05-05-2014 at 20:29hrs Drop of to pick up ration of relay to be checked
400kV Krishnapatnam-Nellore(AP)-2 06-05-2014 at 11:52 hrs Over voltage protection operated at Krishnapatnam.
8
No D.R furnished
400 kV Kaiga-Guttur- 2 08-05-2014 at 13:55 hrs Over voltage protection operated at Guttur. No D.R
9
furnished
400 kV Kaiga-Guttur-2 08-05-2014 at 17:30 hrs Over voltage protection operated at Guttur. No D.R
10
furnished
400kV Talaguppa-Hassan 09-05-2014 at 1:26 hrs over voltage protection had
11
Operated at Talaguppa end. No D.R furnished
400kV Srisailam-Mamidipally line-1 09-05-2014 at 02:53hrs Line tripped on over voltage at Srisailam. D.R not
12
furnished

III. Failure or non-operation of Auto reclose during transient fault


The following Tripping incidents due to non operation of Auto reclosed were discussed in the 32nd PCSC

Sr. No. Element Date & Time Reason/ Deliberation

220kV Idukki-Udumalpet line 19-04-2014 at 17:32 R-Phase to earth fault. Line auto reclosed at Udumalpet
1
hrs end and failed to reclose at Idukki end

9
ANNEXURE II
2 400kV Krishnapatnam-Nellore line-1 20-04-2014 at 2:40 R-phase to ground fault. Line did not auto reclose.

3 400kVKrishnapatnam-Nellore line-2 20-04-2014 at 3:20 R-phase to ground fault. Line did not auto reclose.
400kV Krishnapatnam-Nellore line- 21-04-2014 at 2:48 R-phase to ground fault. Line did not auto reclose.
4
1&2 hrs
400kV Guttur-Narendra line-1 28-04-2014 at 2:25 Y-phase to ground fault. Line auto reclosed at Narendra
5
hrs but failed to auto reclose at Guttur end
400kV Ramagundam-Chandrapur 28-04-2014 at 14:46 R-phase to earth fault had occurred in line. Line did not
6
line – 1 hrs auto reclose
NTPC:
• Auto reclose feature is not in service on Ramagundam – Chandrapur line due HVDC back-to-back link at
Chandrapur. It was informed that HVDC link faces problem if there is auto-reclose feature.
• It was informed that nowhere in the country, 3-phase auto reclose is implemented for the lines at generating
station.
• NTPC informed that sending DT for the earth fault at Chandrapur end is not a correct operation.
PGCIL:
• Problematic protection coupler is to be replaced for the line.
• 3-phase auto reclose feature is implemented on the Gazuwaka-Jeypore which is having HVDC back-to-back at
Gazuwaka. Synchro check is done and 1-phase auto reclose is converted into 3-phase auto reclose.
SRLDC:
• 3-phase auto reclose feature implemented on Gazuwaka-Jeypore line is not known to SRLDC and it is not clear
under what conditions it was approved. However, SRLDC recommends 1-phase auto reclose

MS i/c:
• PGCIL should come back with a plan for implementing auto reclose feature on Ramagundam – Chandrapur line.

400kVGuttur-Narendra line-2 30-04-2014 at 20:19 R-phase to ground fault. Line auto reclosed at Narendra
7 hrs end
but failed to reclose at Guttur end

10
ANNEXURE II

KPTCL:
• Bays are maintained by PGCIL at Narendra.
PGCIL
• Relays were checked individually but the scheme of auto reclose is not yet checked. It will be done after taking
the line shutdown.

400kV NCTPS-Vallur line-1 02-05-2014 at 22:58 R-phase to ground fault. Line did not auto reclose.
8
hrs
NTECL:
• During the grid disturbance, auto reclose feature was disabled at NCTPS side.
• Protection settings in Main-2 are changed and auto reclose is in service.
SRLDC:
• Within next PCSC meeting, TANTRANSCO and NTECL shall submit the details of auto reclose feature
implementation plan.
400kV Raichur-BTPS line 03-05-2014 at 15:42 B-phase to ground fault. Line did not auto reclose.
9
hrs
400kV NCTPS-Vallur-2 04-5-2014 at 4:53 R-phase to ground fault. Line did not auto reclose.
10
hrs
11 400kV NCTPS-Vallur-1 04-05-2014 4:59hrs R-phase to ground fault. Line did not auto reclose.
400kV Almathy-Vallur line-2 05-05-2014 at B-Phase to earth fault
12
05:33hrs

IV. Agenda Item as submitted by MAPS,NPCIL

MAPS,NPCIL had sent the following agenda for discussion in the PCSC forum.

11
ANNEXURE II
There are many line trips during the past which is cause of Concern to them as some of the equipment's are tripping and sometimes AVR of generator
is changing over to manual.
S.No Date & Description
Reason/
time of Deliberation
event
Line-1
1 19.04.2014 Line got tripped at 09:45 hrs with following alarms: Spurious trip as
1) 514-L1 main protection trip, exact reason could
2) 514-L1 trip and lock out, not be found
Relays flagged: 86 RX,YX,BX, 86RZ,YZ,BZ,Y3ZM1,Y3ZM2,186A,186B
MAINS-1 MICOM: R TRI,Y TRIP,B TRIP ZONE-1
Fault Location:1.3Km. Duration:100 milli sec.
MAINS-2 MICOM Y Trip. ZONE-1, distance 1.7Km
Relays flagged at ARNI END: A,B,C phase trip, Zone-1,2.15 Km,Mains-2 Zone-1
Duration:54.98 milli sec.
SP koil end Mains-2 protection operated, R&B phase carrier failure,14 KV dip in grid voltage
was realized at the time of line-1 trip.
1OVRX was flagged in Unit-1 and 2 and the same was reset. 6.6KV BUS E voltage dipped
from 6.59 KV to 6.48KV
During the line-1 trip following alarms appeared/observation/action taken in unit-1/2
1.Line 2 current went to >600amps and line 3 current got increased.
2.Unit-2 generation was lowered from 175 to 170 mW(e) by reducing
Reactor further and further lowered to 158 MW(e) by steam dumping with small steam dumping
for about 5 minutes. LD Chennai was contacted and Line- 4 Acharapakkam end breaker which
was in open condition was closed. Later unit-2 generation was normalized after closing the
steam dump valve and raising the reactor power.
3. EM carried out visual inspection on line-1 at Ist tower and found normal. After getting LD
Chennai clearance, Line-1 was test charged from SP koil end at 11:24hrs. At 11:55hrs line-1
was tied from MAPS end.
2 11.05.2014 At 11:33 hrs 230 kV SP koil line 1 got tripped with Line 1 Main protection trip and trip and Line fault

12
ANNEXURE II
lockout were in. The relays flagged are
Main I : R/Y/B TRIP ZONE 1, started phase C, Fault duration 58.19 millisecond, Relay trip
time 149 milisec,location 3.038 KM 86RX,86YX,86BX,186A,186B,Y3M1,Y3M2,COX-2,
60X-2 in unit 2
MAIN II : B-TRIP,ZONE-1,SOTF,Starter acted were in.
Line 1 was inspected up to first tower and found normal. All relays were reset and it was test
charged from SP koil end found not holding. Declared faulty. Line-1 was taken to service
at 2000 hrs.
Line-2
1 05.04.2014 Line-2 got tripped at 1307hrs on B-phase to ground on zone-1 protection(9.451KM). After Spurious trip as
inspecting S/Y, line-2 was charged back at 1345hrs. exact reason could
not be found
2 15.05.2014 At 12.00hrs 230 KV Line-2 Tripped with following alarms: Spurious trip as
1) 514-L2 main protection trip, exact reason could
2) 514-L2 trip and lock out, not be found
Relays flagged: 186,Y3M2, 85X4
In MAINS 1:
RYB Trip, ZONE -1 fault, started phase C, starter operated, over current. Fault location 32.88
km, fault resistance: 44.29 ohm, Fault duration: 79.97 sec. IA/IB/IC: 285.2A/129.5 A / 3.08 KA.
voltage: 119.3/122.5/97.53kv.
In MAINS 2:
TRIP, B Trip, Distance: 14.3 km.
Line load current: L1/L3: 460/290 amps.
At SP koil end: Mains-I: CGQ, INST, EL, 19.64 km, oc-50
Line was inspected in switchyard and up to first tower and
found normal. Relays were reset and line was taken in to service at 13.05 hrs.
Line load current: L1/l2/L3: 250/230/250 amps.
Line-3
1 12.01.2014 Emergency shut down was taken to attend to glow in R-Phase of the line insulator near Arni end Glow at breaker
breaker. end
2 29.03.2014 Got tripped on Zone-1 R-Phase to earth fault at 0620hrs. As per ADE shift Arni conductor got Conductor

13
ANNEXURE II
snapped at Cheyyur. snapped
3 30.03.2014 Got tripped with alarms 230KV Line-3 Main protn trip Spurious trip as
and 230KV Line-3 trip and lock out. Tripped on Y-phase to earth fault. Zone-1. Distance: 18.43 exact reason could
KM. Line was inspected up to 1st tower and no abnormality was noticed. Line was test charged not be found
from Arani end and found holding. Line was taken to service
4 11.04.2014 Line3 got tripped with following alarms. Spurious trip as
Line 3 tripped and locked out. exact reason could
Line main trip and trip and lock out. not be found
Relays flagged: 186A,B starter operated,Y3Z,M1,M2
86RX,Yx,Bx mains-1: R trip,Y trip, B trip VAN/BN/CN:
123.7/123.7/101.3KV. Zone-1: 9.4 Km. Fault current: 317A/216A/3.56KA
Mains -2:86YZ,86RZ,B trip zone-1 5.5 Km. At 13:06 line was test charged from ARNI end
found holding. It was tied from our end at 13:08 hrs.
5 20.04.2014 As per Arani SS, 230 KV Kalpakkam-Arani line B-Phase wave trap area line glow observed Glow at wave trap
hence 230 KV Kalpakkam-Acharapakkam line-4 breaker at Acharapakkam end closed at 10.30
hrs. 230 KV Kalpakkam-Arani line breaker at both end opened to attend the deficiency
6 01.05.2014 Line-3 which got tripped with 230KV Line-3 main protection trip and 230KV Line-3 trip and Spurious trip as
lock out alarms at 14:07 hrs. 8 KV dip in voltage was noticed. 1OVR relay flagged in both units exact reason could
and was reset. 230 KV Kalpakkam-Arni feeder-3 was checked upto Ist tower and found not be found
normal.230 KV line-3 was test charged from ARNI end found holding. It was tied from our end
at 14:50 hrs
7 03.05.2014 Arni feeder lin3 got tripped at 13.33 hrs on R phase fault, zone1, with 17.3 Km distance. Relays Spurious trip as
were reset and test charge done. As test charge was holding, Line taken back to service at 13.58 exact reason could
hrs not be found
8 06.05.2014 230 KV Line-3 tripped at 0755hrs on B phase to earth fault.Zone-2 distance protection Spurious trip as
(27KM)was operated/Y up to Ist tower was checked and found no abnormality.Line-3 was test exact reason could
charged from Arani end and found line is holding. At 830hrs Line-3 was taken to service. not be found

Line-4
1 04.05.2014 At 08:16 hrs 230 KV Acharapakkam LINE-4 got tripped on main protection. B phase fault at Line conductor got
3.5 Km recorded with 5 KV dip in system. cut
Relays flagged :

14
ANNEXURE II (15/16)

Main 1 : Zone 1, R,Y,B TRIP, Distance 3.524 Km, duration 59.94 milliseconds, Ic 10.5 Kilo
Amps, Vcn : 33.35 KV.
MAIN 2 : B-TRIP, Zone 1 send.
230 KV protection panel :
86RX,86YX,86BX,86RZ,86YZ,86BZ, Starter operated Y3M1,Y3M2.
-Line 4 was inspected in switchyard and up to 1st tower. Test charge was done from
Acharapakkam end, found not holding. Hence line declared faulty and permit given for
inspection by EB. Rain and lightning exists at site during the time. Later CISF reported that line
got cut from the first tower after the road crossing near the first circle. SE LD center, AD shift
Acharapakkam, AD lines SP koil were informed. Line 4 was isolated and Earth switch is kept
close and LC is given.
-During Line4 tripping time, Unit1 AVR got changed over to Manual with alarm "Excitation
protection changeover channel 1-2", House load permissive contact faulty were in. In DVR
panel UN-665(AB 61)
LED 21 - Protection changeover, LED-25 Channel -1 PT fuse failure,
In UN-665(AB-65) for channel 2 LED 25 PT fuse failure were glowing.
Relays 60X1 and 60X2 were found flagged and were reset. House load HS is selected to bypass.
Excitation relay 1 OVR was reset.
-EM checked the Generator PT output MCBs at 110 V side voltage for AVR and protection
channel were found normal at 102 volts. DVR input terminal voltages were checked and found
normal. Alarms were reset from micro tech panel by pressing Release reset and Acknowledge
/reset PBs. Alarms got cleared.
-AVR was changed over to auto channel 1 at 11.05 hrs. The response is checked & found
normal. House load HS is selected to NORMAL.
2 14.05.2014 Acharapakkam line was isolated for attending R phase conductor as it got detached from the R-ph conductor cut
suspension insulator by TNEB personnel. R phase suspension insulator was replaced by TNEB
staff. Acharapakkam end line DS sparking problem being attended by TNEB staff .Line was
taken in to service at 1650hrs on 15.05.2014.

On 22-05-2014, U-1 was operating at 165 MW(E) and U-2 was operating at 168 MW(E) At 13.08hrs both units came on house load operation due
to sudden grid frequency dip from 49.92 to 47.65Hz. 230kV grid supply was found lost. During the units are on house load operation, U-1 PHT

15
ANNEXURE II (16/16)

pump -7 got tripped on protection. In consequence to pump tripping reactor got tripped resulting in unit outage. Unit-2 was synchronized after grid
normalization at 13.36hrs.

Total 8 no of line trips could not be justified & 6 no's of incidents were line faults.

32nd PCSC Deliberations

MAPS:
• There were 18 outages recently due to spurious trippings. Arani line alone tripped about 5 times.
• Arani line is tripping frequently without any fault on the line and the fault distance is known.
• On many occasions during the line trip and subsequent voltage dip effect, the AVR of the generating unit is switching over from automatic to
manual mode on its own. When the voltage becomes normal, AVR is taken from manual to automatic mode manually.
• TANTRANSCO was requested to carry out line patrolling for locating any trouble spots, if any.
• On 22.5.2015, two units at Kalpakkam went on house load.
• From MAPS to TANTRANSCO, there are two lines to Singamperumal (SP) Koil, one line each to Arani and Acharapakkam.
• On 22.5.2014, TANTRANSCO lines (i.e. SP Koil lines-1&2) were radially drawing a load of 450 MW while MAPS was generating around 330
MW. Since there is no connectivity to grid for MAPS, momentarily there was an island formation with 330 MW generation and 450 MW load
which could not sustain and the generating units at MAPS went on house load on account of u/f operation at 47.65 hz after opening the GCB of
the units.
• MAPS opined that had Acharapakkam line been there, the incident could have been prevented.

MS i/c:
• If any Line Clearance (LC) is there in that area for maintenance, then further opening of the lines have to be restricted for avoiding undesired
island formation of MAPS generation with TANTRANSCO loads.
• The MAPS islanding issue would be discussed in the next PCSC meeting.

*****

16
ANNEXURE III (1/59)
ANNEXURE III (2/59)
ANNEXURE III (3/59)

Annexure
Phase-1
S. Name of Substation Details of work Status of Implementation of Phase I
N Recommndations

POWERGRID
1 400 KV Arasur Substation Distance protection Zone-2 & Zone-3 timing of 230 complied
KV feeders need review

2 400 kV Bidadi Substation Synchronisation check relay setting is to be complied


reviewed.

3 400 kV Ghanapur (Hyderabad) Enabling of stub protection in Ramagundam-3 & 4, complied


Substation Kurnool feeders

Replacement of static relays by Numerical Relay complied


provided for Distance, Differential Bus Bar and
Reactor Protection
4 400 kV Gooty Substation Numerical Bus bar protection to be provided Numerical Busbar protection is not
envisaged as per Gazzette notifications.

Static differential relays to be replaced with complied


numerical relays on reactors and ICTs

Electromagnetic back up directional O/C and E/F All Distance protections, ICT Differential
relays to be replaced with numerical relays on ICT- and Reactor B/U protections are
1. provided with Numerical relays.

1
Pld PLCC protection couplers to be replaced with PLCC protection couplers are healthy
new protection couplers and providing trouble free service. In
case of any complaints same shall be
addressed accordingly.

5 400 kV Hassan Based on Setting of distance protection relays to complied


be reviewed as per the revised line parameters
received from KPTCL.

6 400 kV Hiriyur Substation Static distance relays of 400 kV feeders to be complied


replaced with numerical relays

Static bus bar protection relay to be replaced with Replacement of bus bar relays with
numerical relays numerical is not contemplated in the
gazette notification

7 400 kV Kadapa Substation Electromagnetic and static relays for ICTs, All Distance protections, ICT Differential
Reactor, Bus bar,over voltage, distance protection and Reactor B/U protections are
to be replaced with numerical relays. provided with Numerical relays.
However Numerical Busbar protection
is not envisaged as per Gazzett
notifications.

8 400 kV Kalivanthapattu S/S 230 kV feeder distance protection Zone-2 and complied
Zone-3 timings need review

9 400 KV Khammam Substation Old Static line protection (Distance) relays to be complied
replaced with numerical relays

10 400 kV Madakkathara Time synchronising of protection system with GPS complied


to be provided

2
11 400 kV Mysore Substation Replacement of static relays (THR, CAG, RADHA complied
etc.) with numerical relays to be looked into.

Co-ordination of protection settings for 220 kV complied


Downstream lines to be done to avoid un wanted
trippings at Mysore SS.

12 400 KV Narendra Substation Plug setting multiplier setting of back up over complied
current relays of CTs to be reviewed.

Distance protection Zone-2 and Zone-3 timings of complied


220 KV lines need review

Bus sectionaliser direction to be reviewed (both complied


sides operation).

13 400 kV Puducherry Substation Zone-2 & Zone-3 time settings of distance complied
protection relays of 230kV feeders need review.

LBB & Bus Bar protection are in-built in the same In built busbar and LBB protection in
Siemens SIPROTEC 75552 Relay for both Main 1 station bus bar protection scheme is a
& 2. Same needs review general practice being followed in all
SAS based substation and this is as per
the latest practice in protection system

14 400 kV Pugalur Distance protection zone-2 and zone-3 time complied


settings for 230 kV Lines needs review.

3
15 400 kV Salem Substation Static distance protection relays of 400 kV feeders complied
to be replaced with numerical relays

16 400 kV Somanahalli Substation Nomenclature of Binary Inputs/Binary Outputs & complied


function to be done in DR.

The high set setting of HV side DOCR & DEFR of complied


each 500 MVA Transformer needs review.

17 400 kV Trichy Substation Old electromagnetic/static relays to be replaced complied


with numerical relays.

18 400 KV Vijayawada (NUNNA) Old Static line protection (Distance) relays to be complied
Substation replaced with numerical relays.

Evaluation unit is to be made available for Complied


Disturbance recorder of 400 KV Vemagiri-I & II
feeders.
The DRs (Indactic65C) and Event Logger Asset pertains to APTRANSCO. Being
(SER7000) of 400KV VTPS-I & II Feeders are not coordinated for attending the same
healthy and need to rectified.

Monitoring source to be provided for DC earth DC Earth fault relay is already available.
leakage to be provided Complied,

19 400kV Kochi Substation Over voltage protection time setting to be reviewed complied

Review of zone-3 setting for 220kV Kochi- complied


Brahmapura and 220kV Kochi-Kalamashery

20 400kV Munirabad Substation Numerical relay to be provided for differential complied


protection of ICT-1&2

4
21 400kV N'Sagar (Tallapalli) Old relays to be replaced with numerical relays for complied
Substation feeders, ICTs and Reactors.

Mutual compensation to be incorporated in complied


distance protection settings of 400kV N'Sagar-
Ramagundam ckt-1&2.

NTPC
1 220 kV Kayamkulam Zone-2 and Zone-3 timings of distance protection complied
relays need review.

2 400 kV Ramagundam Distrubance Recorders (ABB, INDACTIC) to be complied


time synchronized with GPS.

3 400kV Simhadri Existing MICROMHO relays of Stage-I lines to be complied


replaced with Numerical relays.

NEYVELI LIGNITE CORPORATION

1 400 kV NLC TPS-I Expn. Protection system to be synchronized with Complied


available GPS

Event logger to be rectified and made functional Complied

Disturbance Recorder to be rectified and made Complied


functional

5
Existing micro mho distant protection (Main I) Relays received at site. Erection will be
relays to be retrofitted with numerical relay. taken up.

2 400 kV NLC TPS-II Expn. O/V protection for stage-II time setting to be Complied
revised for instantaneous trip

NPCIL
1 220 KV Kaiga-Generating The line relays 220 KV side are provided with 01 The settings will be implemented
Station-1&2 primary protection ie. Static Relay, and a back up subsequent to the approval at the
relay is to electro mechanical relay with high set. staion at the earliest oppurtunity.
Blocking of High set protection in the back up relay
needs to be reviewed. NPCIL-Kaiga to review the
same

Instead of Static Relays, Numerical Relays to be Action has been initated for
provided with different make for all lines as Main-I procurement of Numerical relays
and Main-II. NPCIL-Kaiga to review the same (Micom-P442 and Micom -P443 ).
Replacement of existing static type
relay (EE,SHPM101) with numerical
relays as Main -I and Main -II will be
implemented upon receipt of material at
Kaiga site.

6
Tamilnadu - TRANSCO/ GEDCO/ IPP
1 230 kV Arni Substation Static relays are to be replaced with numerical Procurement action initiated. Further
relays tender process could not be carried out
due to Election code of conduct. Time
extension requested upto October
2014.
V/F protection for transformers to be made Will be provided.
available
REF protection to be implemented for Neutral CT is arranged to be provided.
Transformers (Capacity below 100 MVA) Numerical diffl. Relay will be provided.

DC leakages are to be complied for DC source I. complied

synchronizing facility to be made available. Synchronising panel to be procured.


Will be done in Phase 2
2 230 kV Basin Bridge Substation Carrier scheme to be provided for 230kV Mylapore Fibre laying is under progress
feeder

No protection during VT Fail condition. Same to be complied


reviewed

No Earth fault protection on HV & LV side of E/F settings for AUTOs not being
transformer. Same to be provided adopted in Tantransco.

O/L settings oauto transformers to be reviewed Uniform setting procedure adopted

Separate earthing for DC system (110 V DC) to be Estimte got sanctioned. Work under
provided progress.
Only Bus PT supply is available for Main I & II Line CVT to be provided in all feeders
protection, no line VT supply is available for and will be taken up in second phase.
protection. Same needs review

7
No Capacitor Tripping Devices are kept in service Due to nuisance trippings Capacitor
for Feeders and Transformers. Same needs review trip device is disabled.

Relay settings for feeders and transformers need Being reviewed whenever needed.
review
Time synchronising with GPS to be provided for Time synchronising with GPS provided
230kV protection system and is in service.

Auto reclosure to be enabled for feeders. complied

Power swing block settings to be reviewed. Adopted as recommended by SRPC.

3 230 kV Ennore (ETPS) Earth fault relay to be provided on HV & LV sides E/F settings for AUTOs not being
of Auto t/p # 1, 2 and TO # 3 t/f. Over fluxing adopted in Tantransco.
relayto be provided.
OT1 and WT1 indicators suspected for not Defects rectified and indication
working. Same needs to be rectified. available now.

PRV device to be made available on Auto T/f # 1 PRV available in Auto 1. Explosion vent
and 2. available in Auto 2.
Surge counters to be made available on lightening Surge counters available in 110kV
arrestor. LAS.Action is taken for provision in
230kV LAS.
DC earthing in 220V DC system to be rectified Earthing checked and rectified.

Zone-2 timing of distance protection relay of 23kV Zone 2 time delay 350mSec as per
kines need review SRPC recommendation.

4 230 kV Gobi Substation REF protection to be made available. REF protection enabled.

8
Time synchronising with GPS to be provided for
protection relays.
Procurement action initiated. Further
Static distance relay to be replaced with numerical
tender process could not be carried out
relays.
due to Election code of conduct. Time
Diiferent type and Make of distance protection extension requested upto October
relays to be provided for Main-I & Main-II protection 2014.
for 230kV Arasur feeder.

5 230 kV Hi-Tech Carbon Co- Earthing system to be improved. Additional earth pits being provided.
Gen.
Dedicated hot line speech facility to SLDC to be May not be insisted since the
established. connectivity is for 33.7MW and in
110kV level.
6 230 kV Ingur Substation Time synchronising with GPS to be provided for
protection relays.
Static distance relay to be replaced with numerical
relays. Procurement action initiated. Further
Diiferent type and Make of distance protection tender process could not be carried out
relays to be provided for Main-I & Main-II protection due to Election code of conduct. Time
for 230kV Arasur and K.R.Thoppur feeders. extension requested upto October
2014.

In Busbar Protection same CT is used for Main &


Check zone relay. Same needs review

7 230 kV Kayathar Substation Earth resistance to be measured and recorded. Earth resistance is measured and
recorded.(0.6 ohms)

8 230 kV Korattur Substation During VT fail condition no protection is available complied


(Backup 1> disabled). Same needs review

No E/L relay protection on ATR 1, 2 & 3 HVs. E/F settings for AUTOs not being
Same to be provided adopted in Tantransco.

9
V/F protection is not available on ATR-1, 2 & 3. Will be enabled.
Same to be provided.

Different type and Make of distance protection Procurement action initiated. Further
relays to be provided for Main-I & Main-II protection tender process could not be carried out
for 230kV feeders due to Election code of conduct. Time
extension requested upto October
2014.

Only Bus PT supply is available for Main I & II Bus PT used for protection in all the
protection. There is no line VT supply available for stations. Procurement action for
protection. Same to be reviewed and rectified. provision for Line CVT is under
process.

No capacitor tripping devices are provided on 230 Due to nuisance trippings Capacitor
kV feeders & ATRs. Provision for the same to be trip device is disabled.
done

Relay settings for feeders and transformers need Reviewed whenever needed
review
Time synchronising with GPS to be provided for Procurement action initiated. Further
230kV protection system tender process could not be carried out
due to Election code of conduct. Time
extension requested upto October
2014.

9 230 kV Madurai Substation Time synchronising with GPS to be provided for Procurement action initiated. Further
(Alandur) protection relays. tender process could not be carried out
due to Election code of conduct. Time
extension requested upto October
Static distance protection relays to be replaced with
2014.
numerical relays.

Station Event loggerto be provided

10
10 230 kV Manali Substation O/C and E/f relay setting on HV & LV sides of both Uniform setting adopted
auto transformers need review.

Diiferent type and Make of distance protection Procurement action initiated. Further
relays for Main-I & Main-II protection to be provided tender process could not be carried out
for 230kV feeders due to Election code of conduct. Time
extension requested upto October
2014.

DC earthing in 220V DC system to be rectified DC earthing rectified.

Earth resistance meaured on 07.02.2009. It is Combined earth resistance


observed to be violating in more number of earth measured.Individual earth resistance
pits. The same to be rectified will be measured on availing LC.

11 230 kV Mylapore Substation Carrier scheme to be provided for 230kV Basi Fibre laying is under progress
bridge feeder

No protection during VT Fail condition. Same to be complied


reviewed

Static Main-2 relay of 230kV Basin bridge feeder to complied


be replaced with Numerical relay

No Earth fault protection on HV & LV side. Same to E/F settings for AUTOs not being
be reviewed and provided adopted in Tantransco.
Earth leakage monitoring system to be provided Earth leakage monitoring provided

Separate earthing for 220 V & 48V DC system to Work under progress.
be provided

Only Bus PT supply is available for Main I & II Bus PT used for protection in all the
protection, no line VT supply is available for stations.
protection. Same needs review

11
No Capacitor Tripping Devices are kept in service Due to nuisance trippings Capacitor
for Feeders and Transformers. Same needs review trip device is disabled.

Time synchronising with GPS to be provided for


230kV protection system
Procurement action initiated. Further
tender process could not be carried out
due to Election code of conduct. Time
Provision for station event logger to be done extension requested upto October
2014.

12 230 kV North Chennai TPS CTD protection to be provided in all 230KV feeders Due to nuisance trippings Capacitor
and Transformers. trip device is disabled.

Different type and Make of distance protection Procurement action initiated. Further
relays to be provided for Main-I & Main-II protection tender process could not be carried out
for 230kV feeders due to Election code of conduct. Time
extension requested upto October
2014.

Remote temperature indicators to be provided for -


station transformers.

13 230 kV Pugalur Substation Time synchronising with GPS to be provided for


protection relays. Procurement action initiated. Further
tender process could not be carried out
due to Election code of conduct. Time
Station Event Logger, Disturbance Recorder with
extension requested upto October
dedicated computer systems, printers to be
2014.
provided.
14 230 kV PUSHEP Switchyard DC leakage in the station to be rectified complied
(Pykara Ultimate S/S (GEN.)

12
15 230 kV Singaperumal Koil Trip circuit supervision relay to be provided for both R&M work will be done.
Substation trip coils for 230 kV Veerapuram, 230 kV
Kalpakkam, 230 kV Kalivanthapattu, 230 kV
Oragadam, 230/110 kV Auto 1 HV side

230 kV Singaperumal Koil Provision for supervision of all the trip coils through -
Substation the TSR relay to be examined.

High water content in auto transformer oil test complied


report needs review and suitable actions

It is found that relays of the same C&R panels are R&M work will be done.
placed in different locations of other C&R panels in
many bays. It is very difficult for the SS operator to
identify the relays during emergency condition.
Hence relays shall be placed on the respective
feeder panel to be examined.

TMS of auto transformers for over currrent relays Uniform setting adopted
(HV/LV) to be reviewed and corrected

Replacement of all static relays (Differential, Procurement action initiated. Further


Busbar, Distance etc) to be done with numerical tender process could not be carried out
type relay due to Election code of conduct. Time
extension requested upto October
2014.

Since the length of 230 kV Veerapuram line is Numerical relay available and
around 650 mts, sensitivity of performance of performance satisfactory
distance protection for that shortest line needs to
be examined.

13
Carrier aided protection scheme to be provided for Fibre laying is under progress. Aided
230 kV Oragadam feeder protection will be provided by June
2014.
Provsion for Direct trip transmission signal on complied
operation of Bus bar/LBB relay for all the lines to
remote end to be provided.

DC earthing in DC system to be rectified leakage R&M work will be done.

Labelling to be done for all the relays in panels to complied


be provided

Cable Duct near Auto transformer 3 needs to br R&M work will be done.
repaired

Over flux protection to be provided for Auto Procurement action initiated. Further
transformers . tender process could not be carried out
due to Election code of conduct. Time
extension requested upto October
2014.

16 230 kV Thiruvalam Substation Battery earth leakage meters provided for DC Work will be takenup
source I & II are not in working condition. Same
needs to be rectified.

Non Directional Over Current relay with 150% on Uniform setting adopted
both sides of all Auto Transformers are provided.
Earth fault relay on both side are not adopted.
Same needs review.

17 230 kV Tondiarpet Substation Transmission line earth wire not connected to SS Work will be takenup
earth mat at Tondiarpet. Same needs review and
rectification

14
100 MVA, 230/110 kV transformer # 1 &2, back up Uniform setting adopted for O/C. E/F
O/C relays setting need review. Earth fault relays settings for AUTOs not being adopted
to be provided on both HV & LV side of ICT's in Tantransco

REF for transformer # 1, overfluxing relays for both Neutral CT to be provided


t/f # 1, 2 to be provided

DC earthing in 220V DC system to be rectified complied

Separate treated earthpit for DG set to be Work under progress.


provided. Body of DG Set to be earthed with
suitable flat or conductor.

18 230kV Mettur Thermal Power Main-I and Main-II protection schemes to be fed Work will be takenup on availing LC
Station from separate DC source. Provision for the same
to be done.

PLCC protection coupler to be made available for Procurement action initiated. Further
MTPS-Stage-III and MTPH feeders. tender process could not be carried out
due to Election code of conduct. Time
extension requested upto October
2014.
Synchronisation cores of Line VT and Bus VT are Reviewed
of different voltage ratios and same needs review

Time synchronising with GPS to be provided for Procurement action initiated. Further
protection relays. tender process could not be carried out
due to Election code of conduct. Time
extension requested upto October

15
Both Main-1& Main-2 distance protection relays of extension requested upto October
230 kV feeders to are be of numerical type. Static 2014.
distance relays to be replaced with numerical
relays.

19 230kV Singarapettai Substation Zone separation for Bus Bar Protection needs to Estimate sent for approval.
be done. .

Staticrelays to be replaced with Numerical Relays. Procurement action initiated. Further


tender process could not be carried out
due to Election code of conduct. Time
V/F Protection to be enabled in autotransformers extension requested upto October
upto the level of 230 kV 2014.

20 400 kV Alamathy Substation Time synchronising with GPS to be provided for Procurement action initiated. Further
400 & 230kV protection system tender process could not be carried out
due to Election code of conduct. Time
extension requested upto October
2014.
Different type and Make of distance protection
relays to be provided for Main-I & Main-II protection
for 230kV feeders

Earth leakage Relays to be made functional work will be taken up

21 400 kV K.R.Thoppur Substation Possibility of providing time synchronising system


(Salem) (GPS Unit) for protection relays.
Procurement action initiated. Further
The existing Static Distance Protection Relays to tender process could not be carried out
be replaced with Numerical Relays. due to Election code of conduct. Time
extension requested upto October
Dedicated event Logger to be provided for post 2014.
tripping analysis.

16
22 400 kV Sunguvarchathiram Separate auxiliary relays for transformer mounted Will be provided.
protection.

Control cable duct to be properly sealed to avoid complied


entry of rain water.

Different type and Make of distance protection Procurement action initiated. Further
relays to be provided for Main-I & Main-II protection tender process could not be carried out
for 230kV feeders due to Election code of conduct. Time
extension requested upto October
2014.

Tap position indication of some of the 1 phase Being attended by OEM


ICTs are not showing properly, which is to be
rectified

Enabling of "directional earth fault protection in complied


main-1 and main-2 distance relays

The differential protection relay in ICTs has inbuilt As per norms one differential relay
function of differential protection, ref protection, provided.
overflux protection, aux. protection for transformer
mounted relays, breaker failure protection. So
provision for additional differential protection relay
with all the above in built function as a main-II to be
reviewd for improving reliability

Providing of Trip-Neutral-Close (TNC) switch for all TNC switch will be procured and
the bays in C&R panel for emergency operation connected.

17
Providing of "Stub protection" for 400 kV lines Provided for NCTPS 1&2. For SPDR
and Pondy feeders Stub protection will
be enabled during the Annual relay test
during 2014.

23 400 kV Sriperumbudur Replacement of static distance, differential & -


busbar protection relays with numerical relays

Provision to be made for continuous monitoring of -


dc earth leakage measurements

Enabling "Direction Earth Fault" function in -


numerical type main-1 and main-2 distance relays

Time synchronising of protection system with GPS -


to be provided

Different make & type of distance relays to be used -


for Main-1 and Main-2 protection

Carried aided protection to be provided for 230kV -


Sriperumbudur-Nokia, 230kV Sriperumbudur-
Mambakkam (sipcot), 230kV Sriperumbudur-
Oragandam

Andhra pradesh - TRANSCO/ GENCO/ IPP

1 220 kV APGPCL - Stage-I Static distance protection relays to be retrofitted -


Vijjeswaram GS with numerical relays

GPS to be provided for time synchronization of -


protection system

18
2 220 kV APGPCL - Stage-II All distance static relays should be retrofitted with -
Vijjeswaram GS latest version Distance Relays for quick and
accurate analysis for the tripping.

GPS to be provided for time synchronization of -


protection system

Directional Earth Fault protection to be provided/ -


enabled

3 220 kV Bommur Substation The Static distance protection relays available on


220 kV feeders are to be replaced with latest
Indent under preparation
numerical relays with inbuilt DR

GPS to be provided for time synchronization of


protection system Indent under preparation

REF is not used in APTRANSCO for 220 kV


Differential protection is used for
substations.
Transformers in 220KV Substations.

4 220 kV C.K. Palli Static Distance Relays of Main I & II on 220 kV


Rajampeta feeder to be replaced with numerical
relays Indent under preparation

Event logger for recording of sequence events is


not available. Same shall be made available
Indent under preparation

Time synchronisation equipment not available.


Same shall be made available.
Indent under preparation

19
5 220 kV Chandrayanaghatta Replacement of existing Static Relays provided for
Distance Protection, diff protection with numerical
Indent under preparation
relays

Replacement of 220 kV Dind-1 & 2 Mamidipally


and Hial feeder control panels to be reviewed 220kV Dindi-I & II and Mamidipally for
control panels replaced with numerical
relays

220 kV Ghanapur-2 feeder annunciation module to


be made functional
Rectified

The Relay panels of different bays are scattered in


different rooms and monitoring of the same is very
The re-arrangement of relay panels in
difficult. Hence re-arrangement of relay panels in
existing control room is not possible and it
main control room to be examined for proper requires entire modufication of existing
monitoring. building.

PTR 4 (100 MVA) LV side dir E/F relay to be made


Directional Earth Fault Relay is Provided on
functional 100 MVA PTR-1 and revised relay settings
implemented.

100 MVA PTR-1 LV side non directional E/F relay


provided due to non availability of directional
feature, whereas recommended relay is directional Made functional.
E/F.

In PTR 1 (100 MVA) and PTR-2 (160 MVA) LV


over flux relays not provided. Also transformer
trouble trips were provided in differential relay as Overflux feauters available in differential
inbuilt function. Providing separate auxiliary relays relay has been enabled.
for transformer troubles to be examined.

20
6 220 kV Chittoor Substation Auto reclosure function is to be enabled for all 220
On 220KV feeders Auto recloser function
KV feeders.
not used in APTRANSCO system.

Surge monitors to be made availble for LAs on LV


PTR-II surge monitor replaced.
side of Auto Transformer 1&2.
PTR-I under progress.

Carrier aided trip to be be made available for


220kV Tiruvalam and Kalikiri feeders. Chittoor - Tiruvalam protection available,
drawn for 220kV Kalikiri and working.
Protection equipment diverted towards
Kalikiri direction and to be commissioned.

Necessary Surge Monitors on LA's to be provided


where they are not available. Provided.

Insulation mats in front of the control panel to be


provided Provided.

7 220 kV Gachibowli (hyderabad) Over flux relay is to be provided on HV side of


Substation 220/132 kV, 100MVA PTR-1. Rectified

DC earth leakage to be rectified in the 220KV DC


Rectified
system-I&II
Replacement of existing Static distance protection
relays for feeders, Differencial relay of
Indent under preparation
transformers with numerical relays

8 220 kV Gajwel Substation Different Make and type of distance relays to be


used for Main- & Main-2 protection for Lines. Same Will be exchanged with new fab city feeder
to be implemented at 400kV SS, Mammidipally

220 kV KAMAREDDY line distance relay settings


As communicated recommended settings
to be reviewed. are adopted

21
100MVA PTR-I, O/L Relay settings of HV and LV
side need to be reviewed As communicated recommended settings
are adopted

Replacement of Static type ABB make Differencial


relays (RADSB) provided in, PTR-1&2 with Indent under preparation
numerical relays

100MVA PTR-2 OLTC tap position indicator in


RTCC panel to be made functional Rectified

9 220 kV Gooty Substation All static distance relays of feeders shall be


replaced with numerical distance relays. Indent under preparation

Event logger for recording of sequence events is


not available. Same shall be made available Indent under preparation

GPS time synchronisation equipment not available.


Same shall be made available. Indent under preparation

10 220 kV HIAL Substation Earth leakage to be provided


Rectified the DC leakage problem

11 220 kV Jurala Generating Provision of differential protection for Jurala line 1 Fund mobilisation proposal is put up to
Station & 2 (line length-1.45 KM) feeders to be examined. board and procurement action will be
made soon after getting approval

Main 1 & 2 distance relays to be of different make


and type for 220kV lines. Same to be implemented. -do-

The inbuilt disturbance recorder available in Referred to the OEM and its reply is
numerical relays to be activated awaited.

22
In adopted distance relay setting for Main 1 & Main Adopted as per recommended settings
2 for Jurala Line 1 & 2 one of the settings of piolet
directional protection i.e. PIL - Dis.resist ROZ is
0.24 ohms whereas recommended setting is 18.05
hms which is the major deviation.

In bus bar protection settings recommended Fund mobilisation proposal is put up to


setting for charge exit differential is on, whereas board and procurement action will be
adopted is Off. This is to be reviewed. made soon after getting approval

Instrument for earth resistance measurement to be Procured


made available

DC earth leakage in DC system to be rectified Rectified

PLCC panel is erected but not commissioned It is found that the same are not
suitable for indian system and
procurement is in progress

GPS time synchronisation for 220 kV switch yard Fund mobilisation proposal is put up to
protective relays to be provided board and procurement action will be
made soon after getting approval

12 220 kV KTPS SS A,B,C Unit (1- All Electro Static Relays to be replaced with latest
Relays Procured. It will be replaced in next
8) - Kothagudem version Numerical relays
shut down of the unit.
110V/220V DC source earth to be removed. Removed.

Over Flux Relays to be provided for IBT and ST Provided.


Transformers.
Time synchronisation equipment (GPS) to be Procurement action will be made soon
provided for protection system
after getting approval from APGENCO
management.

23
The old RAZOA (Electro Static) relays to be Replaced.
replaced with latest version Numerical relays

13 220 kV Lanco Kondapalli Power GPS to be provided for time synchronization of -


Ltd. protection system

14 220 kV Malayalapalli S/S- Time synchronising system (GPS), Distrubance


APTRANSCO Recorder (DR), Event Logger (ER), Synchro check Indent under preparation
relay not available in the station.

15 220 kV N'Sagar Station event logger to be made available Fund mobilisation proposal is put up to
board and procurement action will be
made soon after getting approval

No GPS is available. Time sync facility not Purchase order placed for the same
available. Same to be provided and will be commissioned soon after
procurement.
No A/R feature and no O/V feature is available. Provision is available and will be
Same to be provided activated if recommended.

There is only 3-phase tripping. No I-phase tripping. Provision is available and will be
Same to be reviewed and provided activated if recommended.

Sync facility available in Main-1 relays of all Provided


feeders except Talapalli-3. Same to be provided

Mutual compensation for Talapally 1 & 2 feeders is Provided in Main-1 relay


not available. The same to be reviewed.

PLCC protection panels for Talapally 1, 2,3 are to Commissioned


be commissioned.

PLCC protection panels for Srisailam and will be provided


Chalakurthy are not available. Provision for the
same to be done

24
16 220 kV Ongole Substation Provision of additional 220kV battery charger
Provided battery charger

Provision of Air conditioning to the Control Room to


be done Indent under preparation

17 220 kV Rayalaseema TPS All static relays on feeders to be replaced with Procurement action will be made soon
nemerical distance relays after getting approval from APGENCO
The static Bus Bar Protection to be replaced with management.action will be made soon
Procurement
numerical relays after getting approval from APGENCO
Station Event logger to be madefunctional management.action will be made soon
Procurement
after getting approval from APGENCO
GPS time synchronisation of relays shall be made management.
Procurement action will be made soon
available. after getting approval from APGENCO
18 220 kV Renigunta Substation The carrier aided tripping not available in 220 kV management.
Indent under preparation
Nagari feeder
Auto reclosure function to be enabled for all
Under procurement and awaiting for budget.
220mkV feeders
Surge monitor for 220 kV C.K. Palli (R-Ph)and On 220KV feeders Auto recloser function
Nagari (B-ph) to be replaced not used in APTRANSCO system.
220 V battery charger to be made functional
Replaced

Defective surge monitors to be replaced


Replaced.

Possibility of differential or distance protection to


be provided for 132 kV Grindwell Norton feeder
Replaced
and 132 kV Railway I & II feeders

19 220 kV Samalkot Power Station Distance protection relay settings to be reviewed Reviewed and revised relay settings are
communicated and adopted.
PLCC Inter Tripping Scheme to be made functional
Carrier protection scheme is enabled.

25
Provision for O/V, U/F & df/dt protections for 220kV
feeders to be reviewed. O/V, U/F & df/dt protection features are not
used on 220KV feeders in APTRANSCO
system and O//V, U/F & df/dt relays are
provided on the identified feeders as per the
protection committee meeting directives.

20 220 KV Shahpurnagar Over flux relay is to be provided on HV side of


Substation 220/132 kV, 100MVA PTR, 160 MVA PTR 1 & 2. Rectified

21 220 kV Shamshabad Static distance protection relays to be replaced with


Substation numerical relays Indent under preparation

100 MVA PTR-2 remote temperature indicator to


be replaced Procurement under process

over flux relay to be provided for 100 MVA PTR-1


Overflux relay available in differential relay
has been enabled.

22 220 kV Shivarampally DC earth leakage to be rectified in 220KV DC-I


Substation system Pending from CE/Metro Zone

Different Make and type of distance relays to be


used for Main- & Main-2 protection for 220 KV
mamidipally & Gachibowli lines Lines. Same to be Rectified.
implemented

Static differential and distance protection relays to


be replaced with numerical relays Indent under preparation

Overflux protection to be provided for 100MVA


PTR-I, LV over flux is removed. Overflux features available in differential
relay has been enclosed.

26
100MVA PTR-III Existing LV directional earth fault
relay is to be made functional Made functional.

100MVA PTR-III HV directional earth fault relay is


to be made functional Made functional.

LV over flux protection in 100 MVA, PTR-II to be


made available. Overflux features available in differential
relay has been enclosed.

23 220 kV Spectrum Power O/V protection, df/dt & UFR protection to be


Generation Limited provided for 220 kV feeders. Over voltage, df/dt and under frequency
protection is not provided on 220KV feeders
is APTRANSCO system and O//V, U/F &
df/dt relays are provided on the identified
feeders as per the protection committee
meeting directives.

PLCC inter trip protection to be made functional for


220kV feeders. Made functional.

GPS to be provided for time synchronization of


protection system Indent under preparation

24 220 kV Srisailam Distance protection relay settings, power swing Settings are adopted as per
block settings to be reviewed for 220 kV lines APTRANSCO recommendations

Disturbance recorder, Station Event logger and Fund mobilisation proposal is put up to
GPS to be made available board and procurement action will be
made soon after getting approval

In Tallapalli feeder-1 (P442) relay configuration of Settings are adopted as per


voltage protection, CB failure are disabled. It is manufacturer recommendation and
also noticed that KZ RES component and angle APTRANSCO being consulted for
different from approved settings. Same to be review.
reviewed

27
In N.Sagar line (P442) relay configuration of Settings are adopted as per
voltage protecgtion, CB failure and interval auto manufacturer recommendation and
reclose configuration disabled instead of enable APTRANSCO being consulted for
mode. KZ RES component and angle different review.
from approved setting. Same to be reviewed

All static relays like distance relay, differential relay Fund mobilisation proposal is put up to
and Bus-Bar relays to be replaced with latest board and procurement action will be
version numerical relays having inbuilt D.R made soon after getting approval

Earth resistance measuring instrument to be Procured


procured.

25 220 kV Srisailam power station The Generator differential protection, GT O/C+ E/F Except GT REF protection all other
(right bank) protection , GT REF Protection, Overflux protection protections were duplicated either in
, UAT O/C + E/F protection settings to be main-2 realy or through separate relay.
duplicated and provided in Main-2 relay for
increasing the reliability.
Older version of unit 4 Main-I & II relay (REG Replaced with REG670 relays
316*4) relay to be replaced with REG 670 or other
similar relay as provided for other units

GPS to be provided for time synchronization of GPS already procured and will be
protection system commissioned along with the
switchyard scada.
26 220 kV Sullurpet Substation Eroded flexible copper earthing provided between
CTs and structure of LV1& LV2 of 220/132kv
Rectified
Transformers to be rectified

Surge monitor in Yph of 132kv srikalahasti feeder


to be rectified/ replaced Replaced

Oil leak noticed in 100MVA 220/132KV BHEL


MAKE PTR to be rectified Rectified & arrested oil leakage

28
PLCC equipment on 220kv Gummidipudi feeder to
be replaced/ retrofitted Inter State feeder (to be projected)

Enabling of Auto recloser in all 220kv feeders


On 220KV feeders Auto recloser function
not used in APTRANSCO system.

27 220 kV Tadikonda Dual earthing for CTs and CVTs 220KV VTS-1
feeder to be done Indent under progress

28 220 kV Vijayawada TPS Earth fault/Strips in 220 KV Switchyard are rusty, to Painting completed.
(Dr NTTPS) be bituminous painted.

DC earth leakage in station DC supply to be Attended.


rectified.

Station Transformer Relays (EE Make, DTH31


Purchase Order placed. It will be replaced
Model) to be replaced with Numerical Relays
soon.
In stage-I (Units-1&2) Back-up Impedence New setting Adopted.
Protection, Earth Fault Protection to be reviewed

In stage-3 (Units-5&6) Non directional Earth Fault Attended.


Protection, Phase over current protection settings
in UAT to be reviewed.
29 220 kV Yeddumailaram DC earth fault in 220V DC system to be rectified
Substation Rectified.

220 kV Bus bar protection relay along with in-built


220KV busbar protection scheme kept in
LBB function to be made functional
service.

Replacement of static differential protection and


distance protection relays with numerical relay Indent under preparation

29
Provision of overflux protection for transsformers
Provided.

100 MVA, PTR-III Earth fault relay Time setting for


As communicated recommended settings
HV and LV side to be reviewed
are adopted in the field.

160MVA, PTR-II HV O/L and E/F relays to be


made functional. LV side E/F relay to be made Made functional.
functional.
O/L & E/F setting of transformers to be reviewed Reviewed and recommended settings are
adopted
220 kV Gachibowli line Main-II distance relay is be
made functional Needs relay replacement.

Zone-III setting in Shadnagar feeder to be Zone-III settings are changed as per the
reviewed instructions of Power Systems Wing.
Zone-III Timing setting in Shamshabad-II to be
reviewed. Recommended settings are adopted

30 400 kV Chitoor Substation Carrier aided protection to be made available in


Equipment diverted and are to be
220 KV Palmner feeder
commissioned.

Auto reclosure function is to be enabled for all 220


On 220KV feeders Auto recloser function
KV feeders. not used in APTRANSCO system.

31 400 kV Gajuwaka substation Distance protection relays to be replaced with -


Numerical Relay with inbuilt DR facility.

32 400 kV Gajwel Substation Replacement of PLCC panels of 400 kV


Ramagundam line to be done Under PGCIL scope.

315 MVA ICT-1 O/L relay setting of HV & LV side


to be reviewed Recommended settings are adopted

30
Distance protection relay setting to be reviewed
Recommended settings are adopted

315 MVA ICT-2 OLTC tap position indicator in


RTCC panel is to be made functional Rectified

Procurement of testing kit for testing switchyad Tan delta and universal relay testing kit
equipment . allotted
Replacement of Static differencial protection relays
provided for ICT-1&2 with numerical relays. Indent under preparation

33 400 kV Gajwel/Medak S/S / 400 315 MVA ICT-1 O/L relay setting of HV & LV to be -
kv side of 400/220 kv GAJWEL reviewed
SS

Distance protection setting to be reviewed -

315 MVA ICT-2 OLTC tap position indicator in -


RTCC panel is to be made functional

Replacement of Static type ABB make Differntial -


relays (RADSB) provided in ICT-1&2 by numerical
relays
34 400 kV GMR (Vemagiri) Overvoltage stage-1 protection to be made Over voltage stage-1 protection is enabled
functional in Main-1 relays of 400 kV feeders. in main-I protection relay for both 400KV
feeders.
Over voltage stage 1&2 settings to be reviewed Over voltage stage-1 is enabled and stage-2
is revised.
Auto reclose to be made functional for 400 kV Auto scheme for both 400KV feeders was
feeders kept in auto mode.

31
All the Numerical Protection relays to be time
synchronized with as the GPS. Provision for GPS Indent under preparation
to be done.
Review of Power swing detection settings Power swing detection settings were
corrected as per approved setting.
Generator Transformer over current & high set
Generator Transformer over current &
settings to be reviewed
highset values was corrected as per
approved settings.

35 400 kV GMR Bordge SS (Gen) Distance protection settings, Powerswing block


Energy Ltd., BMPP, Kakinada settings to be reviewed for 220kV lines Settings are adopted as per
recommendations.

36 400 kV GVK Gautami Power Auto reclose scheme to be eanbled for both 400 kV
feeders. Auto recloser scheme was enabled.

Over voltage stage-1 time setting of line-2 to be Deviation has been corrected as per
reviewed APTRANSCO approved relay setting [refer
to letter CE/IPC/112/F(Tech.Limits)
D.No.30/06 dt.26.04.2006].
Provision for under frequency and df/dt protections U/F & df/dt protection features are not used
to be reviewed on 400KV feeders in APTRANSCO system.
37 400 kV SS only Lanco The relays settings to be reviewed -
Kondapalli Power Ltd. Phase-II

38 400 kV Jegurupadu SS & 220 Auto reclose to be made functional for 400 kV
kV Jegurupadu SS(Gen) feeders Auto recloser scheme is enabled.

O/V Stage-1 protection setting to be reviewed


The over voltage stage-1 setting is herewith
normalized as per recommanded setting
i.e., 110% (70V) for both lines.

39 400 kV Kalapaka Distance protection relays to be replaced with


Numerical Relay with inbuilt DR facility. Indent under preparation

32
40 400 kV Konaseema Gas Power Over current relay High. Set value of STGT to be The over current relay high-set value of
Ltd. reviewed STGT has been changed from 9.5 to 7.5.
Over voltage stage-1 time delay settingto be The over voltage stage-1 time delay of
reviewed 400KV line#2 has been changed from 4sec
to 5sec.
Auto reclose to be made functional for 400 kV
To implement auto reclose scheme for
feeders
400KV line-1&2 breakers technical support
is required from OEM which is awaited.

Provision for U/F & df/dt protection to be reviewed


U/F & df/dt protection features are not used
on 400KV feeders in APTRANSCO system.

41 400 kV Kothagudam TPP Configuration of SAS to be completed early for Procurement action will be made soon
Quick analysis of trippings. after getting approval from APGENCO
management.
Possibility of separate GPS for 400 KV Switch yard Procurement action will be made soon
control room to be provided after getting approval from APGENCO
management.
42 400 kV KTPS VI Possibility of separate GPS for 400 KV Switch yard Procurement action will be made soon
Switchyard/Paloncha - control room to be provided after getting approval from APGENCO
Kothagudem
management.
Directional Earth Fault settings of Lines may Letter addressed to APTRANSCO. Reply
reviewed on par with GT Back up O/C and Earth
Fault Relay.
awaited.
43 400 kV Kurnool (Nannur) Provision to be made for having different make
Substation distance relays for Main I & Main II protection for
Srisailam 400 kV feeders, 220 kV AP Carbides I & Indent under preparation
II, 220 KV Brahmanakottur feeder, Somayajulapalli
I & II

33
63 MVAR Bus Reactor (TEED-I) Siemens make,
Model 7UT613 the actual settings in "Power
Reviewed and recommended relay settings
System Data 2" is different from approved setting are adopted.
by APTRANSCO.

Pole Open Current for S1, S2 and S3 approved


setting is 0.10 and actual is 0.2. This is to be Reviewed and recommended relay settings
reviewed are adopted.

All 220 kV side LBB relay time setting adopted is


100 ms instead of approved setting (200 ms). This Reviewed and recommended relay settings
is to be reviewed. are adopted.

400 kV Kurnool (Nannur)-Gooty feeder Main - I


Protection on SEL-421, the "Out-of-step -
tripping/blocking" settings are different from Line pertains to PGCIL
approved setting. This is to be reviewed
All static relays are obsolete models which are
recommended for replacement with numerical Indent under preparation
relays
The existing DR's and EL are obsolete model and it
is breakdown condition, which is to be replaced Indent under preparation
immediately.
REL 100 ABB Make Distance Relay in 5 feeders
(400 kV and 220 kV APTRANSCO feeders) are
obsolete model needs to be replaced with new Indent under preparation
version

Time synchronisig of protection system through


GPS is to be provided unit for 400 kV and 220 kV Indent under preparation
protection system.
Proper/balanced load staggering for 48 V DC
Supply to be done. Rectified

34
44 400 kV Mamidipally & 220 kV Distance protection relays for 400 kV and 220 kV
Mamidipally substation feeders to be replaced with numerical relays Indent under preparation

protection settings for relays to be reviewed Protection settings are reviewed and
adopted settings are as per APTRANSCO
Station Event logger to be made available protection philosophy. (Already furnished to
Staion E/L made available

Analog meters & temperature indicators to be


replaced with Digital Meters Indent under preparation

Review of distance protection setting of Protection settings are reviewed and


transmission lines adopted settings are as per APTRANSCO
protection philosophy. (Already furnished to
SRPC)
45 400 kV Mehboobnagar Replacement of Static Relay like differential relay
Substation (RADSB) of ICT01, Bus bar protection relay Indent under preparation
(RADSS) with numerical relay

Adopted relay setting in 400 kV Line distance


relays, differential and O/C & E/F relay in ICT-3 is Reviewed and found OK
to be reviewed
DEF function in distance protection is found not
enabled which is to be enabled/ activated Enabled

Dead time for Raichur Tie CB for A/R function is


set to 2 sec instead of 1 sec. same to be rectified Reviewed and found OK

Event logger in Micro SCADA needs to be properly


configured. Also existing ABB make event logger
is learnt to be not communicating with relay other
than ABB make and also with ABB make REL316 Indent under preparation
relay. Hence upgrading the event logger to be
done

35
ABB make distance relay of Type REL 316 to be
replaced Indent under preparation

Overflux relay setting of ICT-1 on HV side to be


reviewed Reviewed and found OK

Synchronising panel to be made functional


Equipment to be tested

PLCC protection codes to be tested for Raichur-


Carrier protection equipment available and
Veltoor line working (PGCIL scope)

46 400 kV Srisailam Power setting for excess power condenser mode Setting provided as per practical
relay in unit protection is to be reviewed requirement

Time setting of Dead Machine protection Relay to Setting provided as per practical
be reviewed. requirement
Setting of stub protection function in distance relay Same is informed to APTRANSCO and
to be reviewed the Settings issued by APTRANSCO
are adopted.

Timing of Zone-2 Relay setting for Nunnar, Same is informed to APTRANSCO and
Mamidapally and VTP-S to be re examined the Settings issued by APTRANSCO
are adopted.
Distance protection setting of Main-II Distance Fund mobilisation proposal is put up to
relay to be re-examined. board and procurement action will be
made soon after getting approval

Numerical relays with inbuilt D.R function to be


provided -do-

Disturbance recorders (ABB Make Indactic) to be Purchase order placed for new DR
made functional evaluation unit and will be
commissioned soon after procurement.

36
Station Event logger to be time synchronised with Purchase order placed for the same
GPS. Provision for GPS to be made. and will be commissioned soon after
procurement.

Static Bus bar protection relay to e replaced with Purchase order placed for the same
numerical relay Relay. and will be commissioned soon after
procurement.
Generator Protection id displaying only fault data Fund mobilisation proposal is put up to
records, but no graphical representation with time board and procurement action will be
resolution upto milli sec. related to the made soon after getting approval
disturbances. Same to be reviewed
provisions of GPS to be done for time Purchase order placed for the same
synchronizing of protection system and will be commissioned soon after
procurement.
APTRANSCO

Earth resistance measuring instruments to be procured


made avilableis available.
Unhelathy PLCC protection couplers to be rectified will be replaced in consulation with
APTRANSCO
47 400 kV Vemagiri substation Provision for Under frequency and df/dt protection Under frequency & df/dt protection is not
to be reviewed implemented on 400KV syatems in
APTRANSCO.

37
Karnataka - TRANSCO/ GEDCO/ IPP

1 220 kV Allipura Substation - All 220 kV line and bus coupler C&R panels The old C&R panels are being
BELLARY distance relays are retrofitted with ABB REL511 replaced by new panels. The tendering
relays & REL670 respctively, but the existing process is completed. Purchase order
panels back-up electromechanical relays are very is issued to M/s ER for supply of 220kV
old and sluggish, most of the TS relays are not control panels for Alipur Sub Station.
working properly, announciation not in working
condition. replacement of the relay panels.

For both transformer protection relay setting Attended


adopted differs with the recommended setting
same should be reviewed and adopted.

No PL carrier voice communication available. Attended

For Ragulapadu line carrier inter tripping should be APTRANSCO has to confirm the
restored. availibility of equipments at
Ragalapadu.

For 100MVA-I No REF protection available and The C&R panel is being replaced.
over flux relay should be restored.

Bus coupler relay setting for lines differ with Attened


recommended setting same to be reviewed and
adopted.
2 220 kV Ambewadi RS ICT-1 220 kV side B-phase LA counter is defective
Attended

220 kV Narendra 1 & 2 lines LA counters are not


available Attended

38
Main-2 protection is not available for all the 220 kV
lines. 220kV control and relay panels with
main-1 and main-2 distance protection
are being provided under R&M works.

ICTs 1 & 2 some of the fans are not in working


condition. Attended

The ICT-2 Y phase LA counter is not available.


Attended

The 110 kV LA counters not available for both ICT


1 & 2. Attended

The Event Logger and GPS is not available.


Included in R&M works

3 220 kV BTPS Dead Earth fault in 220 V DC set 1 & 2. Earth Fault in 220 V DC circuit is traced
and rectified.

relays not Synchronised with GPS. The worksynchronization of GPS will be


taken up shortly.

A/R Scheme for 220 kV Lines not available for For implementation of A/R scheme in
lines. 220 KV lines,M/s Alsthom is being
contacted. In consultation with the firm
the work of implementating A/R scheme
will be taken up.

4 220 kV BWSSB, CWSS Synchronising facility is not available. M/s BWSSB is insisted to provide the
Pumping Station, TATAGUNI same.
5 220 kV Gerusoppa Dam Power Different type of Numerical Distance Protection is Preparation of tender specification &
House to be provided as Main-II in place of Static Over obtaining administrative approval is
Current and Earth Fault Protection. under progress.

39
6 220 kV HAL Event logger is not available.

In CB two Nos. of trip coils energised from one DC


source only.
The DPR prepared for renovation and
For line protection, main-1, numerical distance upgradation of protection systems of all
relay has been provided & electromechanical 220kV and above voltage class sub
relays are used as main-2 protection. stations is revised since for sub stations
like Somanahally, Hoody etc work is
7 220 kV Hebbal Main-II protection is not available. However, already awarded to the turn key
electromechanical relay used as back up agencies. Attending protection audit
protection. observations at such stations will be
taken care under R&M works. For
LBB relays not available. remaining stations DPR is finalized and
tender is being floated by KPTCL.
8 220 kV Hebbal - A Station Main-II protection is not available. However,
electromechanical type backup protection relays
have been provided.

9 220 kV HRS Hoody Substation Main-II relays not available in all 220 kV feeders. 220kV control and relay panels with
The same to be provided. main-1 and main-2 distance protection
are being provided under R&M works.

10 220 kV HSR Layout Main-1 protection is Distance Relay and Main-2 Included in the renovation and
protection is Back up relays with OCR & EFR. upgradation of protection system works

Bus Bar protection relay is out of service, the same Included in the renovation and
to be put back to service for protection. upgradation of protection system works

DC Charger-I, the earth reference point to be


rectified/checked. Attended

40
On 09.10.2012 for the 220 kV Hoody Line fault, the
transformer-1 HV & LV tripped. The relay setting
Attended
to be reviewed.

11 220 kV ITPL Substation DC Main battery, +ve ground to be rectified.


Attended

PLCC / Protection Coupler not in service. The


same to be put into service. Attended

12 220 kV JSW ENERGY The over voltage stage - 2 and stub protection
(JINDAL) Substation functions for 400 kV lines to be enabled Attended

13 220 kV Kadakola protection system to be time synchronized with Included in the renovation and
GPS upgradation of protection system works

14 220 kV Kadra (Gen) Carrier protection is out of service for Karwar 1 & 2 Commissioned
feeders

Main-1 Distance protection (SHPM101) is not in Procurement is under progress


service due to power supply module problem for
Karwar 1 & 2 feeders
Double earthing of all the supporting Sufficient space for earthing is not
structures/elements is to be ensured. available. Hovever the work will be
taken up at the earliest.

Neutrals of generating transformers and LAs are to Sufficient space for earthing is not
be exclusively earthed. available. Hovever the work will be
taken up at the earliest.

15 220 kV Kodasalli S/S (Gen) Carrier protection is not in service for all feeders Commissioned
(the real time testing is pending).

41
16 220 kV Kolar Synchronisation facility not available Included in the renovation and
upgradation of protection system works

DR and EL not provided. It is suggested that DR


and EL to be provided with time synchronisation

17 220 kV Lingapura, Munirabad Surge monitor needs to be provided for Jindal


Attended. Also, LA s are provided to
feeder
all 220kV lines.
Only one core of CTs is used for both main and
B/U relays for all feeders except Jindal 1 & 2

GPS clock is not available

Synchronisation relay is not working R&M work is awarded to M/s Alstom


T&D India limited vide KPTCL LOI No.
For all feeders 2 O/C and 1 E/F relay as B/U CEE/T&PSEE(E)/EE-T1/T-3/9682-706;
protection can be replaced with distance scheme 9707-21; 9722-36 dated 4.03.2014.
mostly numerical relay is recommended.

New CTs and CVTs available at yard needs to be


commissioned at the earliest.

18 220 kV Lingasugur All 220 kV line and bus coupler C&R panels, The work of replacement of old C&R
distance relays are retrofitted with ABB REL511 panels will be taken up upon supply of
relays & REL670 , but the existing panels back up new C&R panels
electromechanical relays are very old and sluggish,
most of the TS Relays are faulty, annunciation not
working, hence it is suggested to replace the
panels at the earliest.

Capacity test and curative discharge needs to be


done. Attended

19 220 kV Naganathapura R/S In Bus bar protection relay Master Card is faulty,
sent for repair to M/s. ERL. Attended

42
Main-1: Numerical Distance Protection and Main-2
is Back up protection with OCR & EFR. Included in the renovation and
upgradation of protection system works

20 220 kV Nagjhari Power House The LBB relay time & current are set at 1.5 sec & The LBB time & current is set at 1.5
0.2 A for all feeders and generating transformers. second 0.2 amps are reset to 0.2
seconds and 0.2 amps now.
21 220 kV Narendra SS ICT-1&2 220 KV LA counters are not available.
Attended

ICT 1&2 Remote Temperature Indicators are not


available. Attended

ICT 2 MOG is filled with some liquid content and it


needs to be rectified. Attended

The 220 KV Belgaum lines 1 & 2, Hubli Lines 1 &


2, Ambewadi Line-1 and Haveri Line-2 LA counters LAs are provided and in working
are not available. condition. Surge counters are being
provided.

The 220 KV Belgaum lines 1 & 2 Wave Trap is


found to be bypassed and it needs be rectified. Attended

Main 2 protection is not available for all the 220 KV


lines.
Included in the renovation and
Separate Event Logger, Disturbance Recorder and upgradation of protection system works
GPS is not available.

22 220 kV NRS Rajajinagar Event logger and DRS not available for Peenya & Included in renovation and upgradation
Vrushabavathi Lines. of protection system works

Annunciation panel for Peenya line & Attended


Vrushabhavathy line are not in working condition.
The same to be made available.

43
Winding/Oil temperature indicator are not in Attended
working condition. The same to be made in
working condition.
Main II Distance protection Relays for all 220 Kv Included in renovation and upgradation
feeders is not available & the Protection Coupler of protection system works
for Peenya & Vrushabavathi Lines are not
available.

23 220 kV Peenya, Bangalore GPS, Disturbance recorder and event logger are
not available and same to be provided. Control
panel annunciation not in working condition except
transformers
Is being covered under R&M works
Main-II Distance protections were not propvided in under Peenya.
all 220 kV feeders and PLCC/Protection coupler
was not provided except 220 kV Hebbal feeder

DC negative to earth is persisting and same to be


complied Attended

24 220 kV Raichur TPS 220 V DC earth fault persisting negative dead Negative dead ground is removed.
grounded Partial ground is present with following
voltages. +ve w.r.t ground voltage is
+140 V -ve w.r.t ground
voltage is –90 V

Old electromagnetic relays can be replaced with Budget proposal is made for the year
numerical relays. 2014-2015 budget. Procurement
process will be initiated after approval
of budget.

44
LBB Relay RAICA RXKL1 setting for ICT-II is kept ICT-2 LBB relay setting: Existing
at 50 mA. RXIB24 module (with 50 mA setting)
was replaced with New RXIB24 module
(200mA setting) on 15-02-2013.

25 220 kV Receiving Station, For Main-II distance relays preferably numerical


Yarandahalli, Bangalore relays are not available in all 220 kV feeders, the
same to be provided. Included in renovation and upgradation
of protection system works

26 220 kV Sharavathi SS (Gen) LBB relay timing is observed to be 0.7 sec which is LBB timing was kept at 200
high, can be reduced to 250 to 300 m.sec in msec.However at present the existing
coordination with pole discrepancy relay of breaker. LBB protection panel is removed and
LBB protection will be enabled in new
Bus bar protection panel which is being
commissioned.

Feeders with same Make & Type relay as Main-I & Tendering work is under progress for
Main-II should be changed with different procurement & commissioning of
Make/Type relays for Main-I & Main-II. different make & type of relays for main
I & Main II.

Feeders having O/C and E/F relays as Main-II to The same will be carried out during
be replaced with distance relays for good implementation of different type & make
protection coordination on 220 kV Grid. relays for main I & Main II.

Carrier protection should be kept in service for the carrier protection is provided for all
feeders having no carrier protection. feeders.Protection panels and
healthiness of the same can be
confirmed after ascertaining healthiness
of PLCC equipment from PLCC division
of KPTCL.

45
DC earth leakage should be arrested on top priority Tender action is under final stage for
to avoid spurious trippings due to DC earth the procurement of online DC earth
leakage. leakage tester.However right now
efforts are being made to isolate DC
earth leakage whenver unit/lines are
shutdown.

Substation GPS to be connected to event logger -


and protection relays for correct recording of the
sequence of events.

27 220 kV Shimoga Protection System shall be synchronised with GPS


Time
Included in renovation and upgradation
Feeders having O/C and E/F relays as Main-II to
of protection system works
be replaced with distance relays

28 220 kV Sir M.V. GIS Station In CB two Nos. of trip coils energised from one DC Included in renovation and upgradation
source only. of protection system works

29 220 kV SUBRAMANYAPURA protection system to be time synchronized with Included in renovation and upgradation
GPS of protection system works

30 220 kV T. K. HALLI To provide GPS synchronisation for 220kV Included in renovation and upgradation
protection system. of protection system works

31 220 kV Varahi (VUGPH Electromechanical directional OCR & EFR relays Under Process
Hosangadi) (Gen) are existing as back up protection for 220 kV line
feeders. Different type of numerical distance
relays should be replaced in place of
electromechanical relays.

Time synchronisation of the distance relays with Under Process


GPS may please be reviewed.

46
32 220 kV Vrushabavathi 220 kV Lines provided with Main I only, Main II
Substation protection to be provided.
Included in renovation and upgradation
GPS to be procured and installed for time of protection system works
synchronisation of protection system.

33 400 kV BTPS High setting for the bus bar differential protection The settings will be reviewed in
i.e. 325 V. consultation with OEM.

A/R Selection switch is kept in non auto mode for The operation of Auto reclosure relays
all 400 kV lines. of most of the lines are found to be not
satisfactory.OEM of the relays M/s
Alsthom is being contacted for
rectification works.The firm is not
responding positively.However the firm
is being oersued to take up rectification
works of A/R relays immeditely.Once
the relays are rectified,breakers will be
tested for A/R operation and selection
switch will be kept in Auto mode.

Dead 220 V DC Earth fault for both sets i.e. Earth fault in 220 V Dc circuit is traced
Positive to Earth 235 V. and rectified.

GPS time synchronisation for all the relays & DR GPS time synchronization for relays of
not carried. unit 2,Hiriyur1 & 2 & Disturbance
reorder is implemented.The time
synchronization of other unit & lines will
be completed shortly.

47
Pole descripency relay setting kept at 0.1 Sec for A/R scheme is yet to be commissioned
all the lines. for 400 KV lines.Hence A/R selection
switch is kept in non auto mode.The
operation of A/R relays are found to be
inot satisfactory.Action for its
rectification is under progress.On
commissioning of A/R Scheme PD relay
will be kept at 0.1 sec.

34 400 kV Guttur Event logger and Time synchronisations facilities to


be made available Action is being taken to provide GPS
and event logger facility at Guttur
through M/s Alstom.

ICT-1 differential, bus bar relays and some of 220


kV lines distance relays are static type relays and Replacement of static relays are
are not having the disturbance recorder facilities. included in the renovation and
Replacement of the same with numerical type upgradation DPR.
relays
SOTF time delay has observed high and same to
be reviewed as per the requirements. Reviewed

35 400 kV Hoody Substation Main-II protection not provided in 220 kV feeders 220kV control and relay panels with
instead Backup protection are provided. main-1 and main-2 distance protection
are being provided under R&M works.

36 400 kV Nelamangala & 220 kV Main II distance protection were not provided in all
Nelamangala 220 kV lines and
Included in renovation and upgradation
of protection system works

48
PLCC/Protection Coupler were not provided except
Nittur & Dabuspet lines
Attended

Separate Event Loggers are not available, GPS


are not synchronised with SAS & Distance Attended
Protection Relays.
Main II relays not in service in 400 kV Hassan line,
400 kV Talaguppa line & 400 kV Hoody line-1 and Main-2 relay of Talaguppa line is
the same to be made available in the above replaced and for Hassan and Hoody-1
feeders. line procurement of relays under
process.

37 400 kV Raichur TPS SS (IS) 220 V DC earth fault persisting with leakage Located the D/C earth fault by availing
current of 15 mA services of M/S Taurus Powertronics
Ltd,Bangalore.The earth fault found in
ICT -2 DC Source-2 circuit.The same
will be isolated shortly.

PD settings for Munirabad, BTPS and Timers will be replaced & settings will
Mahboobnagar kept at 0.1 sec be changed as per SRPC norms during
line shutdown.

RTPS-Munirabad line Zone-II setting (26.880 Ohm) The relay settings for all the 400 KV
is more than Zone-III (26.44 Ohm) lines at RTPS have been reviewed &set
in the presence of PGCIL & KPTCL
th th
staff on 13 & 14 of March 2014.Now
the existing settings for munirabad line
are,Zone 1=12.76 ohms,Zone 2=21.6
ohms,Zone 3=24.63 ohms & Zone -4
(reverse)=6 ohms.

49
No fault locator working for Munirabad and The process of retrofitting
Mehboobnagar lines electromechanical relays with
Numerical version for both the lines is
under progress.The numerical relays
will be incorporated with fault locator.

DR communication is not working for Munirabad The process of retrofitting


and Mehboobnagar lines electromechanical relays with
Numerical version for both the lines is
under progress.The numerical relays
will be incorporated with fault locator.

DG set is not extended to 400 kV SS Action is being taken up.

Old electromagnetic relays can be replaced with Replacement of old Electromechanical


numerical relays. relays with Numerical relays has been
completede for RTPS-BTPS line &
commissioned on
17.03.2014.Budgeteory offer received
from a firm for the replacement of Old
electromechanical relays with
Numerical version for Mehaboobnagar
line,ICT-1& ICT-2 , the same is under
progress.

38 400 kV UPCL The extension of permissive trip to Hassa SS in the


event of O/V trip also at Udipi end needs to be
verified & rectified at Udipi end. Attended

39 220 kV Munirabad PLCC system is not functional for 220kV lines


-

50
Bus coupler distance protection to be replaced with
numerical relay -

51
KSEB

1 220 kV Areacode S/S The existing Main-1 (Electrostatic Quadramho)


Distance Relays should retrofitted with latest
version Numerical Relays for easy and quick Done
analysis of the faults.

Over flux protection is not available 220/110 kV,


160 MVA Transformer. Done

2 220 kV Brahmapuram Main-2 relay is not available inall 220 kV feeders.


Substation Only backup protection relays are provided. Done

Protection couplers are not provided in 220 kV


AMBR 1 & 2 and 220 kV BRKL - 1 &2 feeders Under Progress

Ratio test on CTs are done at lower currents only.


Higher capacity not done due to non availability of
Under Progress
kits with sufficient capacity.

Separate DC ground fault annunciation (+ve to


GND & -ve to GND) to be provided. Done

GPS & Event logger is not available.


-

3 220 kV Edamon SS Zone 3 setting not common for all feeders.


Done

Carrier inter tripping not available for SBEM 1, 2 &


3 feeders. Done

Main 2 distance protection for EMPC 1 feeder not


Under Progress
available.

52
LBB not in service for SBEM 2, 3 and EMPC 1
-

4 220 kV Idukki HEP Provision for measuring earth resistance to be would be be considered during
explored. renovation period
LBB protection for all Circuit Breakers shall be
included. Under Progress

Automatic change over facildity shall be made


available for 110 V Switch Yard Battery system. Under Progress

Main-II Distance protection shall be propvided for


feeders Under Progress

Distance Relay with Quadrilateral characteristics


shall be provided for high resistance faults Under Progress

All Electro Mechanical Relays to be replaced with


modern numerical relays. Under Progress

5 220 kV Kalamassery Substation Main-2 relay is not provided on 220 kV BRKL-1


feeder. Backup relays are provided in all feeders Done

Protection couplers are not provided in 220 kV


BRKL-1 & 2 feeders Under Progress

CT ratio tests are done at lower currents only.


Higher capacity not done due to non-availability of Under Progress
kits with sufficient capacity.
GPS & Event logger is not available.
Under Progress

Bus-bar protection is not available. The same to


be provided. (Material to be received)

53
6 220 kV Kaniyambetta S/S The 220 kV line's Main I (Electrostatic
QUADRAMHO) Distance Relays should retrofitted
Under Progress
with latest version Numerical Relays for easy and
quick analysis of faults.
7 220 kV Madakkathara 1 phase auto reclosing to be provided for 220 kV
feeders. Done

8 220 kV New Pallom Switching Resistance reaches to be examined for each zone
Station of protection instead of setting it as a commoin
Done
parameter as in the 220 kV New Pallom-
Kayamkulam 1 & 2.
Load encroachment impedance and the loadability
of the relay to be examined depending upon the
Done
line length and loading nof the feeder.

Providing of stub/EFP protection to be examined


for 220 kV lines. Under Progress

For 220 kV Busbar protection check zone to be


reviewed to take it from a separate PS class core
to have additional security to prevent inadvertent -
tripping of bus zone protection due to main core
saturation.
The carrier aided trip to be examined to have
different channel for main-1 and main-2 protection
Under Progress
as twin channel is available in protection coupler at
different frequencies.
Delay in operating time for zone-2 and zone-3 to
be reviewed to be set at 350ms and 800ms
respectivedly as per SRPC & PGCIL direction, Done
otherwise ensure setting to be identical for both
local and remote end.
Enabling functionality for both main-1 and main-2
relay to be reviewed. Done

54
220 kV Idukki-New Pallom feeder has main-1 static
version relay and main-2 has overcurrent relay
which to be considered to be replaced with Under Progress
numerical distance protection relay.

9 220 kV Palakkad S/S Relay settings of LBB to be checked and corrected


as per norms. Done

Back-up relay in service in all 220 kV feeders


Done

Main-2 relay and PLCC are not available in all 220


kV ELPK-1 and ELPK-2 feeders.
(Already completed for ELPK 1 &2)

CVT ratio is beyond permissible limit in R and Y


phases of ELPK-2 and Bus-1 CVT Done

10 220 kV Pallom Load encroachment impedance and the loadability


of the relay to be examined depending upon the
Done
line length and loading nof the feeder.

Providing of stub/EFP protection to be examined


for 220 kV lines. -

Possibility of providing different make distancve


protection relay for main-1 and main-2 protection to
Under Progress
be explored.

The carrier aided trip to be examined to have


different channel for main-1 and main-2 protection
as twin channel is available in protection coupler at Done
different frequencies.
Enabling functionality for both main-1 and main-2
relay to be reviewed. Done

55
ANNEXURE III (58/59)

220 kV Sabarigiri-Pallom feeder protection is


proposed to be replaced with numerical relay
Done
protection system may6 be expedited.

Constructing of oil sump adjacent to the


transformer at suitable location to be explored for
collecting of oil in the case fire brokes out in the Under Progress
case of emergencies.

11 220 kV Pothencode UFR setting needs to be changed as per


recommended setting. Done

Galvanizing to be done for the supporting


structures in the 220 kV switchyard. Under Progress

Some of the CTs error is found above he


recommende value. Retesting is required. Done

Control Panel for transformer 1 & 2 numerical relay


to be provided.
(Procurement initiated)

12 220 kV Sabarigiri Moozhiyar Earth resistance value is found to be on higher


HEP side. Remedial measures shall be taken. Under Progress

Even though two 110 V DC sources available,


redundancy for protection system not ensured. Under Progress

48V DC positive earthing not proper in the carrier


communication panel and also redundancy not Under Progress
ensured.
Main-II independent distance relay not available for
all the lines. Under Progress

56
ANNEXURE III (59/59)

Line distance relays zone-3 and zone-4 settings


are found to be same but timings are different. Under Progress

Some of the isolators not able to be operated from


SCADA PC. Under Progress

66/11 kV, 4MVA Transformer CB closing voil taking


50A approximately for operation, hence it shall be -
replaced.
High resistance fault are frequent in these lines, so
lines tripping on back up E/F protection for the in
zone line fault. It shall be avoided by providing Under Progress
carrier aided earth fault protection.

LBB protection pickup current is less so it is to be


compared with line charging current and set above
it and LBB time delay to be reduced. Under Progress

57
ANNEXURE IV (1/17)
ANNEXURE IV (2/17)

Discussions held on 28 th May 2014 on the observations of KSEB on different SPS


Schemes implemented post synchronization in WR & SR.

SPS 1 & 3:

It was explained that proposed load relief from the states could not be solely
based on their demand. Usage of ISTS network was also a very important
parameter. Though demand met could be lower, relative usage of ISTS network
in meeting this demand was also to be borne in mind. Another aspect in viewing
the same would be the ISGS allocation /allocation from Talcher-II station of NTPC
and total import ratios of SR beneficiaries.

It was therefore agreed that the existing scheme of load relief be retained. The
matter would be reexamined after commissioning of second circuit of 765 kV
Raichur-Sholapur link and experience post commissioning of the same.

To minimize repeated inconvenience to the same set of consumer on account of


SPS operation, it was suggested that states could come out with suitable schemes
for round robin/rotational load shedding. This would help ensure equitable
sharing of effects of SPS operation.

SRLDC observed that efficacy of the rotational load shedding needed to be


studied in real time operation. Hence, parallel operation for a couple of instances
so as to ascertain actual relief and validation would need to be done before any
migration to the new scheme. Further, there should not be any time delay in
obtaining the load relief. KPTCL informed that the maximum time limit to obtain
the relief would be less than 1000 milli second.

1
It was noted that the number of SPS operations in Southern Region had reduced
of late.

SPS 2:

It was noted that NLDC had already advised blocking of this scheme.

SPS 3:

The matter had been discussed in the Special Meeting held at Hyderabad on 18 th
January 2014. In that Meeting, the need for SPS operation in Southern Region to
meet eventuality of loss of import due to tripping of 765 kV line had already been
discussed and agreed.

POWERGRID was requested to expedite commissioning of this proposed SPS in


the interest of system security.

SPS 4
It was observed that SR Grid was presently connected with WR Grid through
single 765 kv line. Hence, all loads in SR were equally sensitive to the flow on 765
kV Raichur-Sholapur line. As regards load aspect, the same has already been
covered under SPS 1 & 3.

SPS 5 & 6

It was agreed that the matter regarding appropriate load shedding in


Maharashtra system would be taken up with NLDC and WRPC for necessary
compliance.

2
SPS 7

After discussions, it was felt that for flow exceeding 1,500 MW from SR to NEW
Grid, need for 765 kV line tripping may need examination. It was felt that NLDC
could be requested to carry out necessary studies to further examine this
suggestion.Ability of SR Grid to absorb the jerk of sudden loss of export of power
greater than 1,500MW could also be referred to NLDC.

SPS 8 & 9

It was explained by SRLDC that choice of loads had already been made
appropriately. The loads had been identified on the downstreamportion of the
lines so as to give proper relief.

KPTCL and APTRANSCO confirmed the above.

SPS 10

It was clarified by SRLDC that signal 3 had been devised on account of the
extended mode of operation of HVDC.(2500 MW for 10 hrs a day)Earlier, there
was uncovered load of about 500 MW not covered in any load relief scheme. This
was expected to be absorbed by the SR Grid since there was no interconnected
AC link with NEW Grid. However, after commissioning of 765 kV line, any pole
outage would result in increased power flow on the AC inter connection. Hence,
the two conditions had been concatenated. In case the same was not done,
there could be operation of other SPS schemes on account of higher flow through
Raichur-Sholapur line and upstream line.

SPS 11

It was noted that separate loads for Kudankulam SPS had already been identified.

3
Other

Constituents desired that a comprehensive list of SPS Schemes along with the
operating logics be made available to them, since number of modifications had
been proposed/ implemented.

***********

4
ANNEXURE IV (16/17)
ANNEXURE IV (17/17)
ANNEXURE V (1/4)

a. Recommendations to be complied by April- 2014


S Recommendation The Anticip Agency Status 32nd PCSC
N meeting ated Deliberations
in which date of
the issue complet
was ion
Discussed
1 BUSBAR PROTECTION 21st April-14 TANT Pending TANTRANSCO
AT KAYATAR 110KV PCSC RANS informed that it
SUBSTATION held on CO would be
25.06.201 implemented by end
3 of May 2014.
2 Bus Bar protection 26th April-14 APTR pending APTRANSCO
Scheme at Ragalapadu PCSC ANSC informed that it
Substation (21.11.201 O would be
3) implemented by the
end of Nov 2014.
3 PROVIDING DR AND 23rd PCSC April-14 APTR Pending APTRANSCO
EL-MAMIDAPALY held on ANSC informed the DR is
27.08.2013 O got repaired and
working .

b. Recommendations to be complied by May – 2014


SN Recommendation The Anticip Agency Status 32nd PCSC
meeting in ated Deliberations
which the date of
issue was complet
Discussed ion
1 48 V DC SUPPLY 17th PCSC May-14 KSEB Pending KSEB informed that
REDUNDANCY NOT (26.02.201 it would be
AVAILABLE- 3) implemented by end
EDAMON of July 2014.
2 EARTH PITS at 17th PCSC May-14 KSEB Pending KSEB informed that
EDAMON (26.02.201 it would be
3) implemented by end
of September 2014.
3 Main2 distance 17th PCSC May-14 KSEB - KSEB informed that
protection for EMPC#1 (26.02.201 it would be
feeder not available- 3) implemented by end
Edamon of May 2014.
4 DG set at Edamon 17th PCSC May-14 KSEB Pending KSEB informed that
(26.02.201 it would be
3) implemented by end
of July 2014.

1
ANNEXURE V (2/4)

c. Recommendation to be complied by June - 2014


S Recommendation The Anticip Agenc Status 32nd PCSC
N meeting in ated y Deliberations
which the date of
issue was complet
Discussed ion
1 The Main I and Main II 21st PCSC June-14 KPCL Pending KPCL to update the
Protection of Different held on status.
make-Sharavathy 25.06.2013
2 a. APGENCO to 27th PCSC June-14 APTR Pending APGENCO to update
consider usage of relays ANSC the status.
of different make for O/APG
Main –I and Main II ENCO
distance protection for
KPTS- Managuru line-2.
Relevant APTRANSCO

b. APTRANSCO to
review distance
protection settings of
KPTS- Managuru line-2
as it tripped for fault in
KPTS- Managuru line-1.

c. APGENCO to review
reverse distance
protection settings of
KPTS- Shapur nagar
Line.

d. APGENCO to enable
DEF Back Up protection
in all lines emanating
from KTPS.

e. APGENCO to enable
IDMT characteristics for
GTs and ICTs at KTPS
which is to be
coordinated with primary
protection.

f. APGENCO to review
the Overload settings of
Unit 4

g .DR at Khammam
Substation to be time
synchronized with GPS

2
ANNEXURE V (3/4)

h. APGENCO to review
bus bar protection
settings.

d. Recommendations to be complied by Sep - 2014


SN Recommendation The Anticipa Agency Status 32nd PCSC
meeting in ted date Deliberations
which the of
issue was completi
Discussed on
1 Replacement of OLD 21st PCSC Sep-14 KPCL Pending KPCL to update the
CBs at Sharavathy held on status
25.06.2013

2 COMPLIANACE OF 17th PCSC - Sep-14 KPCL Pending KPCL to update the


3RD PARTY AUDIT 25th PCSC status
REPORT-Sharavathy (26.02.2013
to
22.10.2013)

e. Recommendations to be complied by Nov 2014


S Recommendation The Anticipa Agency Status 32nd PCSC
N meeting in ted date Deliberations
which the of
issue was completi
Discussed on
1 •As the Plant was more 26th Nov-14 KSEB Pending KSEB to update the
than 25 years old, all yard status..
equipment need to be PCSC
replaced.
•Modification of Bus
Scheme to be carried out.
•The PCSC forum
recommended for the
modification of Bus Bar
protection scheme at
Idukki Substation. In the
event of bus fault the entire
substation should not be
affected. This would
improve the reliability and
security of the Idukki
Hydro Generating station.

3
ANNEXURE V (4/4)

f. Recommendation to be complied by Dec 2014


S Recommendation The Anticipa Agency Status 32nd PCSC
N meeting in ted date Deliberations
which the of
issue was completi
Discussed on
1 ONLY ONE BUS IS 17th PCSC Dec-14 KSEB Pending KSEB to update the
AVAILABLE, TRANSFER (26.02.201 status.
BUS SHALL BE 3)
PROVIDED-EDAMON

4
ANNEXURE VI (1/11)

SRLDC Proposal :df/dt relay settings


• Setting summary

• Significance of df/dt during large disturbance


– Southern Region separation

• Proposed setting
– Stage-1 : 49.9Hz & 0.1 Hz/sec
– Stage-2 : 49.9Hz & 0.2 Hz/sec
Mundra disturbance on 12th March 2014
ANNEXURE VI (2/11)

Constituent Observed Applicable Envisaged Actual Load Inadequate


df/dt in stages quantum of shedding (MW)
Hz/Sec Load Shedding reported in MW
in MW

Gujarat -0.31 I & II 1911 636 1257


MP -0.23 I & II 716 0 716
Chhattisgarh -0.17 I 64 0 64
Maharashtra -0.31 I & II 1167 334 1167
TPC -0.31 I & II 142 0 142
Total -0.31 4000 960 3040

§ Complete black out at CGPL Mundra (UMPP) due to tripping of all evacuating
lines from CGPL Mundra

§ Generation loss : 4030 MW (CGPL: 3750 MW + 280 MW wind)

§ Change in frequency : 0.67 Hz i.e. from 49.95 Hz to 49.285 Hz.

§ Load loss : 1110 MW was reported during the event out of which
§ Df/dt : 960 MW (Gujarat: 630 MW + Maharashtra: 330 MW)
§ SPS operation : 150 MW
df/dt setting N.R
All India UFR Status
49.2 Hz 49 Hz 48.8 Hz 48.6 Hz Total
Region STATES Remarks
Approved Approved Approved Approved Approved
in RPC Actual in RPC Actual in RPC Actual in RPC Actual in RPC Actual
Punjab 400 435 402 575 406 807 408 415 1616 2232

Haryana 308 366 309 417 312 0 314 0 1243 783

Rajasthan 390 1657 392 1659 395 0 397 0 1574 3316

Delhi 258 297 259 353 262 429 263 1049 1042 2128

UP 551 1393 554 987 559 1368 561 799 2225 4547
NR
Uttarakhand 77 90 77 100 78 0 78 0 310 190

HP 77 30.2 77 40.8 78 0 78 78 310 149

J&K 83 0 84 0 84 0 85 0 336 0

Chandigarh 16 0 16 0 16 0 16 0 64 0

Total 2160 4268.2 2170 4131.8 2190 2604 2200 2341 8720 13345

Gujarat 580 773 580 726 580 1117 580 1025 2320 3641

MP 460 468 460 450 460 460 465 490 1845 1868

Maharashtra 805 1108 810 1200 815 765 820 851 3250 3924

Chattisgarh 150 110 150 114 155 117 155 91 610 432
WR
Goa 25 25 25 25 100 0
UFR under
DD 10 15 15 15 55 0
Procurement
DNH 30 30 35 35 130 0

Total 2060 2459 2070 2490 2085 2459 2095 2457 8310 9865
All India UFR Status
49.2 Hz 49 Hz 48.8 Hz 48.6 Hz Total
Region STATES Remarks
Approved Approved Approved Approved Approved
in RPC Actual in RPC Actual in RPC Actual in RPC Actual in RPC Actual
Andhra Pradesh 809 1064 / 562 812 1172 / 594 822 1120 / 597 825 1130 / 581 3268 4486 / 2334 Max / Average

Karnataka 576 703 / 474 578 821 / 514 586 707 / 451 588 627 / 441 2328 2858 / 1880 Max / Average

Kerala 204 288 / 214 205 263 / 217 208 275 / 218 209 298 / 211 826 1124 / 860 Max / Average
SR
Tamilnadu 740 1098 / 740 744 932 / 745 753 1012 / 756 756 510 / 419 2993 3552 / 2660 Max / Average

Poducherry 21 29 / 21 21 20 / 18 21 39 / 28 22 24 / 19 85 112 / 86 Max / Average

Total 2350 0 2360 0 2390 0 2400 0 9500


All India UFR Status
49.2 Hz 49 Hz 48.8 Hz 48.6 Hz Total
Region STATES Remarks
Approved Approved Approved Approved Approved
in RPC Actual in RPC Actual in RPC Actual in RPC Actual in RPC Actual
Bihar 98 99 99 101 397 Full Quantum Implemented

Jharkhand 61 62 61 62 246 200

DVC 134 136 136 137 542.5 Full Quantum Implemented


ER
Odisha 181.5 183.5 184 186 735 700

WB( Incl CESC) 345.5 350 350 354 1399.5 Full Quantum Implemented

Total 820 0 830 0 830 0 840 0 3320

Arunachal Pradesh 5 3.5 5 0 5 0 5 0 20 3.5

Assam 55 54.5 55 61 55 59 55 57 220 231.5

Manipur 5 3 5 0 5 0 5 0 20 3

Meghalaya 15 15 15 15 15 15 15 15 60 60
NER
Mizoram 5 5.09 5 5.31 5 5.1 5 5.2 20 20.7

Nagaland 5 3 5 3 5 3 5 0 20 9

Tripura 10 11 10 10 10 14.5 10 12.5 40 48

Total 100 95.09 100 94.31 100 96.6 100 89.7 400 375.7
All India df/dt Status
Stage I Stage II Stage III
Total
49.9Hz & 0.1Hz/Sec 49.9Hz & 0.2Hz/Sec 49.9Hz & 0.3Hz/Sec
Region STATES Remarks
Approved Actual Approved Actual Approved Actual Approved Actual
in RPC in RPC in RPC in RPC

Punjab 430 430 490 490 490 490 1410 1410

Haryana 280 280 310 310 310 310 900 900


As per the
Rajasthan 330 330 370 370 370 370 1070 1070 NRPC
website
Delhi 250 250 280 280 280 280 810 810
UP 500 500 280 280 280 280 1060 1060
NR
Uttarakhand 70 70 70 70 70 70 210 210

HP 50 50 70 70 70 70 190 190

J&K 90 90 90 90 90 90 270 270

Chandigarh 0 0 50 50 50 50 100 100

Total 2000 2000 2010 2010 2010 2010 6020 6020

Gujarat 1006 1006 905 905 1001 1001 2912 2912


confirmed
MP 361 361 355 355 392 392 1108 1108 on the
special
Maharashtra 546 546 621 621 686 686 1853 1853
meeting of
Chattisgarh 27 27 37 37 120 120 184 184 WRPC on
16.12.13
WR
TPC 60 60 82 82 273 273 415 415

Goa
DD
DNH
Total 2000 2000 2000 2000 2472 2472 6472 6472
Bihar

Jharkhand

DVC
ER
Odisha NIL

WB( Incl CESC)

Total 0 0 0 0 0 0 0 0
Arunachal Pradesh

Assam
Manipur
Meghalaya
NER
Mizoram
Nagaland
Tripura
Total 0 0 0 0 0 0 0 0
49.5Hz & 0.2 Hz/sec 49.3Hz & 0.3 Hz/sec Total
Region STATES Approved Approved Approved
Remarks
Actual Actual
in RPC in RPC in RPC Actual
Andhra Pradesh 712 714 1767 1635 2479 2349

Karnataka 474 553 485-1036 792 1510 1345

Kerala 172 178 121-175 178 347 356


Under Progress.
SR It would be
Tamilnadu 624 completed in the 559 617 1183 617
first week of
January 2014
Poducherry 18 18 Nil Nil 18 18

Total 2000 1463 3537 3222 5537 4685


ANNEXURE VI (10/11)
Summary - All India UFR & df/dt Status
UFR Status df/dt Status
Region STATES
Approved Actual Status Approved Actual Status
Punjab 1616 2232 Fully Implemented 1410 1410 Fully Implemented

Haryana 1243 783 Partly Implemented 900 900 Fully Implemented

Partly Implemented -
Rajasthan 1574 3316 Scheme implemented 1070 1070 Fully Implemented
only at 49.2 Hz. & 49.0 Hz.

Delhi 1042 2128 Fully Implemented 810 810 Fully Implemented

NR UP 2225 4547 Fully Implemented 1060 1060 Fully Implemented

Uttarakhand 310 190 Partly Implemented 210 210 Fully Implemented

HP 310 149 Partly Implemented 190 190 Fully Implemented

J&K 336 0 Not yet implemented 270 270 Fully Implemented

Chandigarh 64 0 Not yet implemented 100 100 Fully Implemented

Total 8720 13345

Gujarat 2320 3641 Fully Implemented 2912 2912 Fully Implemented

MP 1845 1868 Fully Implemented 1108 1108 Fully Implemented

Partly Implemented -
Maharashtra 3250 3924 Load relief to be added 1853 1853 Fully Implemented
at 48.8HZ
WR Chattisgarh 610 432 Partly Implemented 184 184 Fully Implemented

Goa 100 0

DD 55 0 Not yet implemented

DNH 130 0

Total 8310 9865

Andhra Pradesh 3268 4486 / 2334 Fully Implemented 2479 2349 Partly Implemented

Karnataka 2328 2858 / 1880 Fully Implemented 1510 1345 Partly Implemented
AnnexureVI (11/11)
Summary - All India UFR & df/dt Status
UFR Status df/dt Status
Region STATES
Approved Actual Status Approved Actual Status

Kerala 826 1124 / 860 Fully Implemented 347 356 Fully Implemented
SR Partly Implemented -
Tamilnadu 2993 3552 / 2660 Load relief to be added 1183 617 Partly Implemented
at 48.6HZ
Poducherry 85 112 / 86 Fully Implemented 18 18 Fully Implemented

Total 9500
Bihar 397 Fully Implemented

Jharkhand 246 200 Partly Implemented

DVC 542.5 Fully Implemented


ER
Odisha 735 700 Partly Implemented

WB( Incl CESC) 1399.5 Fully Implemented

Total 3320

Arunachal Pradesh 20 3.5 Partly Implemented

Assam 220 231.5 Fully Implemented

Manipur 20 3 Partly Implemented

Meghalaya 60 60 Fully Implemented


NER
Mizoram 20 20.7 Fully Implemented

Nagaland 20 9 Partly Implemented

Tripura 40 48 Fully Implemented

Total 400 375.7


ANNEXURE VII (1/37)
ANNEXURE VII (2/37)
ANNEXURE VII (3/37)
ANNEXURE VII (36/37)
ANNEXURE VII (37/37)
ANNEXURE VIII (1/11)
ANNEXURE VIII (2/11)
ANNEXURE VIII (9/11)
ANNEXURE VIII (10/11)
ANNEXURE VIII (11/11)

You might also like