RCA

Original Revised Responsibility


Milestone Completion of structure, checker plate & handrail erection at 6.8 Mtr of GCP
10/05/23 31/05/23 Sanjoy Gon

Impact on Maintenance & Measure of Dry GCP vessels

Reason for • Front was not available due to Assembly of main charging conveyor and entire Road was blocked by Crane between stove str & Dust catcher
failure • Delay in material shifting from south yard

Why • Assembly of main charging conveyor was priority

Why • Release of 1200T crane

Why

Responsibility
Root Cause Erection front was not available towards stove side
Sanjoy Gon

Sl.No Action Plan Date Responsibility

1 Remaining checker plate, handrail to be shifted from south-yard 20/05/20 Sanjoy Gon

2 Erection of checker plate & handrail to be done 30/05/20 Sanjoy Gon