You are on page 1of 6

0

Name of work : Widening and Strengthening of Dhansura-Meghraj Road KM-38+501 TO KM-64+583 (Dhansura - Malpur) & km-67+711 to 84+986 (Malpur - Meghraj) SH-145

ASHISH INFRACON PVT. LTD.


Clarification Estimates Ahmedabad - BACKBONE
Item No. DESCRIPTION Unit ENTERPRISES LTD (JV)

Unit Rate Rate Amount


Item No. DESCRIPTION Quantity Amount
1 General Items
1 GENERAL ITEMS

Supply of master CD / DVD's of important site activities with four copies complete as Supply of master CD / DVD's of important site activities with
1.02 Set 1.02 Set 10.00 10,000.000 1,00,000 1,500.00 15,000.00
per Technical Specifications clause 126 four copies complete as per Technical Specifications clause 126

Construction of temporary diversion for passage of traffic, complete as per Technical Construction of temporary diversion for passage of traffic,
1.03 Specifications Section Clause 112.3. Lm 1.03 complete as per Technical Specifications Section Clause 112.3. Lm 2,200.00 3,716.000 81,75,200 2,500.00 55,00,000.00
(separate items are given for CD/ bridge work diversions) (separate items are given for CD/ bridge work diversions)

Total General Items carried to Grand Summary Total general Items carried to Grand Summary 82,75,200 55,15,000.00
2 SITE CLEARANCE AND DISMANTLING 2 Site Clearance and Dismantling

Clearing and grubbing road land including uprooting rank


Clearing and grubbing road land including uprooting rank vegetation, grass, bushes,
vegetation, grass, bushes, shrubs, saplings and trees girth up to
shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier
300 mm, removal of stumps of trees cut earlier and disposal of
2.01 and disposal of unserviceable materials and stacking of serviceable material to be used ha 2.01 ha 52.00 29,520.000 15,35,040 7,500.00 3,90,000.00
unserviceable materials and stacking of serviceable material to be
or auctioned complete as per technical specification clause 201 or as directed by the
used or auctioned complete as per technical specification clause
Engineer.
201 or as directed by the Engineer.

Dismantling of existing structures like culverts, bridges, retaining


Dismantling of existing structures like culverts, bridges, retaining walls and other
walls and other structure comprising of masonary, cement
structure comprising of masonry, cement concrete, wood work, steel work, including
concrete, wood work, steel work, including T&P and scaffolding
2.02 T&P and scaffolding wherever necessary, disposal of unserviceable as well serviceable 2.02 - -
wherever necessary, disposal of unserviceable as well serviceable
material with all leads and lifts beyond the ROW complete as per technical
material with all leads and lifts beyond the ROW complete as per
specification clause 202.
technical specification clause 202

a) Plain cement concrete Cum a) Plain cement concrete Cum 11.00 278.000 3,058 300.00 3,300.00
b) Reinforced cement concrete Cum b) Reinforced cement concrete Cum 12.00 463.000 5,556 500.00 6,000.00
c) Stone / Brick masonry structures Cum c) Stone / Brick masonry structures Cum 12.00 189.000 2,268 200.00 2,400.00

d) Guide/Hand rails / Fencing / kerb / NP3 Pipes / NP4 Pipes Lm d) Guide/Hand rails / Fencing / kerb / NP3 Pipes / NP4 Pipes Lm 35.00 151.000 5,285 100.00 3,500.00

e) Kilometre stone Nr e) Kilometre stone Nr 35.00 136.000 4,760 100.00 3,500.00


f) 5 km stone Nr f) 5 km stone Nr 8.00 226.000 1,808 100.00 800.00
g) Hectometre / Boundary stones Nr g) Hectometre / Boundary stones Nr 173.00 27.000 4,671 50.00 8,650.00
h) Utilities Nr h) Utilities Nr 12.00 101.000 1,212 1,000.00 12,000.00
i) Bituminous Pavement Cum i) Bituminous Pavement Cum 3,689.00 174.000 6,41,886 60.00 2,21,340.00
j) Non- Bituminous Pavement Cum j) Non- Bituminous Pavement Cum 1,280.00 307.000 3,92,960 40.00 51,200.00
- -
- -

Cutting of trees 300 mm and above girth size, the work shall
Cutting of trees from 300mm and above girth size, the work shall consist of cutting of consist of cutting of all such trees as per the direction of the
all such trees as per the direction of the Engineer and further as per duly approved plan engineer and further as per duly aprroved plan by the forest
2.03 by the Forest Department. This shall include duly approved stacking, transport and 2.03 department. This shall include duly approved stacking, transport - -
final handing over to Forest Department with all leads and lifts. Work to comply and final handing over to forest department with all leads and
strictly in accordance with Technical Specifications Clause 201 lifts. eork to comply strictly in accordance with technical
specifications clause 201.

a) above 300mm to 600mm girth Nr a) above 300mm to 600mm girth Nr 1,775.00 156.000 2,76,900 600.00 10,65,000.00
b) above 600mm to 900mm girth Nr b) above 600mm to 900mm girth Nr 1,036.00 278.000 2,88,008 800.00 8,28,800.00
c) above 900mm to 1800mm girth Nr c) above 900mm to 1800mm girth Nr 1,137.00 542.000 6,16,254 1,300.00 14,78,100.00
d) above 1800m Nr d) above 1800m Nr 68.00 1,029.000 69,972 3,000.00 2,04,000.00
Removal of tree stumps and roots, disposal and filling of pits
Removal of tree stumps and roots, disposal and filling of pits complete as per
complete as per technical specification clause 201. The work shall
Technical Specifications Clause 201. The work shall follow the directions of the
2.04 2.04 follow the direction of the engineer andf further approval of plan - -
Engineer and further approval of plan by the Forest Department, where necessary.
by the forest department, where necessary. This shall include all
This shall include all leads and lifts.
leads and lifts.
a) above 300mm to 600mm girth Nr a) above 300mm to 600mm girth Nr 1,775.00 307.000 5,44,925 800.00 14,20,000.00
b) above 600mm to 900mm girth Nr b) above 600mm to 900mm girth Nr 1,036.00 519.000 5,37,684 900.00 9,32,400.00
c) above 900mm to 1800mm girth Nr c) above 900mm to 1800mm girth Nr 1,137.00 777.000 8,83,449 1,400.00 15,91,800.00
d) above 1800mm Nr d) above 1800mm Nr 68.00 2,052.000 1,39,536 2,000.00 1,36,000.00
Total site clearance and dismmantling carried to grand
Total Site Clearance and Dismantling carried to Grand Summary 59,55,232 83,58,790.00
summary.
3 EARTH WORKS 3 EARTH WORKS - -
Roadway excavation necessary for construction of roadway including
Roadway excavation necessary for construction of roadway including cutting and
cutting and loading in tippers, trimming bottom and side slopes, in
loading in tippers, trimming bottom and side slopes, in accordance with requirements
accordance with requirements of lines, grades and cross sections, and
3.01 of lines, grades and cross sections, and transporting to the embankment location within 3.01 - -
transporting to the embenkment location within all leads and lifts up
all leads and lifts upto 1000 m complete as per technical specification clause 301 and
to 1000 m complete as per technical specification clause 301 and
305.
305.
b) Ordinary soil / Hard soil Cum b) Ordinary soil / Hard soil Cum 1,65,677.00 28.000 46,38,956 35.00 57,98,695.00

Loosening and re-compacting the original ground/ sub-grade up


Loosening and re-compacting the original ground/ sub-grade up to the required depths
e) Cum e) to the required depths as directed by the Engineer and as per Cum 6,300.00 43.000 2,70,900 25.00 1,57,500.00
as directed by the Engineer and as per Technical Specifications Clause 301 & 305
Technical Specifications Clause 301 & 305

Construction of embankment with approved material obtained


Construction of embankment with approved material obtained from borrow area with from borrow area with all lifts and leads, transporting to site,
3.02 all lifts and leads, transporting to site, spreading, grading to required slope and Cum 3.02 spreading, grading to required slope and compacting complete as Cum 27,613.00 149.000 41,14,337 70.00 19,32,910.00
compacting complete as per drawings and technical specification clause 305. per drawings and technical specification clause 305.

Construction of embankment with approved materials deposited


Construction of embankment with approved materials deposited at site from roadway at site from roadway cutting and excavation from drain and
3.03 cutting and excavation from drain and foundation of other structures graded and Cum 3.03 foundation of other structures graded and compacted complete as Cum 25,005.00 74.000 18,50,370 30.00 7,50,150.00
compacted complete as per drawings and technical specification clause 305. per drawings and technical specification clause 305.

Construction of subgrade and Earthen shoulder with approved


Construction of subgrade and Earthen shoulder with approved material obtained from material obtained from borrow area with all lifts & leads,
3.04 borrow area with all lifts & leads, transporting to site, spreading, grading to required Cum 3.04 transporting to site, spreading, grading to required slope and Cum 2,78,676.00 174.000 4,84,89,624 70.00 1,95,07,320.00
slope and compacted complete as per drawings and technical specification clause 305. compacted complete as per drawings and technical specification
clause 305.
Construction of Median and Island above road level with
Construction of Median and Island above road level with approved material deposited approved material deposited at site from roadway cutting and
at site from roadway cutting and excavation for drain and foundation of other excavation for drain and foundation of other structures, spread,
3.08 Cum 3.08 Cum 713.00 121.000 86,273 150.00 1,06,950.00
structures, spread, graded and compacted complete as per drawings and technical graded and compacted complete as per drawings and technical
specification clause 407. specification clause 407.
Total Earth Works carried to Grand Summary Total Earth Works carried to Grand Summary 5,94,50,460 2,82,53,525.00
SUB-BASE, BASE COURSES (NON-BITUMINOUS) AND
4 SUB-BASE, BASE COURSES (NON-BITUMINOUS) AND SHOULDERS 4 - -
SHOULDERS
Constructing Hard shoulder with Naturally obtained Granular sub-
Constructing Hard shoulder with Naturally obtained Granular sub-base (GSB) base (GSB) complete as per drawings and Technical
4.01 complete as per drawings and Technical Specification Clause 401 (Grading I, Table Cu.m. 4.01 Cu.m. 73,568.00 581.000 4,27,43,008 400.00 2,94,27,200.00
Specification Clause 401 (Grading I, Table 400-1)
400-1)

Construction of granular sub-base with crushed stone aggregated


only, by mixing material in a mechanical mix plant at OMC,
Construction of granular sub-base with Naturally Obtained Granual sub base (GSB), carriage of mixed Material to work site, spreading in uniform
carriage of mixed Material to work site, spreading in uniform layers with motor grader layers with motor grader on prepared surface and compacting
4.02 4.02 - -
on prepared surface and compacting with vibratory power roller to achieve the desired with vibratory power roller to achieve the desired density,
density, complete as per technical specification clause 401 complete as per technical specification clause 401

b) As per Table 400-1, Coarse- Graded Grading I Cum b) As per Table 400-1, Coarse-Graded Grading I Cum 74,250.00 581.000 4,31,39,250 400.00 2,97,00,000.00
Providing, laying, spreading and compacting graded stone
Providing, laying, spreading and compacting graded stone aggregate to wet mix aggregate to wet mix macadam specification including premixing
macadam specification including premixing the Material with water at OMC in the Material with water at OMC in mechanical mix plant carriage
mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform of mixed Material by tipper to site, laying in uniform layers with
4.03 4.03 paver in sub- base / base course on well prepared surface and - -
layers with paver in sub- base / base course on well prepared surface and compacting
with vibratory roller to achieve the desired density complete as per drawing and compacting with vibratory roller to achieve the desired density
technical specification clause 406. complete as per drawing and technical specification clause 406.

Mechanically laid base (Spread by motor grader) including


Mechanically laid base (Spread by motor grader) including profile corrective course
a) Cum a) profile corrective course and access roads if applicable Cum 23,816.00 742.000 1,76,71,472 785.00 1,86,95,560.00
and access roads if applicable

b) Mechanically laid base (laid by Electronic Sensor Paver) Cum b) Mechanically laid base (laid by Electronic Sensor Paver) Cum 29,186.00 755.000 2,20,35,430 805.00 2,34,94,730.00
Total Sub-Base, Base Courses (Non-Bituminous) and Shoulders carried to Grand Total Sub-Base, Base Courses (Non-Bituminous) and
12,55,89,160 10,13,17,490.00
Summary Shoulders carried to Grand Summary
BASE AND SURFACE COURSES (BITUMINOUS)
5 BASE AND SURFACE COURSES (BITUMINOUS) 5 - -
Providing and applying primer coat with bitumen emulsion on
Providing and applying primer coat with bitumen emulsion on prepared surface of prepared surface of granular Base including clearing of road
granular Base including clearing of road surface and spraying primer at the rate of 0.60 surface and spraying primer at the rate of 0.60 kg/sqm using
5.01 Sqm 5.01 Sqm 2,05,624.00 26.000 53,46,224 24.00 49,34,976.00
kg/sqm using mechanical means complete as per drawings and technical specification mechanical means complete as per drawings and technical
clause 502. specification clause 502.
Providing surface dressing with aggregate using Bitumen over
Providing surface dressing with aggregate using Bitumen over primed water bound
primed water bound macadam/ wet mix macadam complete as - -
5.02 macadam/ wet mix macadam complete as per Technical Specifications Clause 510 5.02
per Technical Specifications Clause 510
b) Second Coat Surface Dressing Sqm b) Second Coat Surface Dressing Sqm 14,000.00 57.000 7,98,000 35.00 4,90,000.00
Providing and applying tack coat with bitumen complete as per
5.03
drawings and Technical Specification clause 503.
a) @ 2.0 to 2.5 kg/10m2 on bituminous surface Sqm a) @ 2.0 to 2.5 kg/10m2 on bituminous surface Sqm 10,72,298.00 9.000 96,50,682 9.00 96,50,682.00
@ 2.5 to 3.0 kg/10m2 on granular surface treated with primer/hungry bituminous @ 2.5 to 3.0 kg/10m2 on granular surface treated with
b) Sqm b) Sqm 2,05,624.00 11.000 22,61,864 11.00 22,61,864.00
surface. primer/hungry bituminous surface.
Providing and laying bituminous macadam (grading II) with 100-
120 TPH batch type HMP producing an average output of 75
Providing and laying bituminous macadam (Grading II) with 100-120 TPH hot mix tonnes per hour using crushed aggregates of specified grading,
plant producing an average output of 75 tonnes per hour using crushed aggregates of premixed with bituminous binder grade,transported to site,laid
specified grading premixed with bituminous binder (VG-30), transported to site, laid over previously prepaired surface with paver finisher with senser
5.04 cum 5.04 controll to the required grade, level and alignment and rolled Cum 28,823.00 4,465.000 12,86,94,695 4,310.00 12,42,27,130.00
over a previously prepared surface with paver finisher with sensor control to the
required grade, level and alignment and rolled complete as per drawings and Technical complete as per drawings and Technical specification clauses
Specification clauses 501.6 and 501.7 or as directed by the Engineer. 501.6 and 501.7 or as directed by the engineer (VG-30).

Providing and laying bituminous concrete with 100-120 TPH


batch type hot mix plant producing an average output of 75
Providing and laying semi dense bituminous concrete with 100-120 TPH batch type tonnes per hour using crushed aggregates of specified grading,
HMP producing an average output of 75 tonnes per hour using crushed aggregates of premixed with bituminous binder as per prroved mix design,
specified grading, premixed with bituminous binder (VG-30) as per approved mixed transporting the hot mix to work site, laying with a hydrostatic
5.08 design, transporting the hot mix to work site, laying with a hydrostatic paver finisher Cum 5.08 paver finisher with sensor controll to the required grade, level and Cum 8,981.00 5,942.000 5,33,65,102 6,917.00 6,21,21,577.00
with sensor control to the required grade, level and alignment, rolling with smooth alignments rolling with smooth wheeled, vibratory and tandem
wheeled, vibratory and tandem rollers to achieve the desired compaction complete as rollers to achieve the desired compaction complete as per
per drawings and Technical Specification clause 508. drawings and Technical specification clause 508. (VG-30).

Variation of quantity of VG 40 grade bitumen in bituminous


Variation of quantity of VG 30 grade bitumen in bituminous courses as per Technical
5.10 MT 5.10 courses as per Technical Specification Clause 507.9 and 509.9 MT 230.00 39,514.310 90,88,291 5,000.00 11,50,000.00
Specification Clause 507.9 and 509.9

Variation of quantity of rapid emulsion in Tack coat as per Technical Specification Variation of quantity of rapid emulsion in Tack coat as per
5.11 5.11 - -
Clause 503. Technical Specification Clause 503.
a) 0.5 kg extra for normal bituminous surface MT a) 0.5 kg extra for normal bituminous surface MT 54.00 34,938.310 18,86,669 4,000.00 2,16,000.00
b) 0.5 kg extra for Granular Surface MT b) 0.5 kg extra for Granular Surface MT 10.00 34,938.310 3,49,383 4,000.00 40,000.00
Variation of quantity of slow emulsion for prime coat as per Technical Specification Variation of quantity of slow emulsion for prime coat as per
5.12 MT 5.12 MT 21.00 33,773.510 7,09,244 5,000.00 1,05,000.00
clause 502. Technical Specification clause 502.
Removal of all failed material, trimming of completed excavation
to provide firm vertical faces, cleaning of surface, painting of
Removal of all failed material, trimming of completed excavation to provide firm tack coat on the sides and base of excavation as per clause 503,
vertical faces, cleaning of surface, painting of tack coat on the sides and base of back filling the pot holes with hot bituminous material of grading
5.13 excavation as per clause 503, back filling the pot holes with hot bituminous material of sqm 5.13 I as per clause 504, compacting, trimming and finishing the sqm 8,548.00 269.000 22,99,412 280.00 23,93,440.00
grading I as per clause 504, compacting, trimming and finishing the surface to form a surface to form a smooth continuous surface, all as per clause
smooth continuous surface, all as per clause 3004.2 3004.2

Providing and applying low viscosity bitumen emulsion for


Providing and applying low viscosity bitumen emulsion for sealing cracks less than 3
5.14 sqm 5.14 sealing cracks less than 3 mm wide or incipient fretting or sqm 11,967.00 35.000 4,18,845 36.00 4,30,812.00
mm wide or incipient fretting or disintegration in an existing bituminous surfacing.
disintegration in an existing bituminous surfacing.
Providing and laying slurry seal consisting of a mixture of fine
Providing and laying slurry seal consisting of a mixture of fine aggregates, portland aggregates, portland cement filler, bituminous emulsion and
cement filler, bituminous emulsion and water on a road surface including cleaning of water on a road surface including cleaning of surface, mixing of
5.15 sqm 5.15 sqm 17,096.00 55.000 9,40,280 25.00 4,27,400.00
surface, mixing of slurry seal in a suitable mobile plant, laying and compacting to slurry seal in a suitable mobile plant, laying and compacting to
provide even riding surface provide even riding surface
Full depth repair of section in case of poor pavement complete as per drawings or as Full depth repair of section in case of poor pavement complete as
5.16 sqm 5.16 sqm 1,710.00 1,296.928 22,17,747 500.00 8,55,000.00
directed by the engineer per drawings or as directed by the engineer
Total Base and Surface Courses (Bituminous) carried to
Total Base and Surface Courses (Bituminous) carried to Grand Summary 21,80,26,438 20,93,03,881.00
Grand Summary
6 STRUCTURES 6 STRUCTURES - -
6A CULVERTS: 6A CULVERTS: - -
Constuction of temporary diversion, including across water way, for
Construction of temporary diversion, including across waterway, for passage of traffic,
6A01 Lm 6A01 passage of traffic, complete as per drawings and technical Lm 200.00 7,385.000 14,77,000 4,000.00 8,00,000.00
complete as per drawings and Technical Specifications Clause 112.3,
specification clause 112.3
Excavation of foundation for culverts including preparation of
Excavation of foundation for culverts including preparation of foundation bed foundation bed complete as per drawing and Technical
6A02 complete as per drawing and Technical Specifications Clause 304 in the following 6A02 Specifications Clause 304 in the following strata - -
strata

a) Ordinary soil / Hard soil Cum a) Ordinary soil / Hard soil Cum 410.00 32.000 13,120 70.00 28,700.00
b) Ordinary rock / Soft rock Cum b) Ordinary rock / Soft rock Cum 146.00 40.000 5,840 150.00 21,900.00
c) Hard Rock (Blasting Prohibited) Cum c) Hard Rock (Blasting Prohibited) Cum 29.00 254.000 7,366 250.00 7,250.00
Providing and laying granular material for pipe bedding of Hume
Providing and laying granular material for pipe bedding of Hume Pipe culverts and Pipe culverts and replacement of soft and loose patches in the
6A03 replacement of soft and loose patches in the bearing area of the Box structure with Cum 6A03 bearing area of the Box structure with layers not exceeding 300 Cum 198.00 747.000 1,47,906 450.00 89,100.00
layers not exceeding 300 mm as per drawing and Technical Specifications Clause 2904 mm as per drawing and Technical Specifications Clause 2904

Plain cement concrete in levelling course in open foundation,


Plain cement concrete in levelling course in open foundation, concrete pipe bedding
concrete pipe bedding and apron complete as per drawing and
6A04 and apron complete as per drawing and Technical Specifications Section 1500 and 6A04 - -
Technical Specifications Section 1500 and 1700
1700

a) M15 grade Cum a) M15 grade Cum 29.00 3,496.000 1,01,384 2,800.00 81,200.00
Providing. laying and jointing RCC. NP-4 Hume Pipes for
Providing. laying and jointing RCC. NP-4 machine finish Hume Pipes for culverts or
culverts or equivalent pipes under IS:458-1988, approved by the
6A16 equivalent pipes under IS:458-1988, approved by the Engineer complete as per 6A16 - -
Engineer complete as per Technical Specifications section 2900
Technical Specifications section 2900

d) Diameter 1200mm Lm d) Diameter 1200mm Lm 211.00 3,842.000 8,10,662 4,800.00 10,12,800.00


Plain cement concrete grade M-20 in Headwall of Access Road
Plain cement concrete grade M-20 in Headwall of Access Road Culverts complete as
6A17 Cum 6A17 Culverts complete as per drawing and Technical Specifications Cum 270.00 3,890.000 10,50,300 3,500.00 9,45,000.00
per drawing and Technical Specifications Clause 1500 and 1700
Clause 1500 and 1700
Painting of culvert reference number complete as per Technical
Painting of culvert reference number complete as per Technical Specifications section
6A18 sqm 6A18 Specifications section 800 or as directed by the Engineer. sqm 10.00 57.000 570 150.00 1,500.00
800 or as directed by the Engineer.
Geo textiles filter membrane underneath pitching complete as per
Geo textiles filter membrane underneath pitching complete as per drawings and
6A22 Sqm 6A22 drawings and technical specification clause 2504 and as directed Sqm 222.00 74.000 16,428 30.00 6,660.00
technical specification clause 2504 and as directed by the Engineer.
by the Engineer.
Filter media beneath the pitching/revetment on slopes for
Filter media beneath the pitching/revetment on slopes for protection of embankment as protection of embankment as per drawings and Technical
6A23 Cum 6A23 Cum 33.00 416.000 13,728 300.00 9,900.00
per drawings and Technical Specifications clause 2504 and as directed by the Engineer Specifications clause 2504 and as directed by the Engineer

Pitching/revetment on slopes with Cement Concrete blocks in


Pitching/revetment on slopes with Cement Concrete blocks in M15 grade conforming M15 grade conforming to Section 1700 complete as per drawings
6A24 to Section 1700 complete as per drawings Technical Specifications 2504 and as Cum 6A24 Cum 67.00 3,566.000 2,38,922 4,000.00 2,68,000.00
Technical Specifications 2504 and as directed by the Engineer.
directed by the Engineer.

750 thick flexible stone apron as per Clause No. 2503.1 of


750 thick flexible stone apron as per Clause No. 2503.1 of Technical Specification and
6A27 Cum 6A27 Technical Specification and as directed by the Engineer Cum 93.00 749.000 69,657 900.00 83,700.00
as directed by the Engineer
Construction and fixing of PCC Pillar with M15 grade of
Construction and fixing of PCC Pillar with M15 grade of concrete of size 400 x 400 x concrete of size 400 x 400 x 1000 mm for inscribing Structure
6A29 1000 mm for inscribing Structure Number as per drawing and Technical Specification Nr 6A29 Number as per drawing and Technical Specification section Nr 20.00 116.000 2,320 800.00 16,000.00
section 1500, 1700 or as directed by the Engineer 1500, 1700 or as directed by the Engineer

Total Culverts carried to Grand Summary Total Culverts carried to Grand Summary 39,55,203 33,71,710.00
6B BRIDGES 6B BRIDGES - -
Construction of temporary, including across water way,for passage of
Construction of temporary diversion, including across waterway, for passage of traffic,
traffic, complete as per Technical Specifications Section Clause
6B01 complete as per drawing and Technical Specifications Clause 112.3, including Lm 6B01 Lm 100.00 7,385.000 7,38,500 4,000.00 4,00,000.00
112.3.Including teporary cross drainage.
temporary cross drainage
Foundation Foundation - -
Earthwork in excavation of foundations for structures including
Earthwork in excavation of foundations for structures including all leads and lifts
6B03 6B03 all leads and lifts complete as per drawings and Technical - -
complete as per drawings and Technical specifications clause 304.
specifications clause 304.
a) In all types of soil Cum a) In all types of soil Cum 140.00 32.000 4,480 70.00 9,800.00
b) In soft/ordinary rock Cum b) In soft/ordinary rock Cum 50.00 40.000 2,000 150.00 7,500.00
c) In hard rock (Blasting Prohibited) Cum c) In hard rock (Blasting Prohibited) Cum 10.00 254.000 2,540 250.00 2,500.00
Plain cement concrete garde M15 in foundation and fill around foundation to protect Plain cement concrete grade M-15 in foundation and fill around
6B04 from erosion complete as per drawing and Technical Specifications Section 1500 and Cum 6B04 foundation to protect from errosion complete as per drawing and Cum 18.00 3,496.000 62,928 3,000.00 54,000.00
1700 technical specifications section 1500 and 1700.
Providing & laying Plain cement concrete levelling course in
Providing & laying Plain cement concrete levelling course in foundation and fill around foundation and fill around foundation to protect from erosion
foundation to protect from erosion including form work but excluding the cost of including form work but excluding the cost of reinforcement
6B05 6B05 - -
reinforcement complete as per drawing and Technical Specifications sections 1500, complete as per drawing and Technical Specifications sections
1700 and 2100. 1500, 1700 and 2100.
b) M-20 grade Cum b) M-20 grade Cum 106.00 3,679.000 3,89,974 3,500.00 3,71,000.00
Supplying, placing and fixing TMT Fe 500 bar reinforcement
Supplying, placing and fixing TMT Fe 500 bar reinforcement complete as per drg. and
6B17 6B17 complete as per drg. and Technical specifications section 1600. - -
Technical specifications section 1600.

a) For Foundation MT a) For Foundation MT 3.00 64,359.000 1,93,077 50,000.00 1,50,000.00


b) For sub-structure MT b) For sub-structure MT 1.00 64,449.000 64,449 50,000.00 50,000.00
c) For super-structure MT c) For super-structure MT 2.00 65,124.000 1,30,248 50,000.00 1,00,000.00
Sub-Structure Sub-Structure - -
Providing & laying Reinforced Cement Concrete in sub-structure
Providing & laying Reinforced Cement Concrete in sub-structure including form work including form work but excluding the cost of reinforcement
6B19 but excluding the cost of reinforcement complete as per drg. and Technical 6B19 - -
complete as per drg. and Technical specifications sections 1500,
specifications sections 1500, 1700 & 2200.
1700 & 2200.
a) M-20 grade Cum a) M-20 grade Cum 110.00 4,033.000 4,43,630 4,000.00 4,40,000.00
Bearing Bearing - -
Supply & fixing of bearings complete as per drg. and Technical specifications section Supply & fixing of bearings complete as per drg. and Technical
6B20 6B20 - -
2000. specifications section 2000.
a) Tar paper bearing Sqm a) Tar paper bearing Sqm 5.00 51.000 255 200.00 1,000.00
Providing & fixing of expansion joints complete as per drg. and Technical Providing & fixing of expansion joints complete as per drg. and
6B22 6B22 - -
specifications section 2600 Technical specifications section 2600
Providing and fixing filler type expansion joint with 2mm thick
Providing and fixing filler type expansion joint with 2mm thick copper plate, 20mm copper plate, 20mm thick compressible fiber board, 20mm thick
thick compressible fiber board, 20mm thick premoulded joint filler in expansion joint premoulded joint filler in expansion joint and filling joint sealant
a) Lm a) Lm 48.00 1,618.000 77,664 2,500.00 1,20,000.00
and filling joint sealant compound complete as per drawings and Technical compound complete as per drawings and Technical specification
specification section 2600. section 2600.
Providing & laying Reinforced Cement Concrete in super-structure including form Super Structure
6B23 work but excluding the cost of reinforcement complete as per drg. and Technical - -
specifications sections 1500, 1700 & 2300.
Providing & laying Reinforced Cement Concrete in super-
structure including form work but excluding the cost of
a) Solid slab 6B23 - -
reinforcement complete as per drg. and Technical specifications
sections 1500, 1700 & 2300.
a) Solid slab
ii) M-30 grade Cum ii) M-30 grade Cum 20.00 4,936.000 98,720 5,500.00 1,10,000.00
Providing 25 mm thick mastic asphalt over the top of the deck
Providing 25 mm thick mastic asphalt over the top of the deck after applying prime after applying prime coat underneath wearing course complete as
6B26 coat underneath wearing course complete as per Technical Specifications Clause 2702, Sqm 6B26 Sqm 324.00 410.000 1,32,840 350.00 1,13,400.00
per Technical Specifications Clause 2702, 503 and 515 (Cost of
503 and 515 (Cost of Prime Coat Included) Prime Coat Included)
Providing 40 mm thick Bituminous concrete in one layer in
Providing 40 mm thick Bituminous concrete in one layer in wearing course complete as wearing course complete as directed by the Engineer and as per
6B27 directed by the Engineer and as per Technical Specifications Clause 2702/509 (Cost of Cum 6B27 Cum 13.00 6,820.000 88,660 7,000.00 91,000.00
Technical Specifications Clause 2702/509 (Cost of Tack Coat
Tack Coat Included)
Included)
Providing cement concrete crash barrier in M-40 grade including
Providing cement concrete crash barrier in M-40 grade including safety kerb,
safety kerb, reinforcement and G.I. pipe complete as per drawing
6B29 reinforcement and G.I. pipe complete as per drawing & Technical Specifications Lm 6B29 Lm 59.00 3,277.000 1,93,343 11,000.00 6,49,000.00
& Technical Specifications sections 1500, 1600, 1700, 2200 &
sections 1500, 1600, 1700, 2200 & clause 809. clause 809.
- -
- -
- -
Misc. Items Misc. Items - -
Providing weep holes in brick masonry / plain / reinforced
Providing weep holes in brick masonry / plain / reinforced concrete abutments, wing concrete abutments, wing walls / return walls etc. with 100mm
walls / return walls etc. with 100mm dia A.C. pipe, extending through the full width of dia A.C. pipe, extending through the full width of structure with
6B30 Nr 6B30 slope of IV:20H towards draining face including porous concrete Nr 20.00 78.000 1,560 250.00 5,000.00
structure with slope of IV:20H towards draining face including porous concrete blocks
complete as per drawing and Technical Specifications clause 2706. blocks complete as per drawing and Technical Specifications
clause 2706.

Providing & fixing drainage Spouts complete as per drawing and Technical Providing & fixing drainage Spouts complete as per drawing and
6B31 Nr 6B31 Nr 4.00 720.000 2,880 2,500.00 10,000.00
Specifications Clause 2705. Technical Specifications Clause 2705.
Back filling behind abutment with selected granular material of
Back filling behind abutment with selected granular material of approved quality as per
6B32 Cum 6B32 approved quality as per Technical Specifications Clause 305 Cum 149.00 672.000 1,00,128 400.00 59,600.00
Technical Specifications Clause 305

Filter media behind abutments, wing walls, & return walls,


Filter media behind abutments, wing walls, & return walls, including all material,
including all material, labour, equipment carriage etc. all complete
6B33 labour, equipment carriage etc. all complete as per drawing and Technical Specification Cum 6B33 Cum 85.00 318.000 27,030 400.00 34,000.00
as per drawing and Technical Specification Clauses 305, 309 &
Clauses 305, 309 & 2504. 2504.
Providing & laying plain cement concrete M-15 grade in levelling
Providing & laying plain cement concrete M-15 grade in levelling course under the course under the approach slab complete as per drg. and
6B34 approach slab complete as per drg. and Technical specifications sections 1700, 2100 Cum 6B35 Cum 26.00 3,496.000 90,896 3,000.00 78,000.00
Technical specifications sections 1700, 2100 and 2700.
and 2700.

Providing & laying reinforced cement concrete M-30 grade in


Providing & laying reinforced cement concrete M-30 grade in approach slab including approach slab including form work and reinforcement complete
6B35 form work and reinforcement complete as per drg. and Technical specifications Cum 6B36 as per drg. and Technical specifications sections 1500, 1600, Cum 50.00 7,282.000 3,64,100 4,500.00 2,25,000.00
sections 1500, 1600, 1700 & 2100 and clause 2704. 1700 & 2100 and clause 2704.

Painting of Bridge No. and span arrangement as per drg., IRC:7-1971 and Technical Painting of Bridge No. and span arrangement as per drg., IRC:7-
6B40 Nr 6B41 Nr 6.00 57.000 342 500.00 3,000.00
specifications section 800. 1971 and Technical specifications section 800.
Total Bridges carried to Grand Summary Total Bridges carried to Grand Summary 32,10,244 30,83,800.00
6C REPAIR & REHABILITATION 6C REPAIR & REHABILITATION - -
Construction of temporary diversion, including across waterway,
Construction of temporary diversion, including across waterway, for passage of traffic, for passage of traffic, complete as per drawings and Technical
6C01 complete as per drawings and Technical Specifications Section Clause 112.3, including Lm 6C01 Lm 61.00 7,385.000 4,50,485 4,000.00 2,44,000.00
Specifications Section Clause 112.3, including temporary cross
temporary cross drainage drainage
Dismantle of various items of structures complete as per
Dismantle of various items of structures complete as per Technical specification clause
6C02 6C02 Technical specification clause 202 or as directed by the Engineer. - -
202 or as directed by the Engineer.

a) RCC Cum a) RCC Cum 10.00 4,630 500.00 5,000.00


463.000
c) Existing Wearing coat sqm c) Existing Wearing coat sqm 2,433.00 53.000 1,28,949 80.00 1,94,640.00
d) Stone/Brick masonry Cum d) Stone/Brick masonry Cum 107.00 189.000 20,223 150.00 16,050.00
f) NP4 Pipe
f) NP4 Pipe Lm Lm 153.00 151.000 23,103 100.00 15,300.00
Providing and fixing filler type expansion joint with 2mm thick
Providing and fixing filler type expansion joint with 2mm thick copper plate, 20mm copper plate, 20mm thick compressible fiber board, 20mm thick
thick compressible fiber board, 20mm thick premoulded joint filler in expansion joint premoulded joint filler in expansion joint and filling joint sealant
6C16 Lm 6C16 Lm 80.00 1,917.000 1,53,360 2,500.00 2,00,000.00
and filling joint sealant compound complete as per drawings and Technical compound complete as per drawings and Technical specification
specification section 2600. section 2600.
Replacement of drainage spout wherever broken including necessary gratings and Replacement of drainage spout wherever broken including
6C17 drainage assembly complete as per drawing and Technical Specification clause 2705 as Nr 6C17 necessary gratings and drainage assembly complete as per Nr 80.00 720.000 57,600 2,200.00 1,76,000.00
directed by the Engineer drawing and Technical Specification clause 2705 as directed by
the Engineer
Cleaning of the Weep holes of Abutment and wing wall as per Technical specification Cleaning of the Weep holes of Abutment and wing wall as per
6C18 Nr 6C18 Technical specification section 200 or as directed by the Nr 20.00 50.000 1,000 200.00 4,000.00
section 200 or as directed by the Engineer.
Engineer.
Cleaning and removal of vegetation growth from structures
Cleaning and removal of vegetation growth from structures channel and protective
channel and protective works complete as per Technical
6C19 works complete as per Technical specification clause 202 or as directed by the Sqm 6C19 Sqm 6,790.00 20.000 1,35,800 30.00 2,03,700.00
specification clause 202 or as directed by the Engineer.
Engineer.

Replacement of RCC railing including reinforcement as per Technical Specifications Replacement of RCC railing including reinforcement as per
6C20 6C20 Technical Specifications Section 1500, 1600, 1700,1900, 2200, - -
Section 1500, 1600, 1700,1900, 2200, 2800 and Clause 2703.
2800 and
Railing in Clause 2703.
M30 grade
a) Railing in M30 grade Lm a) Lm 133.00 1,687.000 2,24,371 1,750.00 2,32,750.00

c) Mild Steel Railing Lm c) Mild steel railing Lm 344.00 2,928.000 10,07,232 1,500.00 5,16,000.00
Providing 25 mm thick mastic asphalt over the top of the deck
Providing 25 mm thick mastic asphalt over the top of the deck after applying prime
after applying prime coat underneath wearing course complete as
6C30 coat underneath wearing course complete as per Technical Specifications Clause 2702, Sqm 6C30 Sqm 2,450.00 410.000 10,04,500 600.00 14,70,000.00
per Technical Specifications Clause 2702, 503 and 515 (Cost of
503 and 515 (Cost of Prime Coat Included) Prime Coat Included)
Providing 40 mm thick asphaltic concrete in one layer in wearing
Providing 40 mm thick asphaltic concrete in one layer in wearing course complete as
course complete as directed by the Engineer and as per Technical
6C31 directed by the Engineer and as per Technical Specifications Clause 2702/509 (Cost of Cum 6C31 Cum 98.00 6,820.000 6,68,360 7,000.00 6,86,000.00
Specifications Clause 2702/509 (Cost of Tack Coat Included)
Tack Coat Included)

Providing & laying Brick masonry in cement mortar 1:3 (1 cement : 3 coarse sand) in Providing & laying Brick masonry in cement mortar 1:3 (1
6C38 floor protection, foundation, sub-structure complete as per drg. and Technical Cum 6C38 cement : 3 coarse sand) in floor protection, foundation, sub- Cum 19.00 3,490.000 66,310 3,500.00 66,500.00
Specification Section 1300. structure complete as per drg. and Technical Specification
Section 1300.
Providing and laying random rubble stone masonry in cement mortar
Providing & laying random rubble stone masonry in cement mortar 1:3 (1 cement : 3
6C39 Cum 6C39 1:3(1 cement: 3 corse sand) works complete as per drawing and Cum 13.00 2,382.000 30,966 3,000.00 39,000.00
coarse sand) works complete as per drg. and Technical Specifications Section 1400.
technical specification section 1400.
Repair of spalling and patches by PMC mortar 50 to 70mm thick
Repair of spalling and patches by PMC mortar 50 to 70mm thick at soffit of slab as per
at soffit of slab as per clause 2804 of specification and additional
6C44 clause 2804 of specification and additional specification A-3 and as directed by the Sqm 6C44 Sqm 172.00 1,769.000 3,04,268 250.00 43,000.00
specification A-3 and as directed by the Engineer
Engineer

Guniting concrete surface with cement mortar applied with compressor after cleaning Guniting concrete surface with cement mortar applied with
6C51 surface and spraying with epoxy complete as per Technical Specification clause 2807. Sqm 6C51 compressor after cleaning surface and spraying with epoxy complete Sqm 70.00 730.000 51,100 300.00 21,000.00
[Assumed thickness 25mm] as per technical specification clause 2807.(assumed thickness 25mm)

6C55 Jacketing 6C55 Jacketing - -


Providing and casting in situ controlled cement concrete 300 for RCC work with Providing and casting in situ controlled cement concrete 300 for
jacketing as directed with necessary formwork vibrating, curing, finishing complete as RCC work with jacketing as directed with necessary formwork
a) Cum a) Cum 54.00 3,947.000 2,13,138 5,000.00 2,70,000.00
per Technical specification section 1700 or as directed by the Engineer with all lead & vibrating, curing, fnishing complete as per technical specifcation
lift. section 1700 or as directed by the engineer with all lift and leads.

providing and placing in position TMT Fe500 bar reinforcement


Providing & placing in position TMT Fe-500 bar reinforcement incl. curing, bending,
b) MT b) including curing, bending, hooking, and tying complete as per MT 4.00 64,449.000 2,57,796 50,000.00 2,00,000.00
hooking and tying complete as per Technical Specification section 1600.
technical specification section 1600
Plain cement concrete grade M-20 in head wall of access road
Plain cement concrete grade M-20 in Headwall of Access Road Culverts complete as
6C56 Cum 6C56 culverts complete as per drawings and technical specification clause Cum 72.00 3,890.000 2,80,080 4,000.00 2,88,000.00
per drawing and Technical Specifications Clause 1500 and 1700
1500 and 1700.
Cement plaster 12 mm thick in cement mortar 1:3 complete as per
Cement plaster 12mm thick in cement mortar 1:3 complete as per drawing and
6C57 Sqm 6C57 drawing and technical specifications section 1000 and 1300 and as Sqm 1,447.00 83.000 1,20,101 225.00 3,25,575.00
Technical Specifications Section 1000 and 1300 and as directed by the Engineer
directed by the engineer.
Cement pointing with cement mortar 1:3 on brick/stone work
Cement pointing with cement mortar 1:3 on brick/stone work complete as per
6C58 Sqm 6C58 complete as per drawings and technical specifications section 1000 Sqm 167.00 35.000 5,845 100.00 16,700.00
drawings and Technical Specifications section 1000 and 1300
and 1300
Removal of accumulated debris in Pipe Culverts complete as per Technical Removal of accumulated debris in pipe culverts complete as per
6C59 Lm 6C59 Lm 13.00 100.000 1,300 100.00 1,300.00
Specification clause 202. technical specification clause 202.
Providing and laying boulders apron without wire crates on river bed
Providing and laying boulders apron without wire crates on river bed for protection
for protection against scour with stone boulders weighing not less
6C61 against scour with stone boulders weighing not less than 40 kg each complete as per Cum 6C61 Cum 96.00 710.000 68,160 800.00 76,800.00
than 40 kg each complete as per drawings and technical specification
drawing and Technical specification section 2500
section 2500.
Total Repair & Rehabilitation carried to Grand Summary
Total Repair & Rehabilitation carried to Grand Summary 52,78,677 53,11,315.00

7 DRAINAGE AND PROTECTION WORK 7 DRAINAGE AND PROTECTION WORK - -


Earthwork in excavation in all types of soil including rock
Earthwork in excavation in all types of soil including rock complete as per Technical
7.01 Cum 7.01 complete as per Technical Specification Clauses 304 & 309. Cum 1,624.00 28.000 45,472 70.00 1,13,680.00
Specification Clauses 304 & 309.

Plain Cement concrete M-15 grade in levelling course in drain


Plain Cement concrete M-15 grade in levelling course in drain including centering and including centering and shuttering all complete as per drawing
7.02 shuttering all complete as per drawing and Technical Specification Sections 309, 1500 Cum 7.02 Cum 63.00 3,496.000 2,20,248 3,000.00 1,89,000.00
and Technical Specification Sections 309, 1500 & 1700.
& 1700.

Construction of open unlined drains as per proper slope and


Construction of open unlined drains as per proper slope and dimension as shown in
7.03 Lm 7.03 dimension as shown in drawing and technical specification clause Lm 70,283.00 38.000 26,70,754 15.00 10,54,245.00
drawing and technical specification clause 309.
309.
construction of covered lined drains of concrete grade M-20
Construction of covered lined drains of concrete grade M 25 including cover slab and
including covered slab and reinforcement as per proper slope and
7.06 reinforcement as per proper slope and dimension as shown in drawing and technical Lm 7.06 Lm 946.00 9,080.106 85,89,780 10,000.00 94,60,000.00
dimension as shown in drawing and technical specification clause
specification clause 309.
309.
Construction of lined brick trapezoidal drain complete as per drawings and Technical Constuction of brick lined trapezoidal drain complete as per
7.07 cum 7.07 Cum 4,441.00 1,745.000 77,49,545 1,300.00 57,73,300.00
Specifications section 300and 1300. drawings and technical specifications section 300 and 1300.
Construction of chute drain in cement concrete M-15 with M-15
Construction of chute drain in cement concrete M-15 with M-15 foundation concrete foundation concrete including construction of bell mouth at entry
7.08 including construction of bell mouth at entry as per drawings and Technical Lm 7.08 Lm 170.00 755.000 1,28,350 1,500.00 2,55,000.00
as per drawings and Technical Specification Sections 309, 1500
Specification Sections 309, 1500 and 1700.
and 1700.
Construction of energy dissipation basin in M-15 as per drawing
Construction of energy dissipation basin in M-15 as per drawing and Technical
7.09 Nr 7.09 and Technical Specification Sections 309, 1500 & 1700. Nr 20.00 1,456.000 29,120 5,000.00 1,00,000.00
Specification Sections 309, 1500 & 1700.

Providing. laying and jointing RCC. NP-4 hume pipes under


Providing. laying and jointing RCC. NP-4 machine finish hume pipes under IS:458-
IS:458-1988, Hume Pipes to discharge storm water from catch
7.11 1988, Hume Pipes to discharge storm water from catch basins as per drawings and 7.11 Lm - -
basins as per drawings and complete as per Technical
complete as per Technical Specifications section 2900
Specifications section 2900
a) 450 mm diameter Lm a) 450 mm diameter Lm 138.00 1,470.000 2,02,860 1,500.00 2,07,000.00
b) 900 mm diameter Lm b) 900 mm diameter Lm 665.00 2,446.000 16,26,590 4,200.00 27,93,000.00
Providing and laying granular material for pipe bedding of Hume
Providing and laying granular material for pipe bedding of Hume Pipe culverts and Pipe culverts and replacement of soft and loose patches in the
7.12 replacement of soft and loose patches in the bearing area of the Box structure with Cum 7.12 bearing area of the Box structure with layers not exceeding 300 Cum 450.00 747.000 3,36,150 400.00 1,80,000.00
layers not exceeding 300 mm as per drawing and Technical Specifications Clause 2904 mm as per drawing and Technical Specifications Clause 2904

Plain cement concrete grade M-20 in Headwall of Access Road


Plain cement concrete grade M-20 in Headwall of Access Road Culverts complete as
7.13 Cum 7.13 Culverts complete as per drawing and Technical Specifications Cum 568.00 3,890.000 22,09,520 4,000.00 22,72,000.00
per drawing and Technical Specifications Clause 1500 and 1700
Clause 1500 and 1700
Providing and laying interlocking paver blocks of high density 65
mm thick M-25 grade in pedestrian pathway and in Island of
Providing and laying interlocking paver blocks of high density 65 mm thick M-25 major intersections areas as shown in the drawing, close jointed
grade in pedestrian pathway and in Island of major intersections areas as shown in the over bed of 50mm thick river sand to a tight pattern, laid to
drawing, close jointed over bed of 50mm thick river sand to a tight pattern, laid to proper line and level including bedding down the completed
7.14 proper line and level including bedding down the completed surface with a plate sqm 7.14 surface with a plate vibrator or by firmly topping level with mallet sqm 11,685.00 621.000 72,56,385 430.00 50,24,550.00
vibrator or by firmly topping level with mallet and a large flat piece of timber, finishing and a large flat piece of timber, finishing by brushing clean dry
by brushing clean dry sand over the surface to fill all the joints thoroughly and as per sand over the surface to fill all the joints thoroughly and as per
Additional Technical Specification A 15 or as directed by the Engineer. Additional Technical Specification A 15 or as directed by the
Engineer.

Providing and laying Grade M15 Concrete perforated erosion


Providing and laying Grade M15 Concrete perforated erosion protection scour blocks protection scour blocks laid on the slopes and bed of the river
laid on the slopes and bed of the river including the rebar, trimming of earth to including the rebar, trimming of earth to required lines and levels,
7.16 cum 7.16 cum 201.00 4,666.000 9,37,866 4,000.00 8,04,000.00
required lines and levels, including capping with concrete on the tops of slopes as per including capping with concrete on the tops of slopes as per
drawings and Specifications drawings and Specifications
Providing and laying plain cement concrete in medians and in
Providing and laying plain cement concrete in medians and in sidewalks, foundations sidewalks, foundations complete as per respective drawings,
7.17 complete as per respective drawings, Technical Specifications section 1500 and 1700 7.17 - -
Technical Specifications section 1500 and 1700 and as directed
and as directed by the Engineer
by the Engineer
Construction of median kerb and island kerb Type B grade M20
Construction of median kerb and island kerb Type A grade M20 (including base
b) Lm b) (including base preparation, foundation and haunch concrete) Lm 1,913.00 224.000 4,28,512 520.00 9,94,760.00
preparation, foundation and haunch concrete)

Pitching/revetment on slopes with Cement Concrete blocks in


Pitching/revetment on slopes with Cement Concrete blocks in M15 grade conforming
M15 grade conforming to Section 1700 complete as per
7.19 to Section 1700 complete as per drawings, technical Specifications 2504 and as Cum 7.19 492.00 3,566.000 17,54,472 4,000.00 19,68,000.00
drawings, technical Specifications 2504 and as directed by the
directed by the Engineer Engineer
Geo textile filters membrane as per Technical Specifications
Geo textile filters membrane as per Technical Specifications Clause 2504 and as
7.21 Sqm 7.21 Clause 2504 and as directed by the Engineer. Sqm 3,665.00 74.000 2,71,210 30.00 1,09,950.00
directed by the Engineer.

Filter media beneath the pitching/revetment on slopes for


Filter media beneath the pitching/revetment on slopes for protection of embankment as protection of embankment as per drawings and Technical
7.22 7.22 Specifications clause 2504 and as directed by the Engineer - -
per drawings and Technical Specifications clause 2504 and as directed by the Engineer

b) Granular Material Cum b) Granular Material Cum 612.00 318.000 1,94,616 400.00 2,44,800.00
Providing and fixing of man hole including excavation, concrete,
Providing and fixing of man hole including excavation, concrete, C.I. Cover, C.I. Steps C.I. Cover, C.I. Steps complete as per drawing and Techinical
7.24 complete as per drawing and Techinical Specifications sections 300, 1500, 1600, 1700 Nr 7.24 Specifications sections 300, 1500, 1600, 1700 and manufacture Nr 5.00 7,000.000 35,000 10,000.00 50,000.00
and manufacture specification approved by the Engineer. specification approved by the Engineer.

Total Drainage and Protection Work rates carried to Grand


Total Drainage and Protection Work rates carried to Grand Summary 3,46,86,450 3,15,93,285.00
Summary
TRAFFIC SIGNAGE AND ROAD APPURTENANCES
8 TRAFFIC SIGNAGE AND ROAD APPURTENANCES 8 - -
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail, 70
Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick cm above road/ground level, fixed on ISMC series channel
corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8
series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m high, m high, 1.1 m below ground/road level, all steel parts and
8.01 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot dip Lm 8.01 fitments to be galvanised by hot dip process, all fittings to Lm 7,621.00 2,713.000 2,06,75,773 1,700.00 1,29,55,700.00
process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on conform to IS:1367 and IS:1364, metal beam rail to be fixed on
the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long the vertical post with a spacer of channel section 150 x 75 x 5
complete as per clause 810 mm, 330 mm long complete as per clause 810

Providing and fixing of retro-reflectorised cautionary, mandatory


and informatory sign made of 1.5mm thick Aluminium
Sheet/3mm Aluminium Composite Material , face to be fully
covered with Class B Type-IV High Intensity Micro Prismatic
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign Grade Sheeting as defined in IRC: 67-2010 having approved
made of 1.5mm thick Aluminium Sheet/3mm Aluminium Composite Material , face to massages e.g. letter, numerals,symbols/legend/arrow etc. in
be fully covered with Class B Type-IV High Intensity Micro Prismatic Grade Sheeting Regional and/or Hindi and /or English as per drawing and
as defined in IRC: 67-2010 having approved massages e.g. letter, TechicalSpecifications for Road and Bridge works (Fourth
numerals,symbols/legend/arrow etc. in Regional and/or Hindi and /or English as per Revision). The sign plate will be fixed with minimum 6 mm dia
drawing and TechicalSpecifications for Road and Bridge works (Fourth Revision). The aluminium rivets back supported on a mild steel angle iron frame
8.02 8.02 - -
sign plate will be fixed with minimum 6 mm dia aluminium rivets back supported on a 35x35x5 mm and one vertical Mild Steel post of NB65 Dia Pipe
mild steel angle iron frame 35x35x5 mm and one vertical Mild Steel post of NB65 Dia (height from crown level of the road and bottom of the sign
Pipe (height from crown level of the road and bottom of the sign board shall not be board shall not be less than 2.10 m.) firmly fixed to the ground
less than 2.10 m.) firmly fixed to the ground by means of properly designed foundation by means of properly designed foundation with M -15 grade
with M -15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground
as per approved drawing including painting of vertical post as per specification. level as per approved drawing including painting of vertical post
as per specification.

a) Informatory Signs a) Informatory Signs - -


Facility information 800 mm x 600 mm complete as per drawings and Technical Facility information 800 mm x 600 mm complete as per drawings
i) Nr i) Nr 78.00 5,679.637 4,43,012 4,000.00 3,12,000.00
Specifications Clause 801 and Technical Specifications Clause 801
Advance direction sign complete as per drawings and Technical Specifications Clause Advance direction sign complete as per drawings and Technical
ii) Sq m ii) Sq m 363.00 10,626.240 38,57,325 5,500.00 19,96,500.00
801 Specifications Clause 801
Route marker sign 450mm x 600 mm complete as per drawings and Technical Route marker sign 450mm x 600 mm complete as per drawings
iii) Nr iii) Nr 25.00 4,867.882 1,21,697 3,500.00 87,500.00
Specifications Clause 801 and Technical Specifications Clause 801
Direction sign less than 0.9 sqm of area complete as per drawings and Techinical direction sign less than 0.9 Sqm of area complete as per drawings
iv) Sq m iv) Sq m 11.00 8,855.240 97,408 5,500.00 60,500.00
Specification clause 801. and technical specification clause 801.
b) Cautionary Signs b) Cautionary Signs - -
Triangular 900 mm side complete as per drawings and Technical Specifications Clause Triangular 900 mm side complete as per drawings and Technical
i) Nr i) Nr 303.00 5,285.229 16,01,424 3,500.00 10,60,500.00
801 Specifications Clause 801
Hazard marker 300 x 900 mm complete as per drawings and Technical Specifications Hazard marker 180 x 1200 mm complete as per drawings and
iii) Nr ii) Nr 4.00 3,582.794 14,331 3,000.00 12,000.00
Clause 801 Technical Specifications Clause 801
c) Mandatory Signs c) Mandatory Signs - -
Triangular 900 mm side (for "GIVE WAY" sign) complete as per
Triangular 900 mm side (for "GIVE WAY" sign) complete as per drawings and
i) Nr i) drawings and Technical Specifications Clause 801 Nr 50.00 5,285.229 2,64,261 3,500.00 1,75,000.00
Technical Specifications Clause 801

Stop sign - Octagon of size 900 mm complete as per drawings and Technical Stop sign - Octagon of size 900 mm complete as per drawings
ii) Nr ii) Nr 209.00 7,485.526 15,64,475 6,500.00 13,58,500.00
Specifications Clause 801 and Technical Specifications Clause 801
Speed limit compulsory keep left 600 mm dia meter complete as
Speed limit compulsory keep left 600 mm dia meter complete as per drawings and
iii) Nr iii) per drawings and Technical Specifications Clause 801 Nr 52.00 4,923.266 2,56,010 3,500.00 1,82,000.00
Technical Specifications Clause 801

Providing and laying of hot applied thermoplastic compound 2.5


Providing and laying of hot applied thermoplastic compound 2.5 mm thick including mm thick including reflectorising glass beads @ 250 gms per sqm
reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of area, thickness of 2.5 mm is exclusive of surface applied glass
8.03 surface applied glass beads as per IRC:35 .The finished surface to be level, uniform 8.03 beads as per IRC:35 .The finished surface to be level, uniform - -
and free from streaks and holes complete as per drawings and technical specification and free from streaks and holes complete as per drawings and
clause 803. technical specification clause 803.

a) Lane/centerline/edge marking or any other marking Sqm a) Lane/centerline/edge marking or any other marking Sqm 16,983.00 471.000 79,98,993 260.00 44,15,580.00
b) Directional arrows, lettering etc b) Directional arrows, lettering etc - -
i) Straight (nr) RM13 Nr i) Straight (nr) RM13 Nr 293.00 518.000 1,51,774 600.00 1,75,800.00
ii) Left/right (nr) RM14 & 15 Nr ii) Left/right (nr) RM14 & 15 Nr 178.00 533.000 94,874 600.00 1,06,800.00
iii) Comb (nr) RM 16& 17 Nr iii) Comb (nr) RM 16& 17 Nr 628.00 661.000 4,15,108 750.00 4,71,000.00
iv) Lettering Nr iv) Lettering Nr 95.00 141.000 13,395 500.00 47,500.00
v) Chevron Marking Sqm v) Chevron Marking Sqm 1,310.00 471.000 6,17,010 450.00 5,89,500.00
vi) Diagonal Marking Sqm vi) Diagonal Marking Sqm 210.00 471.000 98,910 450.00 94,500.00
vii) Pedestrian Crossing Sqm vii) Pedestrian Crossing Sqm 2,734.00 471.000 12,87,714 450.00 12,30,300.00
- -
Reinforced cement concrete M15 grade kilometre stone of
Reinforced cement concrete M15 grade kilometre stone of standard design as per standard design as per IRC:8-1980, fixing in position including
8.04 IRC:8-1980, fixing in position including painting and printing etc complete as per 8.04 - -
painting and printing etc complete as per drawings and technical
drawings and technical specification clause 804. specification clause 804.
a) Hectometer Stone Nr a) Hectometer Stone Nr 173.00 423.000 73,179 300.00 51,900.00
b) Kilometer Stone Nr b) Kilometer Stone Nr 35.00 1,420.000 49,700 1,500.00 52,500.00
c) 5th kilometer stone Nr c) 5th kilometer stone Nr 16.00 2,349.000 37,584 2,500.00 40,000.00
Supplying and fixing of boundary stones of M15 grade concrete
Supplying and fixing of boundary stones of M15 grade concrete complete as per
8.05 Nr 8.05 complete as per drawing and Technical Specifications clause 806 Nr 216.00 319.000 68,904 300.00 64,800.00
drawing and Technical Specifications clause 806
Providing and fixing retro-reflectorised road delineators complete
Providing and fixing retro-reflectorised road delineators complete as per drawing and
8.06 8.06 as per drawing and Technical Specification Clause 805. - -
Technical Specification Clause 805.

a) Cluster of Red Reflectors. Nr a) Cluster of Red Reflectors. Nr 7.00 2,278.073 15,947 1,000.00 7,000.00
b) Road way delineators. Nr b) Road way delineators. Nr 1,734.00 1,920.000 33,29,280 600.00 10,40,400.00
Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows
medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above duly painted on mediam weight steel channels (ISMC series) 100
8.08 Lm 8.08 Lm 7,644.00 2,097.000 1,60,29,468 1,600.00 1,22,30,400.00
ground, 2 m centre to centre, complete as per approved drawings and Technical mm x 50 mm, 1.2 meter high above ground, 2meter c/c, complete as
Specification section 800. per approved drawings and technical specification section 800.
Providing and fixing Raised Pavement Marker (Cats Eye, Road
Stud), made of high strength engineering Plastic Body having at
least 13 tons load bearing capacity of pnumatic tyre. Size or
Providing and fixing Raised Pavement Marker (Cats Eye, Road Stud), made of high marker 9 cms x 10 cms x 1.6 cm having shape so that no water
strength engineering Plastic Body having at least 13 tons load bearing capacity of penetration or dust accumulation takes place on reflective surface,
pnumatic tyre. Size or marker 9 cms x 10 cms x 1.6 cm having shape so that no water fitted with electronically welded tough polycarbonate micro
penetration or dust accumulation takes place on reflective surface, fitted with prismatic reflective panels having 16 sq.cms surface area of each
electronically welded tough polycarbonate micro prismatic reflective panels having 16 side having long distance visibility at night and in wet weather
8.09 sq.cms surface area of each side having long distance visibility at night and in wet Nr 8.09 condition. The body of the marker having finger grip for easy and Nr 10,206.00 425.000 43,37,550 170.00 17,35,020.00
weather condition. The body of the marker having finger grip for easy and accurate accurate placement fitted with two number polymer shanks to
placement fitted with two number polymer shanks to anchor the marker with the road anchor the marker with the road for avoiding dislocation of the
for avoiding dislocation of the marker where the road is bleeding or made with softer marker where the road is bleeding or made with softer grade of
grade of bitumen and application with adhesive on Bituminous road complete as per bitumen and application with adhesive on Bituminous road
Additional Technical Specification Clause A-16 complete as per Additional Technical Specification Clause A-16

Solar Powered Traffic Blinkers LED based 300 mm/200 mm dia


Solar Powered Traffic Blinkers LED based 300 mm/200 mm dia signal head with In signal head with In built blinker unit haivng battery & battery
8.10 built blinker unit haivng battery & battery charger unit with photo electric switch Nr 8.10 charger unit with photo electric switch complete as per technical Nr 16.00 75,000.000 12,00,000 16,000.00 2,56,000.00
complete as per technical specification clause 112 and as directed by the Engineer. specification clause 112 and as directed by the Engineer.

Construction of bus shelters for commuters including all building


Construction of bus shelters for commuters including all building and furnishing and furnishing works, etc. complete as per drawings and
8.11 works, etc. complete as per drawings and additional Technical Specifications A-17 or Nr 8.11 Nr 26.00 1,09,000.000 28,34,000 1,25,000.00 32,50,000.00
additional Technical Specifications A-17 or as directed by the
as directed by the Engineer. Engineer.
Repairing of existing Bus Shelter complete as per drawings and
Repairing of existing Bus Shelter complete as per drawings and Technical
8.12 8.12 Technical Specifications section 800, 1300, 2500 or as directed - -
Specifications section 800, 1300, 2500 or as directed by the Engineer.
by the Engineer.
a) Paintitng sqm a) Paintitng sqm 80.00 35.000 2,800 120.00 9,600.00
b) Plastering sqm b) Plastering sqm 160.00 83.000 13,280 250.00 40,000.00
Providing and fixing of liter bins complete as per Manufacturer
Providing and fixing of liter bins complete as per Manufacturer drawing and
8.13 Nr 8.13 drawing and specification and approved by the Engineer. Nr 36.00 10,000.000 3,60,000 5,000.00 1,80,000.00
specification and approved by the Engineer.
Providing and Fixing of water kioks complete as per
Providing and Fixing of water kioks complete as per Manufacturer drawing and
8.14 Nr 8.14 Manufacturer drawing and specification and approved by the Nr 2.00 15,000.000 30,000 50,000.00 1,00,000.00
specification and approved by the Engineer.
Engineer.
Construction of Toilets in rest area complete as per Manufacturer
Construction of Toilets in rest area complete as per Manufacturer drawing and
8.16 Sqm 8.16 drawing and specification and approved by the Engineer. Sqm 35.00 8,000.000 2,80,000 20,000.00 7,00,000.00
specification and approved by the Engineer.

Rest Area for Drivers completeas per Manufacturer drawing and specification and Rest Area for Drivers completeas per Manufacturer drawing and
8.19 Sqm 8.19 Sqm 128.00 10,000.000 12,80,000 12,000.00 15,36,000.00
approved by the Engineer. specification and approved by the Engineer.
Plantation of shrubs in central median including planting with
Plantation of shrubs in central median including planting with manure, gardening and
8.20 Nr 8.20 manure, gardening and maintenance complete as per Technical Nr 224.00 463.000 1,03,712 1,200.00 2,68,800.00
maintenance complete as per Technical Specifications Clause 308.
Specifications Clause 308.
Providing and Construction of Rain water Harvesting complete as
Providing and Construction of Rain water Harvesting complete as per drawings and per drawings and Technical Specification section 300, 1300,
8.25 Nr 8.25 Nr 87.00 50,000.000 43,50,000 25,000.00 21,75,000.00
Technical Specification section 300, 1300, 1500, 1700 or as directed by the Engineer. 1500, 1700 or as directed by the Engineer.

Providing and construction of raised pedestrain crossing / speed


Providing and construction of Raised Pedesterian Crossing / Speed Hump across the hump across the road of 150 mm height and width of 2.5 mt.
road of 150 mm height and width of 2.5 m with M25 grade concrete considering side With M-25 grade concrete considering side slope in 1:10. 100
8.26 slope in 1:10. 100mm dia steel bollard to be fixed on sides. The surface to be painted sqm 8.26 mm dia steel bollard to be fixed on sides. The surface to be sqm 528.00 2,012.233 10,62,459 1,800.00 9,50,400.00
with brick red colour complete as per drawings and Additional Technical Specification painted with brick red colour complete as per drawings and
clause A15 or as directed by the Engineer. additional technical specification clause A-15 or as directed by the
engineer.
Providing and laying Tactile Block of yellow colour conforming
Providing and laying Tactile Block of yellow colour conforming to IS 13801:1993 to IS 13801:1993 (Reaffirmed 1998) of size 250 x 250 x 65 mm
(Reaffirmed 1998) of size 250 x 250 x 65 mm on pedestrian pathway as shown in on pedestrian pathway as shown in drawing and directed by Eng
8.27 drawing and directed by Eng in charge. The tile should be subjected to a pressure of sqm 8.27 in charge. The tile should be subjected to a pressure of not less sqm 1,518.00 650.000 9,86,700 400.00 6,07,200.00
not less than 14N/sqmm. Sample must be approved complete as per Additional than 14N/sqmm. Sample must be approved complete as per
Technical Specification A18 Additional Technical Specification A18

Providing and Construction of speed hump across the road of


Providing and Construction of speed hump across the road of 100mm height with 100mm height with Bituminous concrete of 3.7m Length and
8.28 Bituminous concrete of 3.7m Length and raidus of 17m for the entire width of Lin.m 8.28 raidus of 17m for the entire width of carriageway complete as per Lin.m 30.00 1,659.000 49,770 3,000.00 90,000.00
carriageway complete as per drawings and IRC: 99 or as directed by the Engineer. drawings and IRC: 99 or as directed by the Engineer.

Providing and Construction of raised Rumble strip complete as


Providing and Construction of raised Rumble strip complete as per drawings and
8.29 Lin.m 8.29 per drawings and technical specifications section 500 and 800 or Lin.m 5,684.00 159.213 9,04,964 1,000.00 56,84,000.00
technical specifications section 500 and 800 or as directed by the Engineer.
as directed by the Engineer.
Providing and fixing Aluminum backed flexible prismatic sheeting
, consisting of yellow/black colored flexible prismatic sheet with
Providing and fixing Aluminum backed flexible prismatic sheeting , consisting of non-mettalic prismatic lens as retro reflective elements and
yellow/black colored flexible prismatic sheet with non-mettalic prismatic lens as retro confirming to ASTM D4946 Type VI specifications for
reflective elements and confirming to ASTM D4946 Type VI specifications for reboundable retro reflective sheeting. The prismatic sheet shall be
reboundable retro reflective sheeting. The prismatic sheet shall be laminated at the back laminated at the back with 50micron aluminum Foil sensitive
8.30 with 50micron aluminum Foil sensitive adhesive and liner with screen printed sqm 8.30 adhesive and liner with screen printed arrow/slant pattern in sqm 23.00 5,377.000 1,23,671 5,500.00 1,26,500.00
arrow/slant pattern in yellow/black color. The AFP shall be applied with adhesive , the yellow/black color. The AFP shall be applied with adhesive , the
edge of the sheeting shall be sealed all around with epoxy based structural adhesive and edge of the sheeting shall be sealed all around with epoxy based
shall be extremely resistant to pill-off complete as per manufacturer drawings approved structural adhesive and shall be extremely resistant to pill-off
by the Engineer. complete as per manufacturer drawings approved by the
Engineer.

Providing and applying Geru paint of approved brand on Trees


Providing and applying Geru paint of approved brand on Trees withing ROW
withing ROW complete as per drawings and Technical
8.31 complete as per drawings and Technical Specification section 800 or as directed by the Nr 8.31 Nr 145.00 10.000 1,450 100.00 14,500.00
Specification section 800 or as directed by the Engineer
Engineer

Providing and Constructing Welcome Sign at Start and End of


Providing and Constructing Welcome Sign at Start and End of Project corridor
Project corridor complete as drawings and Technical
8.32 complete as drawings and Technical Specification 300, 800, 1500, 1600 and 1700 or Nr 8.32 Nr 2.00 36,000.000 72,000 25,000.00 50,000.00
Specification 300, 800, 1500, 1600 and 1700 or as directed by
as directed by the Engineer.
the Engineer.
8.33 Street Lighting in urban areas 8.33 Street Lighting in urban areas - -
xxix) Solar Street Light xxix) Solar Street Light - -
Supplying and erecting MNES certified SOLAR STREET
LIGHT fitting made from M.S. Body powder coated / painted
Supplying and erecting MNES certified SOLAR STREET LIGHT fitting made from with corrosion resistant paint with gasket & transparent cover
M.S. Body powder coated / painted with corrosion resistant paint with gasket & with following CFL non retro lamp with choke, holder &
transparent cover with following CFL non retro lamp with choke, holder & accessories. Fitting shall be mounted on 75/80 mm B class G.I.
accessories. Fitting shall be mounted on 75/80 mm B class G.I. pipe pole up to 5.5 mtr
a) a) pipe pole up to 5.5 mtr load complete erected with C.C. - -
load complete erected with C.C. Foundation duly painted with two coats of red oxide Foundation duly painted with two coats of red oxide and
and corrosive resistant paint. Complete with tubular battery, inverter, charge controller corrosive resistant paint. Complete with tubular battery, inverter,
with photo sensor switch & necessary wiring complete erected connected & charge controller with photo sensor switch & necessary wiring
commissioned in approved manner. complete erected connected & commissioned in approved
manner.

b) 2 x 11 W CFL (Single luminaire with 2 CFL) PV Module:120 W Battery Capacity b) 2 x 11 W CFL (Single luminaire with 2 CFL) PV Module:120
Each Ea. 882.00 33,000.000 2,91,06,000 16,000.00 1,41,12,000.00
12V, 100 AH W Battery Capacity 12V, 100 AH
Supplying & erecting Solar Home light system with structure as
Supplying & erecting Solar Home light system with structure as per MNES per MNES specification consisting of following non retrofit CFL
specification consisting of following non retrofit CFL fitting complete with following fitting complete with following CFL lamps & battery capacity
b) b) dully connected with built in inverter & commissioned as per - -
CFL lamps & battery capacity dully connected with built in inverter & commissioned
as per directed with necessary wiring & fittings. directed with necessary wiring & fittings.

(b) Two No CFL 11 watt non retrofit ceiling / wall mounting features with battery (b) Two No CFL 11 watt non retrofit ceiling / wall mounting
Each Ea. 882.00 12,300.000 1,08,48,600 12,000.00 1,05,84,000.00
capacity 12 watt, 40 AH features with battery capacity 12 watt, 40 AH
Total Traffic Signage and Road Appurtenances carried to
Total Traffic Signage and Road Appurtenances carried to Grand Summary 11,71,24,512 8,12,87,200.00
Grand Summary
9 SAFETY IN ROAD CONSTRUCTION ZONE 9 SAFETY IN ROAD CONSTRUCTION ZONE - -
Supplying and fixing sign boards including the cost of posts,
Supplying and fixing sign boards including the cost of posts, fixtures, foundation, fixtures, foundation, fitting and fixing. Sheeting will be made of
fitting and fixing. Sheeting will be made of encapsulated lens type of Retro-reflective encapsulated lens type of Retro-reflective type and messages/
9.01 9.01 borders will be screen printed complete as per Technical - -
type and messages/ borders will be screen printed complete as per Technical
Specification clause 801 and as directed by Engineer. Specification clause 801 and as directed by Engineer.

a) Speed Limit sign (600mm dia) Nr a) Speed Limit sign (600mm dia) Nr 22.00 3,938.613 86,649 3,500.00 77,000.00
b) Overtaking Prohibited (900 mm dia) Nr b) Overtaking Prohibited (900 mm dia) Nr 22.00 5,988.420 1,31,745 3,500.00 77,000.00
c) Diversion Board (450mm x 600mm) Nr c) Diversion Board (450mm x 600mm) Nr 66.00 3,894.305 2,57,024 4,500.00 2,97,000.00
d) Men at Work Sign (900mm triangular) Nr d) Men at Work Sign (900mm triangular) Nr 44.00 4,228.183 1,86,040 3,500.00 1,54,000.00
e) Direction Sign (Right / Left) (600 mm Circular) Nr e) Direction Sign (Right / Left) (600 mm Circular) Nr 22.00 3,938.613 86,649 3,500.00 77,000.00
Providing of red fluorescent with white reflective sleeve traffic
cone made of low density polyethylene(LDPE) material
Providing of red fluorescent with white reflective sleeve traffic cone made of low with a square base of 390x390x35mm and a height of
density polyethylene(LDPE) material with a square base of 770mm, 4Kg in weight, placed at 1.5m interval, all as per BS 873
9.02 390x390x35mm and a height of 770mm, 4Kg in weight, placed at 1.5m interval, all as Nr 9.02 including cost of all materials, labour, loading, unloading, lead, Nr 3,256.00 238.000 7,74,928 400.00 13,02,400.00
per BS 873 including cost of all materials, labour, loading, unloading, lead, lift, lift, transporting etc complete Technical Specification section
transporting etc complete Technical Specification section & IRC SP 55-2001. & IRC SP 55-2001.

Installation of a steel portable barricade with horizontal rail


300mm wide,2.5m in length fitted on a frame made with
Installation of a steel portable barricade with horizontal rail 300mm wide,2.5m in 45X45X5 mm angle iron section, 1.5m in height, horizontal rail
length fitted on a frame made with 45X45X5 mm angle iron section, 1.5m in height, painted(2coat) with yellow and white strips,150mm in width at
horizontal rail painted(2coat) with yellow and white strips,150mm in width at angle of angle of 45degree, A frame painted with 2 coats of yellow paint,
9.03 Nr 9.03 Nr 3,256.00 2,562.000 83,41,872 700.00 22,79,200.00
45degree, A frame painted with 2 coats of yellow paint, complete as per IRC:SP:55- complete as per IRC:SP:55-2001 including cost of all materials,
2001 including cost of all materials, labour, loading, unloading, lead, lift, transporting labour, loading, unloading, lead, lift, transporting etc complete as
etc complete as per drawings or as directed by the Engineer. per drawings or as directed by the Engineer.
Construction of a permanent type barricade made of steel
Construction of a permanent type barricade made of steel components, 1.5 m high components, 1.5 m high from road level, fitted with 3 horizontal
from road level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron
9.04 Nr. 9.04 vertical support, painted with yellow and white strips, 150 mm Nr. 20.00 4,123.000 82,460 5,000.00 1,00,000.00
5 mm angle iron vertical support, painted with yellow and white strips, 150 mm in
width at an angle of450, complete as per IRC:SP:55-2001 in width at an angle of450, complete as per IRC:SP:55-2001

9.08 Solar Street Light 9.04 Solar Street Light - -


Supplying and erecting MNES certified SOLAR STREET
LIGHT fitting made from M.S. Body powder coated / painted
Supplying and erecting MNES certified SOLAR STREET LIGHT fitting made from with corrosion resistant paint with gasket & transparent cover
M.S. Body powder coated / painted with corrosion resistant paint with gasket & with following CFL non retro lamp with choke, holder &
transparent cover with following CFL non retro lamp with choke, holder & accessories. Fitting shall be mounted on 75/80 mm B class G.I.
accessories. Fitting shall be mounted on 75/80 mm B class G.I. pipe pole up to 5.5 mtr pipe pole up to 5.5 mtr load complete erected with C.C.
i) i) - -
load complete erected with C.C. Foundation duly painted with two coats of red oxide Foundation duly painted with two coats of red oxide and
and corrosive resistant paint. Complete with tubular battery, inverter, charge controller corrosive resistant paint. Complete with tubular battery, inverter,
with photo sensor switch & necessary wiring complete erected connected & charge controller with photo sensor switch & necessary wiring
commissioned in approved manner. complete erected connected & commissioned in approved
manner.
a) 1 x 11 w CFL PV Module : 74 W Battery Capacity : 12V, 75
a) 1 x 11 w CFL PV Module : 74 W Battery Capacity : 12V, 75 AH Each Ea. 88.00 24,000.000 21,12,000 16,000.00 14,08,000.00
AH
Supplying & erecting Solar Home light system with structure as
Supplying & erecting Solar Home light system with structure as per MNES per MNES specification consisting of following non retrofit CFL
specification consisting of following non retrofit CFL fitting complete with following fitting complete with following CFL lamps & battery capacity
ii) ii) dully connected with built in inverter & commissioned as per - -
CFL lamps & battery capacity dully connected with built in inverter & commissioned
as per directed with necessary wiring & fittings. directed with necessary wiring & fittings.

(a) One No CFL 11 watt non retrofit ceiling / wall mounting features with battery (a) One No CFL 11 watt non retrofit ceiling / wall mounting
Each Ea. 88.00 6,900.000 6,07,200 12,000.00 10,56,000.00
capacity 12 watt, 20 AH features with battery capacity 12 watt, 20 AH
Total of Safety in Road Construction Zone carried to Grand
Total of Safety in Road Construction Zone carried to Grand Summary 1,26,66,568 68,27,600.00
Summary
Implementation of Environmental Management Action Plan
Implementation of Environmental Management Plan to be executed under Civil
10 10 to be executed under Civil Works Contract - -
Works Contract
Periodic air quality monitoring during construction stage at
construction camp sites, bitumen hot mix plants, crusher plants (if
Periodic air quality monitoring during construction stage at construction camp sites, specifically established for Project), at major settlement areas
bitumen hot mix plants, crusher plants (if specifically established for Project), at major along project road. The parameters to be monitored are SPM,
settlement areas along project road. The parameters to be monitored are SPM, RPM, RPM, SO2, NOx and CO, Lead. Each monitoring schedule
10.03 10.03 - -
SO2, NOx and CO, Lead. Each monitoring schedule shall be over a duration of 24 shall be over a duration of 24 hours (in 8 hour shifts) for three
hours (in 8 hour shifts) for three seasons per year. (as per the Environmental seasons per year. (as per the Environmental monitoring plan
monitoring plan refered in the EMP) refered in the EMP)

a) Construction Phase Nr a) Construction Phase Nr 36.00 7,500.000 2,70,000 9,000.00 3,24,000.00


b) Operation Phase Nr b) Operation Phase Nr 18.00 7,500.000 1,35,000 7,000.00 1,26,000.00
Water quality monitoring during construction phase at locations .
Water quality monitoring during construction phase at locations . The sampling shall be The sampling shall be carried out for three seasons per year and
carried out for three seasons per year and cover all parameters as per IS10500 cover all parameters as per IS10500 including heavy metals . (as
10.04 10.04 - -
including heavy metals . (as per the Environmental monitoring plan refered in the per the Environmental monitoring plan refered in the EMP).
EMP).

a) Construction Phase Nr a) Construction Phase Nr 36.00 6,000.000 2,16,000 7,000.00 2,52,000.00


Noise quality monitoring at specified silent receptors along
Project Road, at construction camp sites, bitumen hot mix plants,
Noise quality monitoring at specified silent receptors along Project Road, at crusher plants(if specifically established for Project), and at major
construction camp sites, bitumen hot mix plants, crusher plants(if specifically settlement areas along project road. – Each monitoring schedule
established for Project), and at major settlement areas along project road. – Each shall be over a duration of 12hours (6Am to 6PM) for three
10.05 10.05 - -
monitoring schedule shall be over a duration of 12hours (6Am to 6PM) for three seasons per year. (as per the Environmental monitoring plan
seasons per year. (as per the Environmental monitoring plan refered in the EMP)The refered in the EMP)The monitoring shall be carried out in
monitoring shall be carried out in accordance with CPCB norms at locations given . accordance with CPCB norms at locations given .

a) Construction Phase Nr a) Construction Phase Nr 42.00 3,000.000 1,26,000 3,000.00 1,26,000.00


b) Operation Phase Nr b) Operation Phase Nr 18.00 3,000.000 54,000 3,000.00 54,000.00
Soil quality monitoring at construction camp sites, work shop
Soil quality monitoring at construction camp sites, work shop areas, oil/lubricant areas, oil/lubricant handling areas, bitumen hot mix plants, at all
handling areas, bitumen hot mix plants, at all parking lay byes, vehicle servicing parking lay byes, vehicle servicing stations along Project Road.
10.06 stations along Project Road. Parameters shall include N, P, oil and grease, heavy 10.06 Parameters shall include N, P, oil and grease, heavy metals, C/N - -
metals, C/N ratio, pH, organic matter to be monitored for three seasons per year.(as ratio, pH, organic matter to be monitored for three seasons per
per the Environmental monitoring plan refered in the EMP) year.(as per the Environmental monitoring plan refered in the
EMP)
a) Construction Phase Nr a) Construction Phase Nr 6.00 6,000.000 36,000 8,000.00 48,000.00
10.12 Enhancement of Cultural Properties 10.12 Enhancement of Cultural Properties (bill no 10.18) - -
a) Vatda Primary School (47+900) Nr. a) Hanuman Temple (32+800) Nr. 1.00 41,012.000 41,012 50,000.00 50,000.00
HIV prevention / alleviation programme comprissing of conduction of Information, HIV prevention / alleviation programme comprissing of
Education and Comunication (IEC) campaigns at least every other month, providing conduction information, Education and comunication (IEC)
condoms, providing STI and HIV / AIDS screening, diagnosis and referal to dedicated campaigns at least every other month, providing condoms,
national STI and HIV / AIDS programme and programme management support providing STI and HIV / AIDS screening, diagnosis and referal to
10.13 throughout the contract period ( including the defect liability period). 10.13 dedicated national STI and HIV / AIDS programme and - -
programme management support throughout the contract period (
including the defect notification period).

a) IEC materias - Printing, Publishing Nr. a) IEC materials - printing, publishing Nr 24.00 3,000.000 72,000 5,000.00 1,20,000.00
b) Healthcare clinic Nr. b) Healthcare clinic Nr. 8.00 30,000.000 2,40,000 10,000.00 80,000.00
c) Condom vending machines Nr. c) Condom vending machines Nr. 3.00 15,000.000 45,000 5,000.00 15,000.00
d) Condom supplies Nr. d) Condom supplies Nr. 24.00 5,000.000 1,20,000 10,000.00 2,40,000.00
e) Testing Nr. e) Testing Nr. 500.00 1,500.000 7,50,000 1,000.00 5,00,000.00
f) Signage and hoardings Nr. f) Signages and hoardings Nr. 15.00 15,000.000 2,25,000 10,000.00 1,50,000.00
Total Implementation of Environmental Management Action
Total Implementation of Environmental Management Action Plan to be
Plan to be executed under Civil Works Contract carried to 23,30,012 20,85,000.00
executed under Civil Works Contract carried to Grand Summary
Grand Summary
11 DAY WORKS 11 DAY WORKS - -
As per Providing labour at site supplied with all necessary hand tools
Providing labour at site supplied with all necessary hand tools inclusive of all costs, details in inclusive of all costs, overheads and profit margin complete as As per details in
11.01 11.01 1.00 2,57,810.000 2,57,810 7,02,000.00 7,02,000.00
overheads and profit margin complete as directed by the Engineer Schedule directed by the Engineer Schedule “A”
“A”
As per Providing equipment at site with operators, P.O.L. etc. complete
Providing equipment at site with operators, P.O.L. etc. complete in good working details in in good working condition including all types of maintenance As per details in
11.02 11.02 1.00 1,69,241.000 1,69,241 8,45,500.00 8,45,500.00
condition including all types of maintenance during contract period Schedule during contract period Schedule “B”
“B”
As per Providing material at site inclusive of all costs, overheads and
Providing material at site inclusive of all costs, overheads and profit margin complete as details in profit margin complete as directed by the Engineer As per details in
11.03 11.03 1.00 5,35,862.500 5,35,863 1,41,062.50 1,41,062.50
directed by the Engineer Schedule Schedule “C”
“C”
Total Day work rates carried to Grand Summary Total Day work rates carried to Grand Summary 9,62,914 16,88,562.50
12 MAINTENANCE 12 MAINTAINANCE - -
Maintainance of project road for first year of maintainance period
Maintenance of project road for first year of maintainance period after Defect Liability
12.01 per km 12.01 after construction as directed by the Engineers per km 44.00 1,80,000.000 79,20,000 5,000.00 2,20,000.00
Period as directed by the Engineers

Maintainance of project road for 2nd year of maintainance period


Maintenance of project road for 2nd year of maintainance period after Defect Liability
12.02 per km 12.02 after construction as directed by the Engineers per km 44.00 2,20,000.000 96,80,000 10,000.00 4,40,000.00
Period as directed by the Engineers

Total for mainatenance cost Total for mainatainance cost 1,76,00,000 6,60,000.00

GRAND TOTAL Rs Grand total 61,51,11,070.26 48,86,57,158.50

Rebate:- 3.60%
Rebate Amount:- 1,75,91,657.71
Net Amount:- 47,10,65,500.79

You might also like