GANNT CHART

PRESENTATION
THESIS UPDATES
TASK / ACTIVITIES
Gathering of Rubber, Aggregates, sand and cement.

Preparation of Materials.

Preparation of mouldings for compressive strength and flexural strength.

Mixing of materials

Curing of Specimen

Testing (compressive strength and flexural strength)

Data analysis procedure


.
GATHERING OF SAMPLE /
SPECIMENS

TIRE RUBBER
CUTTING AND SEGREGATE CUT TIRE CHIPS
( 1 inch or 25.4 mm)

RUBBER TIRE CHIPS/ RUBBER CRUMBS


PREPARATION OF THE
MATERIALS

Sand And Aggregates


PVC PIPE/CYLINDER
Moulding as Per ASTM C39
6" x 24"
RECTANGULAR BEAM MOULDING As per
ASTM FOR FLEXURAL STRENGTH AND
ADDITIONAL COLLECTION OF RUBBER
FROM THE SOURCE