Professional Documents
Culture Documents
PERT • CPM
Projects
A – 12 A F K
B – 9
C A 10
D B 10 Start C G Finish
E B 24
F A 10
G C 35 B D H J
H D 40
I A 15
J E,G,H 4 E
K F,I,J 6
St. Adolf’s Hospital
Activity Paths
I
Paths are sequences of
activities between a
project’s start and finish. A F K
A-I-K 33
A-F-K 28
B D H J
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
E
St. Adolf’s Critical Path
The longest path is the
critical path! I
A-I-K 33
A-F-K 28 Start C G Finish
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43 B D H J
Project Expected
E
Time is 69 wks.
Activity Time Estimates
PERT or CPM ?
CPM (Critical Path Method) Activity times are
certain, so only one time estimate for each
activity is needed.
◦ Decision making under Certainty
PERT (Program Evaluation and Review
Technique) is used when activity times are
uncertain. (Decision making under risk)
◦ It requires three time estimates for each activity.
(Best case, most likely time, and worst case)
PERT’s
Three time-estimates
OPTIMISTIC TIME: Best time if everything goes
perfectly when doing the activity.
REALISTIC TIME: Most likely time for the activity
PESSIMISTIC TIME: A worst-case situation
B + 4M + P
Expected Time = -------------------
6
In this example, the most likely time is given a weight of four, and the
other two times (pessimistic and optimistic) are each given weights of
one.
Risky activity times make the project length risky, so there is a need
for risk assessment based on the probability distribution of times.
(Standard deviation and variance are computed by the software.)
Activity Slack
Activity slack is the maximum length of time that an
activity can be delayed without delaying the entire
project.
◦ It is the difference between the earliest time we
can start an activity and the latest time we can
start the activity without delaying the project.
◦ The critical path activities have zero slack.
◦ For the St. Adolf’s Hospital project, 69 weeks is the
project length because 69 weeks is the longest
path.
◦ Project delays beyond the projected completion date
often involve penalties.
Activity Start and Finish Times
Earliest Start Time (ES) for an activity is the earliest finish
time of the immediately preceding activity.
Earliest Finish Time (EF) for an activity is its earliest start
time plus how long it takes to do it (activity time).
Latest Start Time (LS) is the latest you can finish the activity
minus the activity’s estimated duration.
Latest Finish Time (LF) is the latest start time plus the
activity time.
◦ The latest finish time is the same as the latest start time of the activity activity
which follows it. (Latest start and finish times for each activity are computed
starting at the project’s last activity completion time and working forward.)
Slack is the difference between the Earliest Start and Latest
start times for an activity (or earliest finish and latest finish
times.)
Earliest Start and Earliest Finish Times
12
I 27
0 A 12 12 F 22 63
K 69
12 10 6
12
C 22 22
G 57
Start Finish
10 35
0
B 9 9
D 19 19
H 59 59
J 63
9 10 40 4
9 E 33
24
© 2013 Lew Hofmann
Earliest Start and Earliest Finish Times
Path Time (wks)
12
I 27 The Critical Path
A-I-K 33 15 takes 69 weeks
A-F-K 28
A-C-G-J-K 67
A K 69
B-D-H-J-K 69 0 12 12 F 22 63
B-E-J-K 43 12 10 6
12
C 22 22
G 57
Start Finish
10 35
0
B 9 9
D 19 19
H 59 59
J 63
Critical Path 9 10 40 4
9 E 33
24
© 2013 Lew Hofmann
Latest Start and Latest Finish Times
(You start with the last activity and work toward the first activity)
12
I 27
48 15 63
A K
0 12 12 F 22 Latest 63 69 Latest
2 12 14 53 10 63 start 63 6 69
finish
time time
C
12 22 22 G 57
Start Finish
14 10 24 24 59
35
0
B 9 9
D 19 19
H 59 59
J 63
0 9 9 9 10 19 19 40 59 59 4 63
9 E 33
35 24 59
F 10 12 53 41
G 35 22 24 2
A
H 40 19 19 0 0 12 12 F 22 63 K 69
I 15 12 48 36 2 12 14 53 10 63 63 6 69
J 4 59 59 0
K 6 63 63 0
C
12 22 22 G 57
Start Finish
14 10 24 24 59
35
0
B 9 9
D 19 19
H 59 59
J 63
Activity Slack 0 9 9 9 10 19 19 40 59 59 4 63
Analysis
9 E 33
35 24 59
© 2013 Lew Hofmann
Analyzing
Cost-Time Trade-Offs.
There are always cost-time trade-offs in
project management.
◦ You can completing a project early by hiring more
workers or running extra shifts.
◦ There are often penalties if projects extends
beyond some specific date, and a bonus may be
provided for early completion.
Crashing a project means finishing the
project early by expediting one or more
activities.
◦ Not all activities can be shortened.
Project Costs
Total Project Costs =
direct costs + indirect costs + penalty costs
Direct costs include labor, materials, and any other
costs directly related to project activities.
Indirect costs include administration, financial, and
other variable overhead costs.
◦ These can be reduced by reducing total project
time.
◦ The shorter the duration of the project, the lower the
indirect costs will be.
Penalty costs are essentially late fees incurred for
going over the projected due date.
Minimizing Costs
We do cost analysis to determine the project
schedule that minimizes total project costs.
When crashing an activity or project, extra money
is spent on direct costs, but money is saved on
indirect costs and possible penalties.
A minimum-cost schedule is determined by
starting with the normal project time schedule and
shortening activities along the critical path until
the costs of crashing (direct costs) start to exceed
the savings in indirect costs and penalty costs.
◦ New critical paths usually appears while doing this.
St. Adolf’s Hospital
Minimum Cost Schedule
a. Determine the project’s critical path(s).
b. Find the activity or activities on the critical path(s)
with the lowest cost of crashing (shortening) per
week.
c. Reduce the time for this activity until…
a. it cannot be further reduced,
b. or another path becomes critical,
c. or the increase in direct costs exceed the savings that
result from lower indirect costs.
d. Repeat this process until the total project costs are
no longer decreasing.
Sophisticated project management software will do
this.
Of the five critical-path activities, the
contractor says D and H cannot be
I shortened. J is the least costly to
12 27
48 15 63
shorten at $1000 a week. Contractor
says it can be shortened to 1 week.
A K
0 12 12 F 22 63 69
2 12 14 53 10 63 63 6 69
C
12 22 22 G 57
Start Finish
14 10 24 24 59
35
B 9 D 19 H 59 J 63 Shorten from 4
0 9 19 59 weeks to 1 week
19
0 9 9 9 10 19 40 59 59 4 63
a m b Time
Optimistic Mean Pessimistic
Figuring Probabilities
Assume a PERT project critical path takes 40 days, and that
the variance of the critical path is 2.147
◦ You wish to know the probability of the project going over 42
days.
Compute the standard deviation of the critical path.
◦ The square root of the variance of 2.147 = Std. Dev. = 1.465
◦ POM/QM software gives you the variance of the critical path.
Compute the Z value: Z = (absolute time difference) / Std.
Dev.
In this example, Z = (42 days - 40 days) / 1.465 = 1.365
Look up the Z value of 1.365 in a Normal Distribution table
to get the probability of the project taking 42 days.
Subtract it from 100% to get the probability of going over 42.
.9139
Probability of
completing Probability of
the project in exceeding 42
42 weeks is weeks is 8.61%
91.39%
40 42
Project duration (weeks)
St. Adolf’s Hospital
A 69-week Project
z = 72 – 69 z= 3
11.89 3.44818
Z = 0.870 Look up Z value in normal distribution table
Look up the Z value (0.870) in the table of normal distribution.
.8078 or 80.78% is the probability of the project taking 72 wks.
Going over 72 weeks would be 100 – 80.78 = 19.22%
St. Adolf’s Hospital
Probability of Completing Project On Time
Normal distribution:
Length of Mean = 69 weeks;
critical path is = 3.45 weeks
69 weeks
Probability of
taking 72 weeks Probability of
is 0.8078 or exceeding 72
80.78% weeks is 0.1922
or 19.22%
69 72
Project duration (weeks)
PERT / CPM
ADVANTAGES