Professional Documents
Culture Documents
Mapping JCT
Standard forms of
JCT contracts contracts to
contract
procurement routes
Standard Form(s) of Contract
Other standard
forms 0.9 2.8
JCT is comprised of seven member bodies. The members of the company represent
those sectors of the construction industry who are the key participants in a
construction project.
• the British Property Federation
• the Local Government Association
• the Royal Institute of British Architects
• the Royal Institution of Chartered Surveyors
• the Contractors Legal Group Limited
• the National Specialist Contractors’ Council Limited;
• the Scottish Building Contract Committee Limited.
• No lump sum price can be given for the work, but a tender sum indicating the
anticipated final price can be calculated based on approximate measurement
of likely work involved.
• The only difference between the bills of approximate quantities and bills of firm
quantities is that they are prepared from less complete design information and
so can be produced at an earlier stage.
JCT Standard Building Contract (SBC 16)
JCT/IC is designed for use when the traditional procurement route has been chosen.
Developed to help fill the gap between the detailed and lengthy provisions of the
SBC and the relative simplicity of the Minor Works Building Contract
Available with or without quantities: the employer must provide drawings and
either a bill of quantities, specification, or work schedule to specify the quantity
and quality of work. Contract is a lump-sum contract.
4. There is the option to use the Intermediate Building Contract with Contractors
Design, ie IC/D, which allows the contractor to design discrete parts of the works
5. In addition to the two versions of the Intermediate Building Contract, the JCT also
publish a number of sub-contracts for use with the Intermediate Building
Contracts
– Intermediate Sub-Contract (ICSub/D)
– Intermediate Sub-Contract with Sub-Contractor’s Design (ICSub/D)
JCT Minor Works Contract
(JCT/MW)
Appropriate/used when:
• Traditional procurement route is selected i.e. the work is designed on behalf of
the employer.
6. If design input is required, use the Minor Works with Contractors Design,
MW/D, which allows the contractor to design discrete parts of the works.
7. In addition to the two versions of the Minor Works Building Contract, the JCT
also publishes a Minor Works Sub- Contract with Sub-Contractor’s Design
(MWSub/D) and Short Sub-Contract (ShortSub).
8. JCT Design and Build (JCT/D&B)
Appropriate:
• Where the contractor is not only to carry out and complete the works but
also complete the design (design and build procurement route)
• Where detailed contract provisions are necessary, and the Employer’s
Requirements have been prepared and provided to the contractor.
• Contract is based on a fixed price lump-sum with stage or periodic
payments to the contractor.
For use with the Design and Build Contract, the JCT publishes the Design and
Build Sub-Contract (DBSub)
9. JCT Major Project Construction Contract (MP)
• JCT/MP is designed for use where the design and build procurement route
has been chosen.
• Is based on fixed price lump-sum contract, but the parties can agree on a
range of payment options e.g. interim valuations, stage payments, scheduled
payments
• Is shorter and simpler than the JCT Design and Build Contract
• For use with the Major Project Construction Contract, the JCT publishes the
Major Project Sub-Contract (MPSub).
10. JCT Management Building Contract (MC) 2011
JCT/MC is designed for use where management contracting procurement route has
been chosen. Based on next tier up (i.e employer and construction manager), the MC
may be appointed based on a % fee (cost reimbursable) or lump sum - client & MC which
in-turn when all the packages have been let and agreed converts to lump sum".
– Large scale projects requiring an early start on site.
– Where the works are designed by the Employers design team
– Where it is not possible to prepare full design information before the works
commence
– Where much of the detail design may be of a sophisticated nature requiring
proprietary systems or components to be designed by specialists
– Where the employer is to provide the management contractor with drawings
and specification
– Where a management contractor is to administer the conditions
• The contractor is paid the prime cost of the works, as well as a contract fee in
respect of its non-site overheads and profit. Therefore, there is a higher risk for the
employer in terms of cost.
13. JCT Measured Term Contracts (MTC)
• Suitable for projects procured via the traditional, using a measurement payment
structure.
• Appropriate for use by employers who have regular flow of maintenance and
minor works, including improvements
• to be carried out by a single contractor over a specified period of time and all
under a single contract.