You are on page 1of 2

E&P Divn. TSK Ph.

II Blast Furnace Project (Overall)


Project Planning Gp.
Daily Progress Report
I. KEY WORK ITEMS PROGRESS Traffic Signal: Compliance: >80% - n Green; 60% -79% - n Yellow; <60% - n Red Data Date: 14/05/23

Report Week (12/05/23 to


Status as on data date May'23 14-May-23
18/05/23)
Asking Rate/ Asking rate Next day
Sl. Work Item UoM Scope
Month1 Compliance2 plan
Balance
Sch. (Baseline) Actual Month Plan MTD Plan MTD Actual MTD Compl. Plan Actual Plan Actual
(Scope.-Act)

Overall (Blast Furnace)


1 Civil - Concreting CuM 88,315 88,315 75,018 13,296 6,648 27% 2,578 715 852 119% 421 142 12 142 148
3 Structural erection MT 36,785 36,214 21,149 15,636 2,606 42% 2,783 1,247 515 41% 634 153 88 134 89
4 Tech. Structure erection MT 16,230 16,091 7,733 8,497 1,416 31% 1,436 657 204 31% 321 72 45 35 45
5 Equipment erection MT 21,287 20,840 5,551 15,736 2,623 52% 2,051 876 637 73% 429 220 55 66 72
6 Piping erection IM 779,700 779,700 68,821 710,879 118,480 14% 42,373 19,136 7,507 39% 9,568 664 1,367 - 1,367
7 Piping welding ID 258,834 258,834 36,916 221,918 36,986 21% 15,125 6,831 3,578 52% 3,415 320 488 - 488
8 Refractory MT 47,386 47,386 797 46,589 7,765 4% 1,163 525 139 26% 263 23 38 13 38
9 Sheeting Sqm 55,245 55,245 1,578 53,667 7,667 33% 2,500 1,129 1,178 104% 565 166 81 - 81
10 Cable tray erection Km 130 130 - 130 22 0% 3 1 - 0% 1 - 0 - 0
11 Cable laying Km 1,450 1,450 - 1,450 242 0% - - - - - - - - -
12 Panel erection Nos. 5,233 5,233 - 5,233 872 0% 80 36 - 0% 18 - 3 - 3
13 Transformer Nos. 23 23 - 23 4 0% - - - - - - - - -
DU-1 (BF Proper, Cast house, SGP, Main ECR)
1 Civil - Concreting CuM 34,004 34,004 27,851 6,152 6,152 10% 1,029 257 289 113% 147 63 - 63 16
3 Structural erection MT 14,183 14,166 10,899 3,284 547 48% 730 320 122 38% 170 20 23 - 23
4 Tech. Structure erection MT 4,615 4,703 2,502 2,113 352 11% 298 135 19 14% 67 14 10 - 10
5 Equipment erection MT 11,413 11,002 3,579 7,834 1,306 64% 1,197 542 391 72% 275 160 38 21 40
6 Piping erection IM 211,634 211,634 57,947 153,687 25,614 28% 12,253 5,534 3,357 61% 2,767 664 395 - 395
7 Piping welding ID 69,478 69,478 32,673 36,805 6,134 56% 6,500 2,935 1,599 54% 1,468 320 210 - 210
8 Refractory MT 18,283 18,283 - 18,283 3,047 0% - - - - - - - - -
9 Sheeting Sqm 28,454 28,454 1,578 26,876 3,839 66% 2,500 1,129 1,178 104% 565 166 81 - 81
10 Cable tray erection Km 56 56 - 56 9 0% 3 1 - 0% 1 - 0 - 0
11 Cable laying Km 515 515 - 515 86 0% - - - - - - - - -
12 Panel erection Nos. 2,795 2,795 - 2,795 466 0% 80 36 - 0% 18 - 3 - 3
13 Transformer Nos. 7 7 - 7 1 0% - - - - - - - - -
DU-2 (Stove, GCP, Pump house, TRT)
1 Civil - Concreting CuM 15,957 15,957 15,943 14 14 6476% 794 299 423 142% 194 29 4 29 120
3 Structural erection MT 12,846 12,846 6,504 6,342 1,057 63% 1,008 456 312 68% 227 122 32 122 32
4 Tech. Structure erection MT 8,791 8,134 4,978 3,813 635 60% 911 411 178 43% 206 58 29 35 29
5 Equipment erection MT 6,118 5,119 782 5,336 889 4% 96 43 17 40% 22 9 3 - 3
6 Piping erection IM 444,800 444,800 8,696 436,104 72,684 11% 26,000 11,742 3,840 33% 5,871 - 839 - 839
7 Piping welding ID 148,267 148,267 - 148,267 24,711 0% 5,800 2,619 - 0% 1,310 - 187 - 187
8 Refrectory MT 29,103 29,103 797 28,306 4,718 6% 1,163 525 139 26% 263 23 38 13 38
9 Sheeting Sqm - 0 - - - - - - - - - - - - -
10 Cable tray erection Km 34 34 - 34 6 0% - - - - - - - - -
11 Cable laying Km 607 607 - 607 101 0% - - - - - - - - -
12 Panel erection Nos. 1,897 1,897 - 1,897 316 0% - - - - - - - - -
13 Transformer Nos. 5 5 - 5 1 0% - - - - - - - - -
DU-3 (Stock House, PCI, Blower)
1 Civil - Concreting CuM 38,354 38,354 31,224 7,130 7,130 4% 755 160 140 87% 80 50 8 50 12
3 Structural erection MT 9,756 9,630 3,746 6,010 1,002 17% 1,045 472 81 17% 236 12 34 12 34
4 Tech. Structure erection MT 2,824 3,254 253 2,571 429 4% 228 112 8 7% 48 - 6 - 6
5 Equipment erection MT 3,756 4,719 1,190 2,566 428 115% 758 291 229 79% 133 51 14 45 28
6 Piping erection IM 123,266 123,266 2,178 121,088 20,181 3% 4,120 1,861 310 17% 930 - 133 - 133
7 Piping welding ID 41,089 41,089 4,243 36,846 6,141 69% 2,825 1,276 1,979 155% 638 - 91 - 91
8 Refrectory MT 0 0 - 0 - - - - - - - - - - -
9 Sheeting Sqm 26,791 26,791 - 26,791 3,827 0% - - - - - - - - -
10 Cable tray erection Km 40 40 - 40 7 0% - - - - - - - - -
11 Cable laying Km 328 328 - 328 55 0% - - - - - - - - -
12 Panel erection Nos. 541 541 - 541 90 0% - - - - - - - - -
13 Transformer Nos. 11 11 - 11 2 0% - - - - - - - - -
1
Asking Rate = Balane scope/ Balance duration; ; 2 Asking Rate Complaince = MTD Actual/ MTD asking Rate
3
Sch. Compln = As per last commitment of Dec'23 Blow-in, 4&5 Estimated Compln = Based on last 3 month construction plan/ Actual
Note: Civil concreting quantities have been reconciled. As on 31/03/23, it was reported as 80,280 Cum Completed against scope of 87915 Cum. This higher quantity contains extra PCC pourings (Aprox. 10,000 Cum) done as per site conditions. As on
01/04/23, 70,194 Cum was achieved.

Manpower Available (Nos.)


Total Manpower
2920
2876

2836
2822

2806

2739

2729
2710
2632

2625
2613

3200
2800
1991

2400
1494

2000
1600
953

1200
800
400
10

0
7-May

8-May

9-May
1-May

2-May

3-May

4-May

5-May

6-May

10-May

11-May

12-May

13-May

Sun 14-May

15-May

16-May

17-May

18-May

19-May

20-May

Sun 21-May

22-May

23-May

24-May

25-May

26-May

27-May

Sun 28-May

29-May

30-May

31-May
Sun
TSK Ph.II Blast Furnace Project
Major Milestones for the month
n Completed, n in Progress, n Delayed & not started

Actual/ Revised
Sl. Zone Area Discipline Major Milestone description Plan date Responsibility
date

1 DU-1 BF Proper Structural Erection of Outrigger crane girder structure 04/05/23 n 04/05/23 Awdhesh Ku singh
2 DU-2 Pump house Structural Erection of Pipe rack structure from Pump house to Cast house (Grid 1 to 13) 04/05/23 n 15/05/23 Digamber Behera
3 DU-2 GCP Tech structure Start of Assembly of cylindrical part of hopper 04/05/23 n 02/05/23 Sanjay Gon
4 DU-1 BF Proper Equipment Valve casing box erection in BLT area 05/05/23 n 20/05/23 Sumit Bhar
5 DU-1 Cast house Civil Completion of Side wall in Cast house ramp (grid 8-13) 05/05/23 n 05/05/23 Rahul biswas
6 DU-3 Blower Civil Concreting of 8.2m slab in blower 05/05/23 n 05/05/23 Santosh Arya
7 DU-3 Blower Equipment Completion of Padding work of Blower 4 & 5 07/05/23 n 08/05/23 Virendra Katre
8 DU-3 Stock House Equipment Erection of SH Desystem -2 hopper & casing 07/05/23 n 07/05/23 A K Mohanty
9 DU-1 Cast house Structural Structural Front handover for BLT gear box erection 08/05/23 n 17/05/23 Saurabh
10 DU-2 Drive house Structural Erection of MCC trestle Z2 10/05/23 n 08/05/23 B K Rout
11 DU-1 Cast house Equipment Erection of Cast house DE System Chimney 10/05/23 n 18/05/23 Sumit Bhar
12 DU-1 BF Proper Refractory Ordering of water pumps for topcone & offtake refractory 10/05/23 n 20/05/23 Subhas Paul
13 DU-3 Stock House Equipment Erection of Vibrating screen in stock house- 1 set 10/05/23 n 04/05/23 Virendra Katre
14 DU-2 GCP Structural Completion of structure, checker plate & handrail erection at 6 Mtr of GCP 10/05/23 n 31/05/23 Sanjay Gon
15 DU-3 Stock House Structural Assembly of 3 Nos conveyor gallery in Stock house feed area 10/05/23 n 22/05/23 Babu Ranjit Singh
16 DU-3 PCI Structural Handover of 5m floor in PCI 10/05/23 n 21/05/23 Virendra Katre
17 DU-2 GCP Tech structure Spray tower shell erection (1 Segment) 12/05/23 n 19/05/23 Anup Viswakarma
18 DU-1 BF Proper Equipment Erection of BLT Hydraulic power pack at 48 Mtr hudraulic room 12/05/23 n 25/05/23 Sumit Bhar
19 DU-1 Cast house Structural Cast house 180 degree front handover for EOT erection 12/05/23 n 12/05/23 Awdhesh Ku singh
20 DU-1 Cast house Structural Delivery of cast house roof Monitors 14/05/23 n 24/05/23 Awdhesh Ku singh
21 DU-1 Cast house Equipment Erection of Cast house machines ( 1 set Mudgun) 14/05/23 n 27/05/23 Sumit Bhar
22 DU-3 Blower Structural Blower structure erection in C-C' row Panel-1 &2 14/05/23 n 21/05/23 S R Bal
23 DU-1 SGP Civil Internal road & drain work in C2 SGP area- 130 Mtr 15/05/23 n 25/05/23 Rahul biswas
24 DU-1 Main ECR HVAC Start of HVAC Duct work in Main ECR 15/05/23 n Subhas Paul
25 DU-1 Cast house Equipment Erection of Cast house DE System ID fan 15/05/23 n 26/05/23 Sumit Bhar
26 DU-1 BF Proper Equipment Completion of grid fixing for Carbon block laying 15/05/23 n 27/05/23 Sumit Bhar
27 DU-2 Stove Refractory Complete Delivery of Stove refractory 15/05/23 Sumit Sarkar
28 DU-2 Stove Refractory Completion of side wall gunning in stove 1 &2 15/05/23 n 31/05/23 D C Nandi
29 DU-2 Stove Structural Erection of 4 Nos structure modules in stove structure (31 Mtr to 54 Mtr) 15/05/23 Bikash mahto
30 DU-2 Stove Refractory Delivery of Stove chimney refractory 15/05/23 Sumit Sarkar
31 DU-3 Stock House Structural Assembly of SH feed area 48 Mtr gallery ( 48m SH proper to TT-01) 15/05/23 Babu Ranjit Singh
32 DU-2 Pump house Civil Completion of concreting in Pumphouse slab 15/05/23 n 05/05/23 Rahul biswas
33 DU-3 Blower Civil Foundation of cable gable gallary(7/9) 15/05/23 n 18/05/23 Santosh Arya
34 DU-1 Cast house Equipment Erection of Cast house DE System hoppers (20 Nos) 16/05/23 Sumit Bhar
35 DU-2 Pump house Civil Internal road & drain work in south side of pump house (from Gate-2 to Stock house)- 550 Mtr 18/05/23 Rahul biswas
36 DU-1 Cast house Equipment Erection of Cast house hydraulic tank in 0 ° side hydraulic room 20/05/23 Sumit Bhar
37 DU-3 Stock House Civil Completion of SH ECR floor slab 25/05/23 Santosh Arya
38 DU-2 Pump house Equipment Erection of 15 Sets Evaporative coolers 25/05/23 Digamber Behera
39 DU-3 PCI Structural Structure erection upto 23 Mtr level 25/05/23 Virendra Katre
40 DU-3 Blower Civil Completion of cable trench infront of blower house 28/05/23 Santosh Arya
41 DU-2 Stove Structure 25m floor Completion along with checker support 28/05/23 Bikas
42 DU-3 PCI Tech structure Erection of fine coal silo in PCI 28/05/23 Virendra Katre
43 DU-2 Stove Structure Completion of all modules & Panel Erection in stove structure 29/05/23 Bikas
44 DU-3 Blower Electrical Erection of Blower transformer #4 29/05/23 Prabir Dey
45 DU-3 Blower Civil completion of flooring in ground floor 30/05/23 Santosh Arya
46 DU-3 Stock House Equipment Bagfilter cage erection in Stock house DE System -1 30/05/23 A K Mohanty
47 DU-3 Blower Tech structure Completion of Cold blast duct inside existing pipe rack 30/05/23 Virendra Katre
48 DU-1 Cast house Structural Roof completion of cast house@270 degree 30/05/23 Awdhesh Ku singh
49 DU-1 Cast house Structural Heat insulation of cast house platform 30/05/23 Awdhesh Ku singh
50 DU-1 SGP Structural C1 & C2 granulation tank platform 30/05/23 Awdhesh Ku singh
51 DU-1 BF Proper Refractory Availability of injection mortar for start of bottom injection 31/05/23 Sumit Sarkar
52 DU-2 GCP Structural Erection of Cable rack structure (16 Nos) near TRT area 31/05/23 Digamber Behera
53 DU-2 GCP Tech structure Erection of Cylindrical part of hopper in Dry GCP 31/05/23 Sanjay Gon
54 DU-1 Cast house Sheeting Completion of roof sheeting in cast house-1 31/05/23 Awdhesh Ku singh
55 DU-1 Cast house Structural Mudgun & drill machine column structural erectionfor Taphole 3 & 4 31/05/23 Awdhesh Ku singh
56 DU-1 BF Proper Structural Completion of Bustle pipe platform (last floor EL.25m) 31/05/23 Awdhesh Ku singh
57 DU-1 BF Proper Structural Assembly of Elevator shaft & cable well 31/05/23 Awdhesh Ku singh