Minutes of the Meeting held on -- 5th june 2018 To: VL Indore


With - M/s Anant Spinning Mills Place: Mandideep cc: VL …../…..
Members Present: cc:VL-SHQ for SS
From Voltas Name LMW ID No Designation Signature
Ltd. Mr. Chintan Bansode 5000846 Service Engineer

Mr. Neeraj khandelwal Sr. VP.(Tech.)


From Mr. L. R. Nishad V.P. (maint.)
Customer Mr. vijay ojha Manager (maint.)

Period of Work
Model M/C No Type of Work Area of complaint
From To
LR9AX-SD 1-06-18 Till Now 01 --
5852,5853

Subject – project status as on 5th june 2018.

Phase-1
Running
Total Received power Bare
M/c Installed with Remark
m/c at site on Commissioned
material
LR9AX 13 13 13 13 13 13 All m/c Running.

Customer complain areas:-


 Suction Tube Chocking issue.
 Separator cut issue.
 Carrier belt got damaged of basket type tube loader in machine no. 1
 Proper RYC cleaning procedure required for Lycra process as same is not possible to do with supllied
gauge.
 Higher ipi LMW m/c in 20s KWCSY compare to KTTM RXI 240.

F :SOP:TMD:7.5.1:002:06 Page of 2 w.e.f 28.06.2012


Textile
Machinery
Division
CONTINUATION
SHEETS

Work done & Action plan:


 For suction tube we have taken the matter with LMW, further our observation was that the suction tubes
which are having any deformation at its mouth, is only leading to suction tube chocking. To insure the
same we had fixed a new set of suction tube at LHS side of mills m/c no. 5 on 17/5/18 and observed for a
week and found the chocking tendency at the LHS side was negligible. We are Awaiting the solution from
LMW.
 There were total 393 separator which were having the cut, FOC replacement for the same was organised.
The docket no. is 334938866 via TCI Express. Despatched on 22 may 18.
 We have raised the report for the belt damaged issue. Awaiting the Solution from LMW.
 We are working on the quality issues, we will update with the positive results.
 For RYC cleaning procedure, we have raised the report, we will update soon.

Phase-2

Running
Total Received power Bare
M/c Installed with Remark
m/c at site on Commissioned
material
Commissioning &
LR9AX 12 3 3 2 2 02 Pre-installation work is in
progress.

Support required from customer end:


 We request to complete the H-plant work for the 2nd phase machineries as the amount of fly in the dept.
is more.
 We request to follow the maintenance and Running in schedule for the better machine performance.
 A list of spare parts was handed over to the customer we suggest to procure the same.

F :SOP:TMD:7.5.1:002:06 Page of 2 w.e.f 28.06.2012


FOC component Status:

SR. No. Description QTY Docket No. Docket date Courier Name Status
1 Solenoid valve y31,32 1 334542036 12-Apr-18 TCI EXPRESS.. Received
2 Jockey pulley Assly 1 334544372 13-Apr-18 TCI EXPRESS.. Received
3 Lifting tape R-Rail 2 334544140 16-Apr-18 TCI EXPRESS.. Received
4 Spindle brake 48 334543952 20-Apr-18 TCI EXPRESS.. Received
V-XPRESS ( A
5 Front roller drive shaft 2 3821116 04-May-18 DIVISION OF VTRANS Received
INDIA LIMITED )
6 Jockey pulley 20 335350223 30-Apr-18 TCI EXPRESS.. Received
V-XPRESS ( A
7 Gripper + Assly 20 3821116 04-May-18 DIVISION OF VTRANS Received
INDIA LIMITED )
8 PLC module 1 40438392 24-04-2018 TCI EXPRESS.. Received
9 Ring rail Saftety Sensor 1 15327293450 26-Apr Bluedart
V-XPRESS ( A
10 Spindle brake 140 3827463 18-May-18 DIVISION OF VTRANS Received
INDIA LIMITED )
11 Separator cut 399 22-May-18 TCI EXPRESS..
12 Higher IPI 39 mm craddle 100
13 Suction Tube in new case 50 334938866 22-May-18 TCI EXPRESS..
14 door safety 2 334549924 19-May-18 TCI EXPRESS.. Received
15 door safety 1 334549924 19-May-18 TCI EXPRESS.. Received
16 Prximity M12 3 334543311 17-Apr-18 TCI EXPRESS.. Received
17 Emergency switch 1 334540581 09-Apr-18 TCI EXPRESS.. Received
18 Pannel door 1