Progress Status Report
Aug, 2020

Ahmed Abdelfattah
Project Control & Planning manager
www.ahmed-Fattah.com
ABC Building
Progress Status Report
Aug, 2020 About
Located in the heart of Hamilton, New Zealand, this redevelopment
transformed an old run-down site into a green, resilient Grade-A commercial
office space for Genesis Energy.
Genesis Energy needed a new home that would bring together 600+ staff
spread across different offices in Hamilton CBD. And they wanted to re-use an
existing site in a cost-effective, sustainable way.
Once an old supermarket, the redevelopment converted two storeys of retail
space into new offices and an indoor carpark with electric vehicle charging
points. An additional three-stories building was added next to the existing
building, providing further office space, a café and central amenities.
The building services design for the project includes integrated energy-
efficient heating and cooling, ventilation, power and lighting systems, and a
standby (Generator) power system which are flexible for future expansion.
The mechanical ventilation system uses efficient direct expansion (DX) heating
and cooling of outdoor air. The volume of air is CO 2 controlled to a variable
speed fan to reduce energy use even further. To minimize heat loss out the
foyer door, an air curtain system was also installed.
An air cooled chiller provides chilled water to cool the spaces with a variable
flow pump that adjusts to maximize efficiency.
With the building hosting a new remote control room for some of Genesis
Energy’s power stations, a generator backed-up power supply was critical to
ensure the building will remain operational in a power-outage or emergency.
The electrical infrastructure was designed to accommodate a secondary
standby generator in event of the primary generator failing to start.
Now together in the heart of Hamilton, Genesis Energy staff can enjoy a
vibrant new workspace and the surrounding services and facilities of the
central CBD.
ABC Building ff
Progress Status Report k-o
ic
Aug, 2020
e c tK
j g n
Pro etin uctio
Me n str
- Jul-19 g Co
09 a r tin
St rks
Wo P
-19 f ME
A ug g o
01- a r
St rks
tin g
i shin
Wo F in
20 of
Jan ng e

Milestones 16- rti ctur


Sta rks Str
u
Wo no
f
eb -20 e tio
F l
01- mp
Co orks a pe
sc
W a nd
0 L
o v-2 g of
N rtin
09- t a
S rks
w o n g & orks
a r-21 g Testi ing w
30-
M
a rtin ission ate
t
S mm n D
C o l e tio
pr -21 Co mp
A
15- j ect
Pro
1
ay-2
M
31-
ABC Building
Progress Status Report
Aug, 2020
Project Scope
ABC Building Project

Engineering Construction

Shop Drawings Material Phase 1 Phase 2 Externals

Objectives: Insulation
Structure External Wor
The Works comprise of the construction, completion
and remedying of defects of ABC Building on the same Package & WP
campus. The scope of the works comprises of all
aspects of construction including foundations, civil,
MEP and external works including construction, any
work required by authorities (SCECO rooms, Mechanical Work
Electrical
transformers, Civil Defense requirements, connections, Package Package Packages
pumps, lift stations, Ministry of Water requirements,
etc.), testing and commissioning, authority approvals
and requirements of third party testing and
commissioning, completion, remedying of any defects
Finishing
Testin
during the Defects Liability Period, all in accordance Conveying
with the Tender Documents and Local Authority Package System
requirements.
ABC Building
Progress Narrative
Progress Status Report
Aug, 2020

 100% Excavation work completed on 20 Aug 19, and the work moved to piles execution
on 21 Aug 19
 Piles Execution has completed 100% on 11 Nov 19. 1050 Pile achieved within 90 days
 In 12 No 19, the structural Skelton works have been started, and up to date, the progress
of the structure works recorded 100% work done in phase 1. Structure works for phase
2
recorded 85%. The structure works for annex building still under progress with about
25% Achievement.
 30,000 m3 Concrete has been casted & 3000 Tone of steel rebar have been
fixed and assembled.
 Block works started on 10 Jan 20 and 97% completed up to date
 Water Proofing Activities are running in parallel with the concrete works. For foundation , it
is estimated that 95% of the WP works are completed.
 Electrical works started on 16 Jan 20 in phase 1, the work started by installing the
conduits and cable tray for in the ground floor, and the work achieved up to date is almost
95% in phase 1.
 Electrical Work has reached to the stage of installing cables and wires in phase 1 & 2 with
progress achievement reached up to 25%
 Mechanical works started on 20 Jan 20 by installing the Water Supply and drainage
pipes which reached up to 76% in phase 1 & 22% in phase 2
 HVAC work started on 23 Jan 2020 in phase 1 with 33% completed up to date. Phase 2
recorded 15% in ground floor..
ABC Building Project Calendar
Progress Status Report
Aug, 2020

00 Project Overall
Elapsed Days 5%  Planned Completion Date: 31 st May 2021
Remaining Days  Actual Completion Date: 23 June 21
36% 58%
160
160  Elapsed Days: 389 D
480 Delays
 Remaining Days: 304 D
 Total Delay: 23 D

320
Phase 1
elapsed days
 Planned Completion Date: 31 st Mar 2021
3%
 Actual Completion Date: 15 Apr 21
Remaining Days
43%
55%  Elapsed Days: 386 D
delay
 Remaining Days: 227 D
Elapsed Days Remaining Days Total Delay  Total Delay: 45 D

389 D 304 D 23 D
Phase 2
Elapsed Days Remaining Days  Planned Completion Date: 31 st May 2021
1%  Actual Completion Date: 23 June 21
Delays
49% 50%  Elapsed Days: 389 D
 Remaining Days: 304 D
 Total Delay: 23 D
ABC Building Time Management
Progress Status Report
Aug, 2020 Jul-19 Oct-19 Jan-20 Apr-20 Jul-20 Oct-20 Jan-21 Apr-21 Pl. Finish Ac. Finish Delay Item
31-May-21 16-Jun-21
                                                23 Total
                                                1-Apr-21 15-May-21 44 Phase 1
Time Schedule                                                 31-May-20 30-Sep-20 122 Structure
15-Jun-20 15-Oct-20
update  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  1-Mar-21 15-Apr-21
122
45
Insulation & WP
Mechanical
                                                1-Mar-21 15-Apr-21 45 Electrical
                                                1-Apr-21 15-May-21 44 Finishing
Elapsed Days 15-Mar-21 14-Apr-21
                                                30 Doors & Windows
389 D                                                 1-Feb-21 22-Mar-21 49 Conveying Sys
                                                22-Mar-21 1-Apr-21 10 External
Remaining Days                                                 31-May-21 16-Jun-21 16 Phase 2
304 D                                                 30-Jul-20 7-Nov-20
14-Aug-20 22-Nov-20
100 Structure
                                                100 Insulation & WP
Total Delay                                                 30-Apr-21 9-Jun-21 40 Mechanical
30-Apr-21 30-May-21
23 D  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  31-May-21 16-Jun-21
30
18
Electrical
Finishing
                                                14-May-21 3-Jun-21 20 Doors & Windows
                                                2-Apr-21 21-May-21 49 Conveying Sys
                                                21-May-21 31-May-21 10 External
                                                31-May-21 16-Jun-21 16 Landscape
                                                22-Mar-21 7-Apr-21 16 Hard-scaping
                                              31-May-21 16-Jun-21 16 Softe-scaping
ABC Building Time Management
Progress Status Report
44 45
Aug, 2020
40
39
50 35

40

Delay Accumulation
Delay Analysis 30 24

20
12 11 13
10 10 9
10
3
0
1-Jul 1-Aug 1-Sep 1-Oct 1-Nov 1-Dec 1-Jan 1-Feb 1-Mar 1-Apr 1-May 1-Jun 1-Jul 1-Aug

Q1=12 d Q2=10 d Q3=39 d Q3=35 d


The first 3 months By the month of COVID-19 For the month of
of the project
COVID-19 = Progress delay = have recorded up
Jan. 2020, the impacted with 20 Aug, 2020
total delay days in the - Total delay is 35
20 days 9 days to 10 days due to reached to 10. project total d
VO &
Changes = 4 Bad weather Authorities Approval a progress delay there is 4 days delay, and by the - COVID Delay is
days
= 0 days = 2 days progress month of May, 20 days
recovery and 4 2020, the overall - VO impact is 4
days due to the delay has Days
VO made for reached up to 44 - Authorities
level days. Approval for a
modifications night-shift
concrete casting
2 days
AF Construction Company, - Progress delay
impacted with 9
Building Dreams With Concrete… days
ABC Building 10,000,000.00 100,000,000.00

89.3%
9,000,000.00 Planned Value 90,000,000.00
Progress Status Report Earned Value
8,000,000.00 80,000,000.00
Aug, 2020 Acc. PV
7,000,000.00 Acc. EV 70,000,000.00 Planned

6,000,000.00 60,000,000.00

5,000,000.00 50,000,000.00
Planned Value
Work 4,000,000.00

3,000,000.00
40,000,000.00

30,000,000.00
89,352,170.4

Performance
2,000,000.00 20,000,000.00

1,000,000.00 10,000,000.00

81.8%
- -

1.00 1.00 Completed


Schedule Performance Line
0.97
0.97
0.94
0.93 Earned Value
0.94 0.92
0.91 0.89 81,842,008.4
0.90 0.89 0.91
0.88
0.91 0.89 100,000,000.00 89,352,1
70.47 81,843,2
0.87 0.89 80,000,000.00
08.67
0.85

The Project is behind the schedule according to the 60,000,000.00


comparison made to the accumulative planned value
SPI against the accumulative earned value from the project 40,000,000.00

start up to this update. However, the performance line is


0.92 showing that there was a trend for a good performance
20,000,000.00

during the last 4 months. -


PV EV
Packages Planned Actual Delay
Finish Finish Structural Package Finishing Package
30,000,000.00
Elec. Package
16,000,000.00
35,000,000.00 30,570,783.30,570,783.
13,676,80
80 80 23,878,73 14,000,000.00 1.13 12,646,19
Total 01 Nov 20 27 Dec 20 57 30,000,000.00 25,000,000.00 8.04 2.78
19,794,70 12,000,000.00
Structural Pkg 02 Jan 20 29 Feb 20 57 25,000,000.00 20,000,000.00 6.96
10,000,000.00
Insulation Pkg 01 Apr 20 30 Apr 20 29
20,000,000.00
15,000,000.00 8,000,000.00
Mech. Pkg 05 Aug 20 30 Sep 20 55
15,000,000.00
6,000,000.00
Elec. PKG 27 Aug 20 22 Oct 20 55 10,000,000.00
10,000,000.00
4,000,000.00
Finish. PKG 03 Oct 20 30 Nov 20 57 5,000,000.00
5,000,000.00 2,000,000.00
External PKG 03 Sep 20 30 Oct 20 57
- - -
,000,000.00 89,352,170. ACC. PV ACC. EV ACC. PV ACC. EV ACC. PV ACC. EV
47 81,843,208.
67 Package 100% Completed Package 40% Completed Package 80% Completed
,000,000.00

,000,000.00 81.5%
Completed Mech. Package W.P Package Ex. Finish Package
,000,000.00 16,000,000.00 13,785,50 2,500,000.00
5,417,530
4.81 12,934,65 2,022,8 6,000,000.00
.00
14,000,000.00 3.87 12.69 1,786,4
,000,000.00 Structueal WP 2,000,000.00
12,000,000.00 74.10 5,000,000.00
Mechanical Electrical 3,874,058
Finishing Façade & CW 10,000,000.00 4,000,000.00 .56
- 1,500,000.00
Acc. PV Acc. EV
1.00 1.00 8,000,000.00
3,000,000.00

0.97 0.97 Schedule Performance Index 6,000,000.00 1,000,000.00


2,000,000.00
0.93 4,000,000.00
0.94 0.94 0.92 500,000.00
0.89 1,000,000.00
2,000,000.00
0.91
0.90 0.91
0.91 0.89 0.89 - - -
0.88 0.89 ACC. PV ACC. EV ACC. PV ACC. EV ACC. PV ACC. EV
0.87
0.85 Package 80% Completed Package 90% Completed Package 25% Completed
19 19 19 19 19 19 19 20 20 20 20 20 20 20
un- Jul- ug- ep- ct- ov- ec- an- eb- ar- pr- ay- un- Jul-
J A S O N D J F M A M J
ABC Building
Progress Status Report
Aug, 2020

Photo Backfilling under the slab on grade is 99%


Structural works is completed The second floor slab has been 100%
25%
Gallery
ongoing with Completed for for the second building, and the work completed on 22 Aug 20, and the
the first building is being prepared to block works process of curing is under progressing

RC columns for the Annex Building Metal Duct Material Delivered Block Works is under progress for the
have ben casted with 68% 100%, and the fabrication is under Building #01 with progress reached to
Completed , and the curing process progress with 33% Completed 45%
is under progress
Created By
Ahmed Abdelfattah
Project Control & Planning Manager