Professional Documents
Culture Documents
2018 GoMaximo Slaying The Backlog Dragon
2018 GoMaximo Slaying The Backlog Dragon
J o h n Re e ve , A u t h o r, C R L , C M M S C h a m p i o n
Scott Stukel, CMRP
Director, Energy/Utilities & Asset Management
TRM - Total Resource Management
BSME, EE/CE Minors – Kettering University (formerly GMI)
28 Years of experience in Engineering, Maintenance and Asset
Management Practices & Technology
16 Years of Asset Management & EAM Consulting Experience
Seasoned Asset Management, ISO-55000, IIMM Practitioner
and Advisor
Former NASA Deep Space Sr. Engineer & Reliability/RCM
Director
Guinness World Record Holder, Engineered Worlds Largest
Rice Krispies Treat for Charity/Reality TV Program – 10,314 lbs
2
Asset Management RELIABILITY LEADERs
MX S/W CONSULTANTs
COST/SCHED. ANALYSTs
Before we start, I’ve got questions
5
Dif feren t T yp es of B a cklo g
Planning Backlog
Scheduling Backlog
Execution Backlog
6
Maintenance Backlog --- Measures the work necessary to prevent the
deterioration of an asset or its function that has not been carried out, but has been
identified to be done.
BACKLOG ACCURACY REVIEWS
When reviewing new work requests….a rigorous examination of the work requested needs to be
carried out. This will remove duplicate work, finished work, unwanted work and modifications
(modifications need to go through the 'management of change' process, modifications need
engineering and fiscal approval, a modification is not maintenance work) out of the list.
ACCEPTABLE BACKLOG SIZE
Author #1 About 2 to 3 weeks of backlog would be usual in an effective and well-regulated maintenance environment.
Author #2 Backlog forward resources (Crew weeks equivalent 4 - 5 weeks)
Author #3 A standard backlog of one week may not be a problem for your organization,….
Author #4 Any (work) backlog, other than deferred maintenance, would be bad.
Author #5 To target. Say, about 4 man weeks.
Author #6 Backlog weeks, which list all deferrable work not yet scheduled for completion. Goal: Four-six weeks.
Author #7 Non-outage CM work order count greater than >50 per facility/area (for sites with multiple areas)…would be
bad.
Whereas, elective maintenance work order count > 450 per facility, would be bad.
Author #8 There is no answer. Which is exact or correct for any industry.
Author #9 To help the planning process it is normal to run with approximately 2 man weeks of backlog per technician.
If you are constantly below that figure then you could be over-manned. If the Backlog climbs to 4 man weeks
then consider overtime working or bringing on additional resources.
Author #10 Jack R. Nicholas, Jr., P.E., CMRP stated that the acceptable range of man-weeks of backlog per technician is 3-
5 where 4 is ideal.
Categorizing the Backlog
Traditionally Backlog has been measured in effort , i.e. weeks, days, hours..
Modern backlog should be measured in effort as well as cost. This topic also
gets into defect and deferred maintenance tracking.
9
It is extremely important to Trend Backlog Growth
Ma int ena n ce Pla nnin g
”What do you mean I need to think ahead?
I just get the work order,…. go get stuff, and get er done”
17
This is one idea for work prioritization.
You may have a better one.
P la nn er/s ched ule r Ro le
Planner/Scheduler Activities
1. Screening – The Scheduler reviews the work plan and makes any
necessary modifications to priority, additional estimate details, and/or
designation if work will be performed by a specific crew, specialty, or
tradesperson.
2. Build the Schedule – Oversee Backlog & 4-Week schedule.
3. Track schedule adherence
4. Trend backlog growth [Planner & Scheduler role]
5. Coordinate with Operations & Facilitate the weekly scheduling meeting.
6. Support Supervisors/Leads with executing the schedule.
19
Doc Palmer Speaks out on Daily Plan Creation
Supervisors should be making a Daily Plan, each day, from the Weekly Schedule
Best practice is to have the crew supervisor create daily schedules as the week unfolds.
Reason: There is too much churn in the daily execution of maintenance to create the daily
schedules a week ahead of time. Therein, the first-line supervisors should create the daily
schedules, assign names, coordinate lockout/tagout (LOTO), and deal with new urgent work
that cannot wait.
Many/some scheduling practitioners and CMMS programs advocate laying out the entire next
week in advance, specifying specific days for each work order, as well as technicians and hour
slots assigned to them. Their reasoning seems to be that because each work order has a time
estimate, the schedule should dictate exactly when the work should be performed for best
coordination. [JR} just because the scheduling software permits this type of thing, doesn’t
mean you should do it.
Backlog
Management
Using a
Risk-based
Prioritization
Matrix
Prioritization Matrix – for ranking the open
backlog
Asset Criticality Ranking – example #1
Asset Criticality Ranking – example #2
Other considerations for Matrix
Benefits of Planning & Scheduling
32
Benefits of Planning & Scheduling
33
Path Forward
That all sounds great, but how do we get there?
Here’s How:
1. Understand where you are, where you want to go, and what benefits
you can expect to achieve.
2. Develop a workable implementation plan and get management
behind it.
3. Execute your plan.
4. Train and empower your people.
5. Measure progress and continuously improve.
34
What should my ratio of supervisor,
planner/scheduler, or maintenance engineer to
craftsperson be?
35
Measure your progress to continuously improve
36
Planning & Scheduling Metrics/KPIs
Key Performance Indicators – Work Planning
Name Description Definition Benchmark Current Value Targeted Goal/
Value (if available) Timeframe
Percentage of Planned What percentage of completed work Count of planned work orders > 85% Not available TBD
Maintenance orders were planned divided by count of all work orders
Planning Effectiveness Difference between planned work Total hours planned divided by +/- 10% Not available TBD
hours and actual hours spent to total maintenance hours
complete work
Ratio of Planned & Scheduled Ratio of Planned & Scheduled Total hours of planned & scheduled 85-95% Not Available TBD
Maintenance Maintenance to total hours worked work divided by total hours
PM Schedule Compliance* Ratio of PMs completed to PMs PM work Completed divided by PM > 95%, Not Available TBD
scheduled work scheduled Upward
trend
Scheduling Effectiveness Difference between weekly hours Actual work hours divided by +/- 10% Not Available TBD
scheduled for work and actual hours scheduled hours (weekly)
taken to complete work
* Schedule compliance metric needs to take into account minimum schedule or total availability to discourage schedule manipulation to boost compliance
numbers, initially the weekly schedule should leave 10-15% of available time free to handle emergencies or schedule injections
37
Shifting
focus to
Reliability
Something
to
Remember