You are on page 1of 3

Daily Report

• Construction logistics
Steel structure

1. Level checked with base nut


2. Mounted columns
3. Anchor points for bracing of
columns (steel cable ¼”)
4. Assembly of miscellaneous items
5. Leaded columns
6. Grout application
7. Previously assembled elements
8. Columns prepared for assembly
Daily Report
• Construction logistics
Steel structure

9. Mounted beams
10. Welding review (SMAW, AWS-D1.1)
11. Slump Tolerances review AISC-360.10
Daily Report

Activities planned for next day:


- Assembly of columns from axis 5.
- Assembly of beams from axis 6.
- Assembly of columns from axis 6.
- Colums lead review
- Columns plumbing
- Deflexion in beams review
- *Wind loads above 22.15 miles per hour
- *Rainy conditions and gusty winds