PERMIT TO WORK

Polin Panggabean

I AM LEADER IN HSE
www.medcopower.co.id
ALL ACCIDENTS ARE PREVENTABLE
OUTLINE
PHILOSOPHY

SCOPE AREA

SAFE FROM THE SYSTEM & SAFETY


FROM ENVIRONMENT

RESPONSIBILITY OF PERSON

PTW DOCUMENT AND PROCESS

2
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PHILOSOPHY

Principle:
 Designed to prevent or reduce the possibility of workplace accidents,
incidents or unit failures that could harm workers, the environment and
the plant itself.
 Every related stakeholder in the permit to work system shall implement
the PTW procedure.

3
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PHILOSOPHY

Purpose:
 Know Permit to Work system and process

 More skill related to safety aspect during a hazardous work is executed

 Each stakeholder understands their position and responsibilities in the


PTW system

 The PTW system is applied to prevent / minimize accident, incident or


plant failure

4
I AM LEADER IN HSE | ALL ACCIDENTS ARE
SCOPE AREA

REQUIREMENT AREA
Non Part of System (no PTW required)
⛔ Laboratory
⛔ Workshop
⛔ Office
⛔ Mobile plant / heavy equipment

Part of System (required PTW)


✅ Mechanical Plant
✅ Electrical Plant
5
I AM LEADER IN HSE | ALL ACCIDENTS ARE
SCOPE AREA

1. Non Part of System (no PTW required)

Laboratory Workshop Office Heavy Equipment

6
I AM LEADER IN HSE | ALL ACCIDENTS ARE
SCOPE AREA

2. Part of System (PTW is required)


ELECTRICAL PLANT

ESP TURBINE
BFP MOTOR CEP MOTOR
TRANSFORMER GENERATOR

7
I AM LEADER IN HSE | ALL ACCIDENTS ARE
SCOPE AREA

2. Part of System (PTW is required)


MECHANICAL PLANT

BFP CEP CONDENSER ACWP

8
I AM LEADER IN HSE | ALL ACCIDENTS ARE
SAFETY FROM THE SYSTEM

HAZARDS:
1. HAZARD FROM THE SYSTEM: Temperature, Pressure, Electrical, Chemical

Electrical Shock

High
Temperature Chemical

High
Pressure

Condensate Extraction Pump Ammonia Storage Tank

9
I AM LEADER IN HSE | ALL ACCIDENTS ARE
SAFETY FROM THE SYSTEM

HAZARDS:
2. HAZARD FROM ENVIRONMENT: Slippery floor, wet floor, high elevation

Unsafe access road


Lack of Lighting

10
I AM LEADER IN HSE | ALL ACCIDENTS ARE
SAFETY FROM THE SYSTEM

GENERAL SAFETY
1. SAFE ACCESS AND EXIT PATHS
2. SAFE METHOD OF WORKS
3. SAFE WORKPLACE
4. PROPPER PPE
5. PROPPER TOOLS

The MAINTENANCE SUPERVISOR is responsible for establishing General


Safety in the area of work before work begins
11
I AM LEADER IN HSE | ALL ACCIDENTS ARE
RESPONSIBILITY OF PERSON
1. AUTHORIZED LEADER (AL)
a. AL shall comply with the procedure when preparing, confirming,
issuing/re-issuing and closing PTW document.
b.AL shall ask permission to Shift Coordinator in charge for any
work/testing which could effect safety to people, operating plant,
environment impact.
c. AL shall inform to Shift Coordinator in charge after work/testing has
been completed.
d. AL issue work permits based on hazard, risk and people
competency.
AL = Shift Coordinator, PTW Officer

12
I AM LEADER IN HSE | ALL ACCIDENTS ARE
RESPONSIBILITY OF PERSON
2. AUTHORIZED OPERATOR (AO)
a. AO shall comply with these procedure when carrying out isolation,
de-isolation, and restoration as instructed by AL.
b.AO shall check and confirm that integrity of isolation is fulfilled.
c. AO shall complete the Isolation Restoration Instruction (IRI) before
giving it to AL for confirming.
AO = Unit Supervisor, Field Operator

13
I AM LEADER IN HSE | ALL ACCIDENTS ARE
RESPONSIBILITY OF PERSON
3. COMPETENT PERSON (CP)
a. CP shall comply with these procedures when carrying out work or
testing whether instructions are issued verbally or written.
b.CP shall use safe methods of work, safe means of access and Personal
Protective Equipment which is provided for their safety (Establishing
& Maintaining General Safety)
c. CP receive work permit (verbally or PTW doc), carry out the
work/testing, clear work/testing, transfer or suspend PTW document.
CP = Maintenance Supervisor, Technician

14
I AM LEADER IN HSE | ALL ACCIDENTS ARE
RESPONSIBILITY OF PERSON
3. COMPETENT PERSON (CP)
d. Maintenance Supervisor may act as Competent Person &
Supervisor at the same time
e. Maintenance Supervisor briefs the Competent Person in charge of a
working party stated on PTW document
f. Record all names of working party people
g. Make sure that the Work Order (WO) clearly inform that the work
to be done is under working party
h. Cross check the integrity of isolation points
i. Inform Authorized Leader if the System safety hazard arise
j. Inform Maintenance Supervisor if General safety hazard arise

15
I AM LEADER IN HSE | ALL ACCIDENTS ARE
RESPONSIBILITY OF PERSON
4. QUALITY PERSON (QP)
Quality Person is responsible to make a report and recommendations
for specific works: Confined Space, Working at Height, Hot Work,
Excavation and Radiography.
QP = HSE Officer

16
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
SAFETY DOCUMENT:
VERBAL
PERMIT TO WORK
NONE

SPECIFIC WORK CERTIFICATE:


CONFINED SPACE
EXCAVATION
HOT WORK
RADIOGRAPHY
WORKING AT HEIGHTS
17
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS

18
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
SEQUENCE OF PTW DOCUMENT PROCESS

1. PREPARING PTW 3. ISSUING PTW 4. PTW DOCUMENT


2. ISOLATION
DOCUMENT DOCUMENT RECEIVED
BY AO
BY AL BY AL BY CP

5. WORK 6. DE-ISOLATION & 7. CLEARANCE 8. CLOSING


EXECUTION RESTORATION DOCUMENT DOCUMENT
BY CP BY AO BY CP BY AL

19
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
SEQUENCE OF PTW DOCUMENT PROCESS

1. PREPARING
PTW DOCUMENT
BY AL

20
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
ISOLATION PROCESS

1. RECEVING IRI 3. GOING TO


2. INFORMING UNIT
FROM AUTHORIZED SWITCH GEAR
SPV INCHARGE
LEADER BY AL ROOM (MV/LV)

4. IDENTIFYING 5. CONFIRMING TO
EQUIPMENT TAG UNIT SPV, THEN 6. MECHANICAL
NUMBER/KKS SWITCH OFF ISOLATION
NUMBER POWER/RACK OUT

21
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
BASIC ISOLATION

ELECTRICAL MECHANICAL
ISOLATION ISOLATION

BASIC RESTORATION

ELECTRICAL MECHANICAL
ISOLATION ISOLATION
22
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
SEQUENCE OF PTW DOCUMENT PROCESS

2. ISOLATION Apply Isolation


BY AO  The Authorized Operator Inform &
Coordination to Unit Supervisor (by radio or
phone before apply isolation)
 The Authorized Operator Check & Confirm
equipment is correct (tag number)
 Use correct isolation method:
1. Motor
2. Mechanical
3. Earth, drain, vent, purge, stored energy

23
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
SEQUENCE OF PTW DOCUMENT PROCESS

2. ISOLATION
BY AO

24
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
SEQUENCE OF PTW DOCUMENT PROCESS

2. ISOLATION Authorized Operator applying


BY AO Lock Out Tag Out

Authorized Operator returns keys


to Authorized Leader

25
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
SEQUENCE OF PTW DOCUMENT PROCESS

3. ISSUING PTW
DOCUMENT
BY AL

26
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
SEQUENCE OF PTW DOCUMENT PROCESS
4. PTW DOCUMENT
RECEIVED
BY CP

27
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
ESTABLISHMENT OF GENERAL SAFETY
5. WORK
EXECUTION
BY CP

The MAINTENANCE
SUPERVISOR is responsible for
establishing General Safety in the
area of work before work begins

28
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
ESTABLISHMENT OF GENERAL SAFETY
By Supervisor
SHALL IMPLEMENT AND MAINTAIN
OF GENERAL SAFETY
By Competent Person

• Competent Person shall ensure that his


working person ONLY do the work specified
on the Work Order and the PTW Document

• If an additional System-derived hazard


occurs or is suspected, Competent Person
shall stop the work & withdraw all working
people

29
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS

6. DE-ISOLATION &
RESTORATION
BY AO

30
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS

7. CLEARANCE
DOCUMENT
BY CP It shall to be cleared if the work/
test has been done

Unit/equipment now turned


to stand by

31
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS

8. CLOSING
DOCUMENT
BY AL

32
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS
Note:
a. CP must inform shift coordinator and or US/Field Operator
b.After work finished, CP shall check there’s no tools left at site
c. CP can ask field operator for equipment identification
d.When doing de-isolation and restoration, AO have to applying
mechanical part first then electrical part

33
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS

Special case:
1. Transfer PTW Document
a. Transfer PTW Document
Competent person RETURNING
PTW document shall fill part 1.
b. New Competent Person receiving
PTW document shall fill part 3
c. Authorized Leader re-issuing PTW
document shall fill part 3

34
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PTW DOCUMENT AND PROCESS

2. Suspend PTW Document


Authorized Leader receiving
Suspended PTW document shall fill
part 2

35
I AM LEADER IN HSE | ALL ACCIDENTS ARE
Case Study
1

2
3

5
4

Masing-masing
Equipment di LOTO

ISOLATION : 1-2-3-4-5
RESTORATION : 5-4-3-2-1
36
I AM LEADER IN HSE | ALL ACCIDENTS ARE
THANK YOU
I AM LEADER IN HSE | ALL ACCIDENTS ARE
PREVENTABLE

PT Medco Power Servis Indonesia


The Energy Building 31st Floor
SCBD Lot 11A
Jl. Jend. Sudirman, Jakarta 12190
Indonesia
P. +62-21 2995 3300
F. +62-21 2995 3301

Website : www.medcoenergi.com | www.medcopower.co.id

OE for Safety, Excellent Operations and Efficiency

You might also like