General section
VARIO form
Hydraulic jack arrangement
Level -2 Level -3
Installation of temporary bent and anchor box
Target Progress Schedule
Working Day
Lot Start El. to End El. Start Date Finish Date
A.Box Rebar Form Survey Concrete Curing W.Day
Diaphragm 207.0 ~ 208.0 - 1.0 14.0 0.5 0.5 0.5 16.5 2014-02-15 2014-03-02
1 208.0 ~ 212.6 5.0 1.5 5.0 0.3 0.7 0.5 13.0 2014-03-03 2014-03-15
2 212.6 ~ 217.2 - 1.5 1.5 0.3 0.7 0.5 4.5 2014-03-16 2014-03-20
3 217.2 ~ 221.8 2.0 1.5 1.5 0.3 0.7 0.5 6.5 2014-03-21 2014-03-26
4 221.8 ~ 226.4 1.5 1.5 0.3 0.7 0.5 4.5 2014-03-27 2014-03-31
5 226.4 ~ 231.0 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-04-01 2014-04-05
6 231.0 ~ 235.6 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-04-06 2014-04-11
7 235.6 ~ 240.2 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-04-12 2014-04-16
8 240.2 ~ 244.8 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-04-17 2014-04-21
9 244.8 ~ 249.4 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-04-22 2014-04-26
10 249.4 ~ 254.0 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-04-27 2014-05-01
11 254.0 ~ 258.6 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-05-02 2014-05-06
12 258.6 ~ 263.2 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-05-07 2014-05-11
13 263.2 ~ 267.8 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-05-12 2014-05-17
14 267.8 ~ 272.4 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-05-18 2014-05-22
15 272.4 ~ 277.0 1.0 1.5 6.0 0.3 0.7 0.5 10.0 2014-05-23 2014-06-01
16 277.0 ~ 281.6 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-06-02 2014-06-06
17 281.6 ~ 286.2 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-06-07 2014-06-11
18 286.2 ~ 290.8 1.0 1.5 1.5 0.3 0.7 0.5 5.5 2014-06-12 2014-06-16
19 290.8 ~ 295.4 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-06-17 2014-06-21
20 295.4 ~ 300.0 0.5 1.5 1.5 0.3 0.7 0.5 5.0 2014-06-22 2014-06-26
slab1 300.0 ~ 302.0 - 4.0 6.0 0.5 1.0 1.0 12.5 2014-06-27 2014-07-09
slab2 302.0 ~ 304.0 - 4.0 - - 1.0 1.0 6.0 2014-07-10 2014-07-15
slab3 304.0 ~ 304.5 - 3.0 6.0 0.5 0.5 0.5 10.5 2014-07-16 2014-07-25
Dismantle 6.0 2014-07-26 2014-07-31
Typical Cycle Time