HVAC Duct Work Zone Wise Installation Progress 6/8/2023

Executed Quantity (as Zone-01 Zone-02 Zone-03


Item Description BOQ Quantity Progress (%) Progress (%)
Sr No per Site)
Commulative Remaining Completion Commulative Remaining Completion Commulative Remaining Target Completion
Total (Sft) Target Date Total (Sft) Target Date Total (Sft)
(Sft) (Sft) Date (Sft) (Sft) Date (Sft) (Sft) Date Date
1 US Guage 26 GI Duckt 31960 13 847 0 1264 677 587 10/8/2023
2 US Guage 24 GI Duckt 128310 53 47029 19 931 485 446 10/8/2023
3 US Guage 22 GI Duckt 64077 26 40985 17
4 US Guage 20 GI Duckt 17978 7 5185 2
Total: 242325 100 94046 39 2195 1162 1033

Zone Wise Installation Progress 7/8/2023


Zone-01 Zone-02 Zone-03
Commulative Remaining Completion Commulative Remaining Completion Commulative Remaining Target Completion
Total (Sft) Target Date Total (Sft) Target Date Total (Sft)
(Sft) (Sft) Date (Sft) (Sft) Date (Sft) (Sft) Date Date
1264 747 517 10/8/2023
931 565 366 10/8/2023

2195 1312 883

Zone Wise Installation Progress 8/8/2023


Zone-01 Zone-02 Zone-03
Commulative Remaining Completion Commulative Remaining Completion Commulative Remaining Target Completion
Total (Sft) Target Date Total (Sft) Target Date Total (Sft)
(Sft) (Sft) Date (Sft) (Sft) Date (Sft) (Sft) Date Date
1264 867 397 10/8/2023
931 715 216 10/8/2023

2195 1582 613

Zone Wise Installation Progress 9/8/2023


Zone-01 Zone-02 Zone-03
Commulative Remaining Completion Commulative Remaining Completion Commulative Remaining Target Completion
Total (Sft) Target Date Total (Sft) Target Date Total (Sft)
(Sft) (Sft) Date (Sft) (Sft) Date (Sft) (Sft) Date Date
1264 947 317 10/8/2023
931 825 106 10/8/2023

2195 1772 423