The document tracks the progress of HVAC duct work installation across three zones. As of September 8th, Zone 1 is 77% complete, Zone 2 is 88% complete, and Zone 3 is 81% complete. All zones are targeting a completion date of October 8th, 2023, though Zone 2 is nearly finished while Zones 1 and 3 still have work remaining. The installation has been steadily progressing over the reported months of June, July, August, and September according to the cumulative totals provided for each zone at each date.
The document tracks the progress of HVAC duct work installation across three zones. As of September 8th, Zone 1 is 77% complete, Zone 2 is 88% complete, and Zone 3 is 81% complete. All zones are targeting a completion date of October 8th, 2023, though Zone 2 is nearly finished while Zones 1 and 3 still have work remaining. The installation has been steadily progressing over the reported months of June, July, August, and September according to the cumulative totals provided for each zone at each date.
The document tracks the progress of HVAC duct work installation across three zones. As of September 8th, Zone 1 is 77% complete, Zone 2 is 88% complete, and Zone 3 is 81% complete. All zones are targeting a completion date of October 8th, 2023, though Zone 2 is nearly finished while Zones 1 and 3 still have work remaining. The installation has been steadily progressing over the reported months of June, July, August, and September according to the cumulative totals provided for each zone at each date.
HVAC Duct Work Zone Wise Installation Progress 6/8/2023
Executed Quantity (as Zone-01 Zone-02 Zone-03
Item Description BOQ Quantity Progress (%) Progress (%) Sr No per Site) Commulative Remaining Completion Commulative Remaining Completion Commulative Remaining Target Completion Total (Sft) Target Date Total (Sft) Target Date Total (Sft) (Sft) (Sft) Date (Sft) (Sft) Date (Sft) (Sft) Date Date 1 US Guage 26 GI Duckt 31960 13 847 0 1264 677 587 10/8/2023 2 US Guage 24 GI Duckt 128310 53 47029 19 931 485 446 10/8/2023 3 US Guage 22 GI Duckt 64077 26 40985 17 4 US Guage 20 GI Duckt 17978 7 5185 2 Total: 242325 100 94046 39 2195 1162 1033
Zone Wise Installation Progress 7/8/2023
Zone-01 Zone-02 Zone-03 Commulative Remaining Completion Commulative Remaining Completion Commulative Remaining Target Completion Total (Sft) Target Date Total (Sft) Target Date Total (Sft) (Sft) (Sft) Date (Sft) (Sft) Date (Sft) (Sft) Date Date 1264 747 517 10/8/2023 931 565 366 10/8/2023
2195 1312 883
Zone Wise Installation Progress 8/8/2023
Zone-01 Zone-02 Zone-03 Commulative Remaining Completion Commulative Remaining Completion Commulative Remaining Target Completion Total (Sft) Target Date Total (Sft) Target Date Total (Sft) (Sft) (Sft) Date (Sft) (Sft) Date (Sft) (Sft) Date Date 1264 867 397 10/8/2023 931 715 216 10/8/2023
2195 1582 613
Zone Wise Installation Progress 9/8/2023
Zone-01 Zone-02 Zone-03 Commulative Remaining Completion Commulative Remaining Completion Commulative Remaining Target Completion Total (Sft) Target Date Total (Sft) Target Date Total (Sft) (Sft) (Sft) Date (Sft) (Sft) Date (Sft) (Sft) Date Date 1264 947 317 10/8/2023 931 825 106 10/8/2023