Tower Construction by ACS

from EL+207 to EL+304.5

22. Jan. 2014

1
General section
VARIO form
Hydraulic jack arrangement

18(E) + 8(I) = 26jacks 5 grouping


Assembly procedure
General procedure Remarks
Pre-assembly of ACS on ground On-going (Level-2 ~ Level+2)
Transport the lower parts to tower site 9 parts
Lean them against the slope Stand-by till slipform dismantlement
Lift and install the lower parts on tower Level-2 ~ Level 0
Lift and install 1.5m form For slab (EL+207~EL+208)
Slab (bracket/form insert/rebar/concrete) 2times (0.4m+0.6m) + kicker 0.3m
Install temporary bent and anchor box
Dismantle 1.5m form
Install rebar for 1st lot
Lift and install 9 pieces of upper part Level 0 ~ Level+2
Concrete pouring for 1st lot
5day-cycle operation for leg construction upto EL+300
Tower top slab 3times
Pre-assembly

9-parts x 3-levels = 27-parts


Operation 1
Operation 2
Rebar self-standing mock-up
Concrete supply through piping
Access plan 1
Access plan 2

Level -2 Level -3
Installation of temporary bent and anchor box
Target Progress Schedule
Working Day
Lot Start El. to End El. Start Date Finish Date
A.Box Rebar Form Survey Concrete Curing W.Day
Diaphragm 207.0 ~ 208.0 - 1.0 14.0 0.5 0.5 0.5 16.5 2014-02-15 2014-03-02
1 208.0 ~ 212.6 5.0 1.5 5.0 0.3 0.7 0.5 13.0 2014-03-03 2014-03-15
2 212.6 ~ 217.2 - 1.5 1.5 0.3 0.7 0.5 4.5 2014-03-16 2014-03-20
3 217.2 ~ 221.8 2.0 1.5 1.5 0.3 0.7 0.5 6.5 2014-03-21 2014-03-26
4 221.8 ~ 226.4 1.5 1.5 0.3 0.7 0.5 4.5 2014-03-27 2014-03-31
5 226.4 ~ 231.0 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-04-01 2014-04-05
6 231.0 ~ 235.6 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-04-06 2014-04-11
7 235.6 ~ 240.2 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-04-12 2014-04-16
8 240.2 ~ 244.8 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-04-17 2014-04-21
9 244.8 ~ 249.4 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-04-22 2014-04-26
10 249.4 ~ 254.0 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-04-27 2014-05-01
11 254.0 ~ 258.6 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-05-02 2014-05-06
12 258.6 ~ 263.2 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-05-07 2014-05-11
13 263.2 ~ 267.8 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-05-12 2014-05-17
14 267.8 ~ 272.4 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-05-18 2014-05-22
15 272.4 ~ 277.0 1.0 1.5 6.0 0.3 0.7 0.5 10.0 2014-05-23 2014-06-01
16 277.0 ~ 281.6 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-06-02 2014-06-06
17 281.6 ~ 286.2 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-06-07 2014-06-11
18 286.2 ~ 290.8 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-06-12 2014-06-16
19 290.8 ~ 295.4 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-06-17 2014-06-21
20 295.4 ~ 300.0 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-06-22 2014-06-26
slab1 300.0 ~ 302.0 - 4.0 6.0 0.5 1.0 1.0 12.5 2014-06-27 2014-07-09
slab2 302.0 ~ 304.0 - 4.0 - - 1.0 1.0 6.0 2014-07-10 2014-07-15
slab3 304.0 ~ 304.5 - 3.0 6.0 0.5 0.5 0.5 10.5 2014-07-16 2014-07-25
Dismantle 6.0 2014-07-26 2014-07-31
Typical Cycle Time

Activity Required Time Remarks


(day)
Anchor box installation 0.5 (0.0~5.0) 32ton max.
Rebar installation 1.5 Ave. 40ton
(incl. embedded material)
Form lifting & adjusting 1.5
Survey, final form adjusting, in- 0.3
spection
Concrete pouring by pumping 0.7 Ave. 180m3
(+bucket)
Curing 0.5 10MPa
Cycle time 5.0
Worker Organization

For tower (mainly by local workers) : 65persons/site


• Rebar worker : 18/shift x 2shift = 36
• Carpenter : 12/shift x 2shift = 24
• Etc(welder, electrician, common labor) = 5

For strut & diaphragm (mainly by Korean workers) : 22persons/site


• Korean worker : 6/shift x 2shift = 14
• Korean skyworker : 8/shift x 1shift = 8

Total workers to be mobilized


• (65 + 22)/tower x 2tower = 174