Planning and Scheduling of Activities by Adding Detailed Tasks and Establishing the Time Required

to Complete the Tasks:

Days
Activity SL Detailed Activity
Required
1 Selection of project 2

2 Selection of appropriate client for project 1

3 Discussion with client and approval for project 2


Analysis
4 Existence manual data gathering 4

5 Final discussion and final data gathering 1

6 Database design 3

7 ER Diagram and Flow Chart 2

8 Selection of language and platform 1

Design
9 Selection of database server 1

10 Front-End develop (including UI/UX design) 20

11 Back-End develop 20

12 Testing 3

13 Maintenance and Bugs fixing 3

14 Final productionizing 1
Implementation

15 Training and Implementation 1

16 Handover to the client 1

Total 66 days