WEEKLY MEETING 6

PROYEK UNDERPASS AKSES


KADUSIRUNG 2, BSD BARAT
30 JANUARI 2022
1. Progress of Work
PROGRESS 2. S Curve and Progress Report
PROJECT 3. Request For Information
PROGRESS OF WORK
MONITORING PROGRESS SHEET PILE
DIMENSI BOBOT
TANGGAL NO TITIK JUMLAH TOTAL TOTAL KEDALAMAN AMPERE METER
NO PANCANG HAMMER (KW) KET.
PANCANG BATANG PANJANG (M) SAMBUNGAN PANCANG (M)
B1 B2 (CM) B1 B2 B1 B2
1 12-Jan-23 13-Jan-23 1 2 40 cm 45 45 24 1 23,30 120/130 160/170
2 12-Jan-23 14-Jan-23 2 2 40 cm 45 45 24 1 22,75 110/120 150/160
3 12-Jan-23 14-Jan-23 3 2 40 cm 45 45 24 1 21,15 120/130 150/160
4 12-Jan-23 14-Jan-23 4 2 40 cm 45 45 24 1 21,45 120 150/160
5 12-Jan-23 14-Jan-23 5 2 40 cm 45 60 24 1 22,00 120/130 170/180
6 12-Jan-23 15-Jan-23 6 2 40 cm 45 45 24 1 21,20 110/120
7 12-Jan-23 15-Jan-23 7 2 40 cm 45 45 24 1 21,50 110/130
8 15-Jan-23 17-Jan-23 8 2 40 cm 45 45 24 1 22,30 100/110 200
9 15-Jan-23 17-Jan-23 9 2 40 cm 45 45 24 1 22,25 100 200
10 15-Jan-23 18-Jan-23 10 2 40 cm 45 60 24 1 22,43 100/120 170
11 15-Jan-23 18-Jan-23 11 2 40 cm 45 60 24 1 22,48 100 180
12 15-Jan-23 18-Jan-23 12 2 40 cm 45 60 24 1 22,85 100/130 180
13 18-Jan-23 18-Jan-23 13 2 40 cm 60 24 1 22,40 170
14 18-Jan-23 19-Jan-23 14 2 40 cm 60 60 24 1 22,50 190
15 18-Jan-23 19-Jan-23 15 2 40 cm 60 60 24 1 21,10 190
16 18-Jan-23 19-Jan-23 16 2 40 cm 60 60 24 1 21,48 200
17 18-Jan-23 19-Jan-23 17 2 40 cm 60 60 24 1 21,40 180
18 19-Jan-23 19-Jan-23 18 2 40 cm 60 60 24 1 23,40 200
19 19-Jan-23 20-Jan-23 19 2 40 cm 60 45 24 1 23,00 180
20 19-Jan-23 20-Jan-23 20 2 40 cm 60 45 24 1 21,30 170
21 19-Jan-23 20-Jan-23 21 2 40 cm 60 45 24 1 22,70 190
22 20-Jan-23 20-Jan-23 22 2 40 cm 45 45 24 1 22,45 190
23 20-Jan-23 20-Jan-23 23 2 40 cm 45 45 24 1 22,50 185
24 20-Jan-23 20-Jan-23 24 2 40 cm 45 45 24 1 22,60 ` 190
25 20-Jan-23 21-Jan-23 25 2 40 cm 45 45 24 1 22,30 160
26 20-Jan-23 21-Jan-23 26 2 40 cm 45 45 24 1 22,30 180
27 21-Jan-23 21-Jan-23 27 2 40 cm 45 45 24 1 22,20 170
28 21-Jan-23 21-Jan-23 28 2 40 cm 45 45 24 1 22,50 175
29 21-Jan-23 21-Jan-23 29 2 40 cm 45 45 24 1 22,50 190
30 21-Jan-23 21-Jan-23 30 2 40 cm 45 45 24 1 22,40 180
31 21-Jan-23 22-Jan-23 31 2 40 cm 45 45 24 1 20,10 120 160/170
32 21-Jan-23 22-Jan-23 32 2 40 cm 45 45 24 1 21,40 120 170/180
33 21-Jan-23 22-Jan-23 33 2 40 cm 45 45 24 1 21,15 130 160/170
34 21-Jan-23 22-Jan-23 34 2 40 cm 45 45 24 1 23,20 130 160
35 21-Jan-23 22-Jan-23 35 2 40 cm 45 45 24 1 23,20 140 150
36 21-Jan-23 22-Jan-23 36 2 40 cm 45 45 24 1 21,40 120 170
37 22-Jan-23 23-Jan-23 37 2 40 cm 45 45 24 1 22,50 130 170
MONITORING PROGRESS SHEET PILE
DIMENSI BOBOT
TANGGAL NO TITIK JUMLAH TOTAL TOTAL KEDALAMAN AMPERE METER
NO PANCANG HAMMER (KW) KET.
PANCANG BATANG PANJANG (M) SAMBUNGAN PANCANG (M)
B1 B2 (CM) B1 B2 B1 B2
38 22-Jan-23 23-Jan-23 38 2 40 cm 45 45 24 1 23,80 150 180
39
40
22-Jan-23
22-Jan-23
23-Jan-23
24-Jan-23
39
40
2
2
40 cm
40 cm
45
45
45
45
24
24
1
1
22,05
22,30
160
130
190
160
Rekap per 29 Jan 23:
41
42
23-Jan-23
23-Jan-23
24-Jan-23
24-Jan-23
41
42
2
2
40 cm
40 cm
45
45
45
45
24
24
1
1
22,75
23,17
110
100
170
150
1. 66 titik pancang kedalaman 24 meter
43 23-Jan-23 24-Jan-23 43 2 40 cm 45 45 24 1 23,30 100 170 2. 5 titik pancang kedalaman 12 meter
44 23-Jan-23 24-Jan-23 44 2 40 cm 45 45 24 1 21,60 120 180
45 23-Jan-23 24-Jan-23 45 2 40 cm 45 45 24 1 22,30 110 150 3. Total terpancang 137 Batang
46 23-Jan-23 24-Jan-23 46 2 40 cm 45 45 24 1 22,60 110 170
47 23-Jan-23 26-Jan-23 47 2 40 cm 45 45 24 1 22,30 80 180 4. Total panjang terpancang= 28 meter
48
49
26-Jan-23
26-Jan-23
26-Jan-23
27-Jan-23
48
49
2
2
40 cm
40 cm
45
45
45
45
24
24
1
1
22,30
22,00
60
90
180
180
5. Sisa pekerjaan:
50
51
26-Jan-23
26-Jan-23
27-Jan-23
27-Jan-23
50
51
2
2
40 cm
40 cm
45
45
45
45
24
24
1
1
22,00
22,10
80
90
180
170
• 284 titik pancang 24 meter
52 26-Jan-23 27-Jan-23 52 2 40 cm 45 45 24 1 22,00 60 190 • 150 titik pancang 12 meter
53 26-Jan-23 27-Jan-23 53 2 40 cm 45 45 24 1 22,10 80 180
54 26-Jan-23 27-Jan-23 54 2 40 cm 45 45 24 1 22,20 50 180 • 713 batang
55 27-Jan-23 27-Jan-23 55 2 40 cm 45 45 24 1 22,15 40 190
56 27-Jan-23 27-Jan-23 56 2 40 cm 45 45 24 1 20 180 • 172 meter
57 27-Jan-23 28-Jan-23 57 2 40 cm 45 45 24 1 21,90 40 150
58 27-Jan-23 28-Jan-23 58 2 40 cm 45 45 24 1 22,00 50 150
59 27-Jan-23 28-Jan-23 59 2 40 cm 45 45 24 1 22,00 60 160
60 28-Jan-23 28-Jan-23 60 2 40 cm 45 45 24 1 22,00 60 180
61 28-Jan-23 28-Jan-23 61 2 40 cm 45 45 24 1 21,90 50 170
62 28-Jan-23 29-Jan-23 62 2 40 cm 45 45 24 1 21,90 50 140
63 28-Jan-23 29-Jan-23 63 2 40 cm 45 45 24 1 22,60 60 170
64 28-Jan-23 29-Jan-23 64 2 40 cm 45 45 24 1 22,90 50 190
65 28-Jan-23 29-Jan-23 65 2 40 cm 45 45 24 1 23,10 50 180
66 28-Jan-23 29-Jan-23 66 2 40 cm 45 45 24 1 21,80 40 160
67 29-Jan-23 67 1 40 cm 45 12 0 40
68 29-Jan-23 68 1 40 cm 45 12 0 50
69 29-Jan-23 69 1 40 cm 45 12 0 60
70 29-Jan-23 70 1 40 cm 45 12 0 50
71 29-Jan-23 71 1 40 cm 45 12 0 50
71 137
SCHEDULE OF BC & CB
2023

JANUARI 2023 FEBRUARI MA RET APRIL

NO URAIAN PEKERJAA N Volume durasid urasi start finish 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 KETERANGAN

hari minggu 26 Dec 02 Jan 09 Jan 16 Jan 23 Jan 30 Jan 06 Feb 13 Feb 20 Feb 27 Feb 06 Mar 13 Mar 20 Mar 27 Mar 03 A pr 10 Apr 17 A pr 24 A pr

Minggu ke Minggu ke 01 Jan 08 Jan 15 Jan 22 Jan 29 Jan 05 Feb 12 Feb 19 Feb 26 Feb 05 Mar 12 Mar 19 Mar 26 Mar 02 A pr 09 A pr 16 Apr 23 A pr 30 A pr

CROSSING JA LAN TOL SERPONG -BALARA JA (AREA INTERCHANGE LEGOK STA


9.800)

1 BOX CULVERT 8x4M Crossing Jalan STA 1+280


Galian Tanah 105,35 2,000 5,000 6,000 1 1
Pemadatan tanah Sub grade CBR 6% 323,59 1,000 7,000 7,000 1
Buang tanah 105,35 2,000 5,000 6,000 1 1
Granular 850,00 1,000 7,000 7,000 1
Learn Concrete t= 100 mm 34,64 1,000 8,000 8,000 1
Blinding stone t= 200 mm 66,44088 1,000 7,000 7,000 1
Beton Ready Mix
Beton 1.042,88 3,000 8,000 10,000 1 1 1
Bekisting 1.105,30 3,000 8,000 10,000 1 1 1
Pembesian 144.336,28 3,000 8,000 10,000 1 1 1

2 BOX CULVERT 4x1.5M STA 0+739,82 (UTA RA)


penimbunan akses jalan sementara (opsional) 2,000 7,000 8,000 1 1
Galian Tanah 685,30 2,000 8,000 9,000 1 1
Pemadatan tanah Sub grade CBR 6% 249,20 1,000 10,000 10,000 1
Buang tanah 685,30 2,000 8,000 9,000 1 1
Granular 168,00 1,000 10,000 10,000 1
Learn Concrete t= 100 mm 14,28 1,000 10,000 10,000 1
Blinding stone t= 200 mm 28,56 1,000 10,000 10,000 1
Beton Ready Mix
Beton 180,10 2,000 10,000 11,000 1 1
Bekisting 361,20 2,000 10,000 11,000 1 1
Pembesian 29.796,64 2,000 10,000 11,000 1 1

CAP BEAM (SISI TIMUR STA 0+797,6 - STA 0+992,6 . STA


3 1+082 - STA 1+137,8 DAN SISI BARAT STA 0+815,7 - STA
0+992 . STA 1+082 - STA 1+238)
Sisi Utara (section Barat & Timur)
Gali Tanah dan Bobok kepala Borepile 2,000 5,000 7,000 1 1 1

Lantai kerja 2,000 6,000 7,000 1 1


Beton Ready Mix
Beton 279,89 2,000 10,000 11,000 1 1
Bekisting 699,72 3,000 8,000 10,000 1 1 1
Pembesian 23.618,98 3,000 7,000 9,000 1 1 1
Sisi Selatan (section Barat & Timur)
Gali Tanah dan Bobok kepala Borepile 3,000 8,000 10,000 1 1 1
Lantai kerja 2,000 9,000 10,000 1 1
Beton Ready Mix
Beton 279,89 3,000 12,000 14,000 1 1 1
Bekisting 699,72 3,000 11,000 13,000 1 1 1
Pembesian 23.618,98 3,000 10,000 12,000 1 1 1
S CURVE AND PROGRESS
S CURVE
2023

JA NUA RI FEB RUA RI MA RET A PRIL MEI JUNI JULI A GUSTUS SEPTEM B ER
Dur asi
NO URA IA N PEK ERJAA N B obot % 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 K ETERA NGA N
(Har i)
26 D ec 02 Jan 09 Jan 16 Jan 23 Jan 30 Jan 06 Feb 13 Feb 20 Feb 27 Feb 06 Mar 13 Mar 20 Mar 27 M ar 03 A pr 10 A pr 17 A pr 24 A pr 01 May 08 M ay 15 M ay 22 May 29 May 05 Jun 12 Jun 19 Jun 26 Jun 03 Jul 10 Jul 17 Jul 24 Jul 31 Jul 07 A ug 14 A ug 21 A ug 28 A ug 04 Sep 11 Sep 18 Sep

01 Jan 08 Jan 15 Jan 22 Jan 29 Jan 05 Feb 12 Feb 19 Feb 26 Feb 05 Mar 12 Mar 19 Mar 26 Mar 02 A pr 09 A pr 16 A pr 23 A pr 30 A pr 07 May 14 M ay 21 M ay 28 May 04 Jun 11 Jun 18 Jun 25 Jun 02 Jul 09 Jul 16 Jul 23 Jul 30 Jul 06 A ug 13 A ug 20 A ug 27 A ug 03 Sep 10 Sep 17 Sep 21 Sep

1 PEK ERJA A N PERSIA PA N 5,774 270 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,158 0,090 100%

CROSSING JALA N TOL SERPONG -B A LA RA JA (AREA INTERCHA NGE LEGOK STA


A
9.800)
1 B OX UNDERPA SS 12.075 X 5.3M STA 0+992,824 - STA 1+083,292 203 p ile by o ther
1,1 Pekerjaan tanah 0,582 63 0,065 0,065 0,065 0,065 0,065 0,065 0,065 0,065 0,065
1,2 Beton Ready M ix 28,236 63 3,137 3,137 3,137 3,137 3,137 3,137 3,137 3,137 3,137
1,3 Trotoar 1,340 77 0,149 0,149 0,149 0,149 0,149 0,149 0,149 0,149 0,149
1,4 Pekerjaan Aspal 0,828 35 0,166 0,166 0,166 0,166 0,166

2 B OX CULVERT 8x4M (Di Sampi ng BO X UNDERPA SS 12.075 X 5.3M) g ali & p ile b y o th er
2,1 pekerjaan tanah 0,263 14 0,132 0,132
2,2 Beton Ready M ix 11,819 112 0,844 0,844 0,844 0,844 0,844 0,844 0,844 0,844 0,844 0,844 0,844 0,844 0,844 0,844

3 B OX CULVERT 8x4M Cr ossing Jalan STA 1+ 280


3,1 pekerjaan tanah 0,069 14 0,034 0,034
3,2 Beton Ready M ix 3,373 21 1,124 1,124 1,124

4 B OX CULVERT 4x1.5M STA 0+739,82


4,1 pekerjaan tanah 0,119 14 0,059 0,059
4,2 Beton Ready M ix 0,688 21 0,229 0,229 0,229

5 SA LURA N TERB UK A 4x1.5M STA 0+739,82 - STA 0+ 992,824


5,1 Pekerjaan tanah 0,798 14 0,399 0,399
5,2 Beton Ready M ix 2,880 133 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152 0,152

6 B OX CULVERT 2x2M (Di Sampi ng BO X UNDERPA SS 12.075 X 5.3M)


6,1 Pekerjaan tanah 0,188 14 0,094 0,094
6,2 Beton Ready M ix 0,732 84 0,061 0,061 0,061 0,061 0,061 0,061 0,061 0,061 0,061 0,061 0,061 0,061

CA P B EA M (SISI TIM UR STA 0+797,6 - STA 0+992,6 . STA 1+082 - STA 1+137,8 DA N
7
SISI B A RA T STA 0+815,7 - STA 0+992 . STA 1+ 082 - STA 1+ 238)
7.1 Beton Ready M ix 1,550 28 0,388 0,388 0,388 0,388

PLAT INJA K DA N PLAT B ETON T= 90CM (AREA BOX UND ERPA SS 12.075 X 5.3M
8 DA N B OX CULV ERT 8x4M Cr ossin g Jalan STA 1+280) JUGA BO X CULVERT 4x1.5M
STA 0+ 739,82
8.1 Plat Injak Ujung Box dan Plat Injak atas (Tol) 0,794 42 0,199 0,199 0,199 0,199
8.2 Plat Injak Box Maidrain 8X4m Sta 1+280 0,401 28 0,200 0,200
8.3 Plat Injak Box Maidrain 4X1.5 Sta 0+750 0,280 28 0,140 0,140
8.4 Plat Beton T 0.9m 3,924 42 0,981 0,981 0,981 0,981

Pek er j aan Perker asan Jalan (Opr i t) STA 0+650 - STA 0+992,824 Dan STA 1+083,292 -
9
STA 1+ 421,094
9.1 Sub Base Coarse
9.1.1 Agregat kelas B, t = 40 cm 2,058 14 1,029 1,029
9.2 Base Coarse
9.2.1 Agregat kelas A, t = 30 cm 1,407 14 0,704 0,704
9.3 Leveling, pemadatan dan perapihan sub grade 0,321 14 0,160 0,160
9.4 Pekerjaan Kansteen dan Street Inlet 1,504 31 0,340 0,340 0,340 0,340 0,146
9.5 Pekerjaan Saluran 3,405 35 0,681 0,681 0,681 0,681 0,681
9.6 Pekerjaan Aspal 5,457 31 1,232 1,232 1,232 1,232 0,528

10 Pek er j aan L ain lain


10.1 Street Inlet/M ulut Tali Air 0,075 14 0,038 0,038
10.2 Pasir urug t= 100 mm 0,043 28 0,022 0,022
10.3 Finish ekspose borepile 1,183 14 0,591 0,591
10.4 Concrete Cover Pipa RCP dia. 60 cm 0,183 14 0,092 0,092
10.5 Saluran U-ditch Cast In Situ Median 0,335 49 0,067 0,067 0,067 0,067 0,067
10.6 M aindrain Terbuka 1,837 35 0,367 0,367 0,367 0,367 0,367
10.7 Pekerjaan Tiang Pancang Box Culvert 4x1.5 M STA 0+739,82 0,166 14 0,083 0,083
10.8 Replacement Granular 0,394 7 0,394
10.9 Geotextile Non Woven 0,014 7 0,014
10.10 Cerucuk Bambu 0,384 35 0,077 0,077 0,077 0,077
10.11 Railling (D iatas Box Culvert Crossing Jalan) 0,074 7 0,074
10.12 Tarikan kabel dari gardu PLN ke KWH dan LVM DP -
10.13 Pipa Perporasi Ø20 cm 0,110 7 0,110
10.14 Batu Split 0,041 7 0,041
10.15 Geotextile Non Woven (separator) 0,010 7 0,010
10.16 Grounding 5,161 7 5,161
10.20 Pipa Sulingan 0,081 14 0,041 0,041
10.21 Pekerjaan CSSP L12 (Sheel pile) 3,609 49 0,516 0,516 0,516 0,516 0,516 0,516 0,516
10.22 Tie Beam Sisi Bore Pile 0,272 7 0,272

B B A NGUNA N RUM A H POM PA DAN GENSET


1 B A NGUNA N RUM A H POM PA
1,1 Pekerjaan tanah 0,169 14 0,085 0,085
1,2 Beton Ready M ix 3,160 84 0,316 0,316 0,316 0,316 0,316 0,316 0,316 0,316 0,316 0,316

2 PEK ERJA A N DINDING DA N FINISHING


2.1 PENGECATA N DINDING EKSTERIOR
2.2 PENGECATA N DINDING INTERIOR
2.2.1 Pengecatan Dinding 0,022 14 0,011 0,011

3 PEK ERJA A N PLA FOND :


3.1 PENGECATA N PLA FOND INTERIOR
3.1.1 Plafond Beton Expose 0,009 7 0,009

4 PEK ERJA A N ELEK TRIKA L 0,073 7 0,073

5 Pemipaan di Ruang Pompa ( Pipa Di schar ge di a 300 & di a 200) 0,641 14 0,320 0,320

6 Pemipaan di Ruang Pompa ( Pipa Exhaust dia 150 dan Pipa Intake dia 100 ) 0,016 14 0,008 0,008

7 PEK ERJA A N L AIN-LA IN 0,435 35 0,087 0,087 0,087 0,087 0,087

C M EP
1 Pek er j aan Tanah 0,076 7 0,076

2 K A B EL
2.1 K abel NYFGB Y 0,784 7 0,784

3 Pek er j aan K onekti ng + Per ij inan 0,222 7 0,222

4 Pek er j aan Panel 1,009 7 1,009

5 Pek er j aan Upah pasang Lampu 0,008 7 0,008

6 Pek er j aan Pompa Ver t ikal Tur bi n (M at er ial SBO ) 0,250 7 0,250

7 PEK ERJA A N L AIN-LA IN 0,362 7 0,362


0%
Rencana Pr ogr es M ingguan 100,000 0,158 0,673 0,805 1,649 2,263 5,401 5,435 6,559 6,009 5,328 4,263 4,642 4,582 5,887 3,235 3,475 - - 3,227 1,800 1,733 1,704 1,555 1,737 1,265 1,232 6,322 1,574 1,213 0,708 1,516 0,371 1,565 1,565 2,812 2,812 2,268 1,890 0,764
K omul ati f Rencana Pr ogr es M ingg uan - 0,158 0,831 1,636 3,285 5,549 10,949 16,384 22,943 28,953 34,281 38,545 43,186 47,769 53,655 56,890 60,365 60,365 60,365 63,593 65,393 67,126 68,830 70,385 72,122 73,387 74,620 80,942 82,516 83,729 84,437 85,953 86,324 87,889 89,454 92,266 95,077 97,346 99,236 100,000
A ct ual Pro gr es Mingg uan 1,080 0,161 0,831 0,624 0,568 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
K omul ati f A ctual Pr ogr es M ingguan 1,080 1,241 2,072 2,696 3,264
Deviasi 0,922 0,410 0,436 (0,590) (2,285)
WEEKLY PROGRESS 23-29 JAN 23
LAPORAN KEMAJUAN KEGIATAN MINGGUAN
Minggu Ke : 5 (Lima)
23 Januari 2023 s/d 29 Januari 2023
REKAPITULASI BOBOT PEKERJAAN
PROYEK UNDERPASS AKSES KADUSIRUNG 2, BSD BARAT

REALISASI KEMAJUAN PEKERJAAN (%)


BOBOT PEKERJAAN
NO. URAIAN PEKERJAAN S/D MINGGU LALU MINGGU INI S/D MINGGU INI
(%) RENCANA REALISASI RENCANA REALISASI RENCANA REALISASI

1.1 PEKERJAAN PERSIAPAN 5,774 0,632 1,478 0,158 0,128 0,789 1,606

1.2 CROSSING JALAN TOL SERPONG -BALARAJA (AREA 86,990 2,654 1,218 2,105 0,440 4,759 1,658
INTERCHANGE LEGOK STA 9.800)

1.3 BANGUNAN RUMAH POMPA DAN GENSET 4,526 - - - - - -

1.4 MEP 2,711 - - - - - -

Rencana Progress Fisik s/d Minggu Ini : 100,000 3,285 2,263 5,549
Realisasi Progress Fisik s/d Minggu Ini : 2,696 0,568 3,264
Deviasi : (0,590) Tidak Tercapai (1,695) Tidak Tercapai (2,285) Tidak Tercapai
Catatan: progress minus dikarenakan sesuai schedule rencana minggu ke 4 harus sudah mengerjakan box Culvert Main Drain 8x4m
REQUEST FOR INFORMATION
CAPING BEAM

Sisi barat
CAPING BEAM
CAPING BEAM

Rencana realisasi
TERIMA KASIH