HOW TO CONSTRUCT A

PRECEDENCE TABLE
ID: Key-in ID on every line
ID Tasks & Subtasks Duration (Day) Predecessor(s) Resource Unit

1
2
3
4

5
6
7
8

9
10
11
12
13

14

15

16
TASKS AND SUBTASKS: Processes and
details of processes
ID Tasks & Subtasks Duration (Day) Predecessor(s) Resource Unit

1 Start
2 Concept
3 Evaluate Current System
4 Define Requirements

5 Website Design
6 Design User Interface
7 Design Server Setup
8 Develop Server Support Infrastructure

9 Website Development
10 Develop Pages and Links
11 Develop Functionality
12 Content Integration
13 Testing

14 Roll Out

15 Support

16 Deadline
DURATION (DAYS): No of days to do each
subtask
ID Tasks & Subtasks Duration (Day) Predecessor(s) Resource Unit

1 Start 0
2 Concept
3 Evaluate Current System 5
4 Define Requirements 5

5 Website Design
6 Design User Interface 12
7 Design Server Setup 6
8 Develop Server Support Infrastructure 6

9 Website Development
10 Develop Pages and Links 18
11 Develop Functionality 22
12 Content Integration 27
13 Testing 23

14 Roll Out 25

15 Support 28

16 Deadline 0
PREDECESSOR(S): previous subtask(s)
needed to be completed
ID Tasks & Subtasks Duration (Day) Predecessor(s) Resource Unit

1 Start 0
2 Concept
3 Evaluate Current System 5 1
4 Define Requirements 5 3

5 Website Design
6 Design User Interface 12 4
7 Design Server Setup 6 4,6
8 Develop Server Support Infrastructure 6 6,7

9 Website Development
10 Develop Pages and Links 18 4,6
11 Develop Functionality 22 4,6,10
12 Content Integration 27 7,10,11
13 Testing 23 12

14 Roll Out 25 13

15 Support 28 14

16 Deadline 0 15
RESOURCES: Types of workers required to do
each subtask
ID Tasks & Subtasks Duration (Day) Predecessor(s) Resource Unit

1 Start 0
2 Concept
3 Evaluate Current System 5 1 Web Analyst
4 Define Requirements 5 3 Web Analyst

5 Website Design
6 Design User Interface 12 4 Web Designer
7 Design Server Setup 6 4,6 System Engineer
8 Develop Server Support Infrastructure 6 6,7 Support Engineer

9 Website Development
10 Develop Pages and Links 18 4,6 Web Designer
11 Develop Functionality 22 4,6,10 Web Programmer
12 Content Integration 27 7,10,11 Web Analyst
13 Testing 23 12 Tester

14 Roll Out 25 13 System Engineer

15 Support 28 14 Support Engineer

16 Deadline 0 15
UNIT: No of workers required to do each
subtask
ID Tasks & Subtasks Duration (Day) Predecessor(s) Resource Unit

1 Start 0
2 Concept
3 Evaluate Current System 5 1 Web Analyst 1
4 Define Requirements 5 3 Web Analyst 1

5 Website Design
6 Design User Interface 12 4 Web Designer 1
7 Design Server Setup 6 4,6 System Engineer 2
8 Develop Server Support Infrastructure 6 6,7 Support Engineer 1

9 Website Development
10 Develop Pages and Links 18 4,6 Web Designer 1
11 Develop Functionality 22 4,6,10 Web Programmer 2
12 Content Integration 27 7,10,11 Web Analyst 2
13 Testing 23 12 Tester 1

14 Roll Out 25 13 System Engineer 2

15 Support 28 14 Support Engineer 1

16 Deadline 0 15