Professional Documents
Culture Documents
Hydrology
by
Noor Farahain
Muhammad Amin
Chapter 4
Hydrograph Analysis
Total runoff Direct runoff
- Baseflow = hydrograph
hydrograph
Q Q Q
t t t
1cm RE
Q
Intensity = 1/D cm/h
t
tb
Effect of Storm
Duration
2-hr UH 6-hr UH 12-hr UH
Q Q Q
Unit RE
Unit RE Unit RE
A1 A2 A3
t t
t
1cm RE P cm RE
Q Q
t t
tb tb
1cm RE P cm RE
Q Q
t t
tb tb
x3.5
0 0 0
x3.5
3 25 87.5
x3.5
6 50 175 DRH
x3.5
9 85 297.
x3.5 5
12 125
437. UH
…
x3.5
5
60 8 0
x3.5
69 0 0
tb
Method of Superposition &
Lagging
D-hr UH DRH for 2D-hr rain of 1cm each
Q
2D hr
D hr
2cm RE
Q 1cm RE
t t
tb
tb
tb
Lag time
Hence, D-hr UH can be used to derive DRH for storms which has
a duration of nD, n=integer
Method of Superposition &
Lagging DRH for a complex storm event
D-hr UH
Q D D D
D Q cm R cm
1cm P cm
Q
t
tb
tb t
60
40
20
0
0.0 2.0 4.0 6.0 8.0 10.0
Derivation of UH
Requires at least five (5) QUALIFIED storm events
with the following characteristics:
• Storm must be isolated/ independent
• Storm must be uniform over entire duration
• Storm must be uniform over entire watershed
• Storm duration must be ±20%D (preferably less)
• Storm duration must be 1/5 to 1/3 of basin lag
•Storm magnitude must be significant, preferably
between 1 to 4cm
Derivation of UH
DRH for D-hr rain D-hr UH
D hr D hr
Q Q
P units RE
1 unit RE
V=PxA V=1xA
t t
tb tb
(Ord. DRH) / R = UH
Derivation of
UH • 5 UH from qualified storm events
• Qp are different
Q
• tpk are different
• tb are different
t
Average
UH • determine average Q , t
p pk and tb
Qp
Q
tb t
tpk
Limitations of UH
•Storm are rarely uniform over entire catchment,
hence, UH method is only applicable for
2km2<A<5000km2
•Large storage in catchment which will affect the
assumption of linear response is not considered.
•Precipitation must be rainfall only, snow fall
cannot be considered.
• Method invalid if the storm is nonuniform in
time.
R1U9+ R2U8
R1U1 R1U10+ R2U9
R2U10 t
D-hr
Convolution Computation
Tim Rainf UH Runoff due Runoff due Runoff due Total direct runoff
e all Un to 1st to 2nd to 4th Qi
(hr) excess
X-hr rain X-hr rain X-hr rain
Rm
0 - 0 0 0 0 0
X R1 U1 R1U1 0 0 R1U1
13X
R4U10 R4U10
14X 0 0
Deconvolution Computation
= R1 U 1
= R2U1 + R1U2
= R3U1 + R2U2 + R1U3
Q1 Q2 Q3
…
QM = RMU1
= 0 + 0 + … + RMUN-1 + RM-1UN
+ R U2 + … + + … + 0 + RMUN
= M-1
0 + 0
R1UM
Q = R x UQM+1 = 0
+ RMU2
Unit hydrograph+U…can
+ be solved using matrix method.
R2UM + R1UM+1
…
QN+M-2 QN+M-1
UH of different durations
• Method of Superposition
• S-hydrograph Method
Method of
Superposition DRH for 2D-hr rain
D-hr UH
Q
2D hr
D hr
Q 1cm RE 2cm RE
t t
tb
tb
tb
Lag time
Method of
Superposition
DRH for 2D-hr rain 2D-hr UH
Q Q
2D hr 2D hr
2cm RE
1cm RE
t t
tb tb + D
tb
Q Q
3D hr 3D hr
3cm RE
1cm RE
t t
tb tb + 2D
tb
tb
Q Q Q
A1 A2
A3
t t t
t
tb
S-hydrograph
Q T hr
Q
Storm (2)
Storm (1)
D hr
S-hydrograph(1)
Maximum
S-hydrograph(2)
S S
t t
tb
S-hydrograph
Q T hr
Intensity = 1/D cm/h
Storm (2)
Duration = T h
Depth = Intensity x Storm (1)
Duration
S-hydrograph(1)
= T/D cm
Q
S
S-hydrograph(2)
S
T/D cm S
S x D/T
1 cm
t
S-hydrograph
Intensity = 1/D cm/h
Duration = T h
Depth = Intensity x
Duration
= T/D cm
Q
T-hr UH
1 cm
Synthetic UH
A synthetic unit hydrograph is derived from
empirical equations of regional validity when
observed rainfall-runoff data are not available for
unit hydrograph derivation. Its uses are:
• to anticipate post-development conditions,
•to extend the usage of point–specific unit
hydrograph to other locations of similar
characteristics.
Synthetic UH
• Snyder’s method
• SCS method
Both to utilize existing UH from a neighbouring
meteorologically similar watershed.
Watershed A Watershed B
UH UH not available
available
Rainfall duration
?
Qp
t
t
Snyder’s Standard UH
tr = tp / 5.5
t
For any UH, tR = rainfall duration (h), tp’ = basin lag (h)
For standard UH
tp’ = tp
tR For non-standard UH
tr = tR
t p’ t p
tp’
Qp = t2.78
r tRCpA/ tp’
Qp
t
Snyder’s Method
Step 1: check whether source UH is standard
Step 2: determine regional constants of source UH
Step 3: check whether required UH is standard
Step 4: determine parameters of required UH
Step 5: determine time base of required UH
Step 6: finalising required UH using S-curve
method
Source UH Required UH
?
Qp
t t
Snyder’s Method
Step 1: check whether source UH is standard
Assume tr = tR
Source UH
tR tr = tp / 5.5 tp
I tp’ = tp standard
tp’
f
Qp
I tp’ tp non-standard
f
t
Snyder’s Method
Step 2: determine regional constants of source UH
tp = Ct ( L Lca )0.3 Ct
tp’
Qp
Qp = 2.78 CpA/ tp’ Cp
t
Snyder’s Method
Step 3: check whether required UH is standard
If tr t R non-standard
t
Snyder’s Method
Step 4: determine parameters of required UH
Qp
tpk = tR/2 + tp’
tpk t
Snyder’s Method
Step 4: determine parameters of required UH
W75
Qp W75 = W50 / 1.75
0.75Qp
0.5Qp
W50
t
Snyder’s Method
Qp
W75 /3
0.75Qp
2/3 W75
0.5Qp
W50 /3 2/3 W50
tpk t
Snyder’s Method
Step 5: determine time base of required UH
Qp
For small catchment:
tb = 5(tp’ +0.5tR) (h)
To the nearest larger integer divisible by tR
tb t
tb is always least accurate
Snyder’s Method
Step 6: Finalising UH using S-curve method
• Plot Q vs t
10
9
8
Example: 7
6
tpk = 20h 5
Qp = 10m3/s 4
3
2
1
0
0 20 40 60 80 100 120