You are on page 1of 1

Activities Predecessors Duration (Days)

Project Approval 0 1
Design Layout 1 14
Hire Set Designer 1 14
Database & Feature design 2 7
Module design & Admin control pannel 2 7
Product category listing 4,5 28
Item listing 3,6 42
Payment gateway development 3,6 12
DOMAIN & HOSTING 4,5 2
Developing website 9 84
Testing website 1 7
Rating & Review system development 11 7
Training and developing admins 6,9,11 35
Survey review about website 13 1
Maintainance 14 5
Develop an Advertising Plan 6 7
Advertising Media 16 21
Stakeholder analysis 12 4
Cost & Benefit analysis 9 7
Technical & Operational analysis 7,19 5
Risk analysis 8,10,18,20 1
Website launching 15,17,21 10
Total Days for Project 119