Professional Documents
Culture Documents
ON
CC ROAD CONSTRUCTION
SUBMITTED TO - SUBMITTED BY -
Mrs.A. PUNYAVATHI
H.O.D
CIVIL ENGINEERING A.RAMYA
DEPARTMENT -18069-C-001
GOVT POLYTECHNIC WOMEN –
MEDAK
1
INTRODUCTION
Development of a country depends on the connectivity of various
places with adequate road network.
Roads constitute the most important mode of communication in
areas
where railways have not developed much.
India has one of the largest road networks in the world (over 3
million km at present).For the purpose of management and
administration, roads in India are divided into the following five
categories:
• National Highways (NH)
• State Highways (SH)
• Major District Roads (MDR)
• Other District Roads (ODR)
• Village Roads (VR)
2
TYPES OF PAVEMENTS
There are various types of pavements depending upon the materials used; a
briefs description of all types is given here-
FLEXIBLE PAVEMENTS
Bitumen has been widely used in the construction of flexible pavements for a long
time.
Have low flexural strength
Load is transferred by grain to grain contact
Have low completion cost but repairing cost is high
Have low life span (High Maintenance Cost)
RIGID PAVEMENT
Rigid pavements, though costly in initial investment, are cheap in long run
because of low maintenance costs.
Deformation in the sub grade is not transferred to subsequent layers. Have high
flexural strength.
No such phenomenon of grain to grain load transfer exists.
Life span is more as compare to flexible (Low Maintenance Cost).
3
Basic Components of a Concrete
Pavement
Surface smoothness Thickness Design
Longitudinal joint
Transverse joint
Surface Texture
Concrete materials
Dowel bars
Tiebars
Subgrade
Base
4
1. Preparation of base
2. Preparation of subgrade
3. Formwork
4. Watering of base
5. Material mix and placing
6. Compaction
7. Finishing of surface
8. Curing
9. Joint filing
10. Open to traffic
5
1. As base material of W.B.M. Road; stone ballast, concrete 10-
15cm layer are used. For bonding between concrete slab &
W.B.M. used 1:2 cement wash on W.B.M.
2. Concrete base
On the road used 10cm Cement concrete(1:2:4).
If base is dry
Than using the sprinkling process on it properly after that
placing the concrete.
7
5.MATERIAL MIXING AND PLACING
Mixer is equipment that mix the concrete using
distinct amount of cement , concrete, sand and water.
Concrete slab should have more than 5-10cm thick
cause of drying.
Used two type mixer-
1. Batch mixer-
at site, used for small road construction
2. Continuous mixer-
Continuous mixer used for large
construction . if distance is more from site ,
mix concrete
transported at site within setting time.
8
6.COMACATION
Purpose of compaction is that to pull out air from void
and make concrete harden.
7.Finishing of surface
1.Floating-
For levelling the surface use floating, scree-
ding , power trowel. So that there is no
acceptable more than 3mm variation in concrete
level surface. 9
8. Curing
Curing is the name of increasing the hydration
process of cement.
after setting the concrete , curing process
done till 14-28days.
9.Filling joint
After drying road, clean the joints and fill
the shelling compound or hot bitumen .
12
10
OPENTO TRAFFIC
• Generally after a month ,road should be
open to traffic.
• If used rapid hardening cement in take 7
days to traffic.
THANK
YOU.
14