• In the event, tank cleaning date coincides with the date for carrying out
microbiological test or if the tank is being taken up for cleaning during
which period the microbiological test falls due, the date of
microbiological test shall be advanced and the samples shall be taken
before emptying out the tank.
DELIVERY SYSTEM
• Delivery lines shall be positively segregated.
• A filter/water separator of 5-micron rating or finer as per API/EI
standards shall be installed on the delivery system for each product. This
filter shall be installed at the farthest possible end of the delivery system.
• FWS shall be inspected yearly and shall be changed:
1. After 3 years of use or the periodicity specified by the
manufacturer
whichever is earlier or
2. When the pressure differential reaches 15 PSI or
3. When the pressure differential drops suddenly at same flow rate.
REFUELLERS
• Refuellers shall be bottom loaded.
• After filling, product shall be settled for at least 10 minutes. Then a sample shall
be drawn from refueller tank bottom and checked for Test F.
• After heavy rains and washing of refueller, a tank bottom sample shall be tested
for Test F.
• Each refueller tank shall be internally cleaned once a year. Chemicals/Detergents
shall not be used for cleaning.
• Filter Elements / Monitors installed on the refuellers and hydrant dispensers
shall be replaced:
1. After 1 year of use or the periodicity specified by the manufacturer
whichever is earlier or
2. When the pressure differential reaches 15 PSI or
3. When the pressure differential drops suddenly at same flow rate.
• The filtration system of the Refuellers shall be subjected to Millipore
Test by gravimetric method, once in three months and colorimetric
method once in every month.