Professional Documents
Culture Documents
Vijay Vittal
Regents’ Professor
Ira A. Fulton Chair Professor
Arizona State University
Overview
• This first part of the hybrid simulation or co-simulation of
the transmission and distribution system will address the
topic of co-simulation between the a) transmission and
distribution system components and b) between
transmission system components related to electromagnetic
transient simulation and electro-mechanical simulation
• Topic a) will examine hybrid simulation between EMT and
Phasor domain simulation related to single-phase motor
models in the distribution system
• Topic b) will examine hybrid simulation between EMT
models of HVDC components in the transmission system
and the rest of the system modeled in phasor domain
2
Introduction
Significant changes in power systems
• Rapid development of • Distributed generation (PV,
renewable generation Wind)
• Shutdown of coal power • More dynamic loads (Air
plants conditioners, VFD motors)
• HVDC
• FACTS
Electromagnetic
Simulation Transient stability
transient
Three-phase, Positive-sequence,
Modeling
point-on-wave phasor
6
Introduction: Hybrid simulation
Involves electromagnetic transient (EMT)- electro-mechanical
transient stability(TS) hybrid simulation
Remainder of the system
Region of interest • Sequence,
• Instantaneous
phasor model
variable model • TS simulator
• EMT simulator Boundary
System
Current
Zik
8
Two main challenges in power system dynamic simulation
• Three-phase, • Sequence,
POW model phasor model
• EMT simulator • TS simulator
Region of interest Remainder of the system
< 300 buses ~15000 buses
Detailed system External system
Boundary bus i Vi0abc Boundary bus i
Composite Ii120
Iiabc Zi + -
Load
Detailed Model External system
Thévenin modeled in three-
……
System
Zik
10
OpenHybridSim: A new EMT-TS hybrid simulation tool
A decoupled architecture
Three-sequence TS simulation developed based on InterPSS
Network equivalents:
• Three-phase Thévenin equivalent of the external system in EMT simulation
• Three-sequence current source as the equivalent of the detailed system in three-sequence
TS simulation
TCP/IP socket communication for connecting two simulators
A generic interface framework for integrating with different EMT
simulators, e.g., PSCAD, ATP-EMTP
Three-sequence TS
𝑎𝑏𝑐
PSCAD/EMTDC
𝑉 𝑇 (𝑡 )
algorithm
ATP-EMTP
TCP/IP Hybrid Simulation Manager
Socket
MATLAB/Simulink
communi- OpenHybridSim
SimPowerSystems Network
... cation
Socket Equivalent Helper
120
EMTP-RV
𝐼 𝐸𝑀𝑇 ( 𝑡 )
Server Sub-Network
Helper
11
Socket based communication framework
TCP/IP socket based communication framework
• Enables decoupling of the EMT and TS simulators
• Supports application environment
- Single computer
- Local area network(LAN)
- Internet
• Socket components in PSCAD and Matlab/SimPowerSystems
are developed for interfacing
13
The procedure of building a three-phase
Thévenin equivalent
Perform source
Convert the three-sequence Build a three-sequence
transformation to obtain
Norton equivalent to three- Norton equivalent for the
the objective three-phase
phase Norton equivalent external system
Thévenin equivalent
14
Equivalent of the external system in EMT simulation:
Three-phase Thévenin equivalent
Three- Three-phase
Three-phase
sequence Source
120-ABC Norton Thévenin
Norton transformation
equivalent equivalent
equivalent
𝜙 𝜙 𝜙
INi120 IEMTi120
𝐼
𝑎𝑏𝑐
𝑁𝑖 =𝑺 𝐼
120
𝑁𝑖
V =𝐼 /𝑦
𝑇𝑖 𝑁𝑖 𝑖
𝜙 𝜙
𝑧 =1 / 𝑦
INj120 IEMTj120
YN120 𝑎𝑏𝑐 120 −1 𝑖 𝑖
𝑦 𝑖 =𝑺 𝑦 𝑖 𝑺
...
...
INk120 IEMTk120
𝑎𝑏𝑐 120 −1
𝑦 𝑖𝑘 =𝑺 𝑦 𝑖𝑘 𝑺
[ ]
𝑰 120
𝑁 =𝒀 120
𝑁 𝑽 120
𝑇𝑆 − 𝑰 120
𝐸𝑀𝑇
1 1 1
𝑺= 𝑎 2 𝑎 1
[ ]
𝑌 (𝑁𝑖𝑘
1) 2
0 0 𝑎 𝑎 1
120
𝑌 𝑁𝑖𝑘= 0 𝑌 (𝑁𝑖𝑘
2)
0 𝑗 2𝜋 /3
0 0 𝑌 (𝑁𝑖𝑘
0) 𝑎=𝒆
15
Equivalent of the detailed system in TS simulation: three-
sequence current source
• Three-sequence current source
• Seamlessly integrated into the network solution step of the
three-sequence TS simulation
• Obtained from boundary current injection waveforms
using FFT and 3-phase to 3-sequence transformation
Boundary bus i
Ii120
External system
modeled in three-
sequence
Ik120
Boundary bus k
=0
Negative sequence
=0
Zero sequence
17
Interaction protocol
• Interactions between the two simulators
Socket InterPSS Core Engine
EMT
Simulator Communication
Network
I120 Equivalent Helper
EMT (t )
Socket
V abc Socket HybridSim
Component T (t )
Server Manager
2
TS TS
… Parallel …
Serial 3
5
1
4 … …
.. .. ..
... ...
...
. . . EMT EMT
t t+ΔT t+2ΔT t+3ΔT t t+ΔT t+2ΔT t+3ΔT
Step (4)
120 120
I EMT ( t ) I EMT ( t T )
EMT EMT EMT Step (5) EMT EMT
socket
client step step step …………………………………….. step step
1 2 3 N-1 N
t x(t T ) t T
120
x(t ) V TS ( t )
Calculate
Three-
socket three-phase socket
server 120 Thévenin sequence TS
VTS120(t ) I EMT ( t ) equivalent
server
simulation
VTS120(t T )
120 Step (b) Step (c) Step (d) Parallel
I EMT Step (a)
(t )
V abc protocol
T (t )
120
120 Step (e) I EMT ( t T )
I EMT ( t ) EMT EMT EMT EMT
socket
client
step step ... step step
1 2 N-1 N
t t T 19
The fault-induced delayed voltage recovery problem
• What is FIDVR problem?
• Root cause:
Stalling and prolonged tripping of 1-ϕ residential air conditioner (A/C)
compressor motor
• Direct impact of distribution on transmission system
[1] D. N. Kosterev, A. Meklin, J. Undrill, B. Lesieutre, et al., "Load modeling in power system studies: WECC progress
update," in 2008 IEEE Power and Energy Society General Meeting, 2008, pp. 1-8.
20
Application of EMT-TS hybrid simulation to FIDVR study on
the WECC system
The WECC system Buses with a large percentage of
Transmission 1-Ф A/C load
Buses lines Generators Loads
• Bus 24151
15750 13715 3074 7787
• Bus 24138
sub
24092
500 kV 7
24236
EAST Number of 230 kV 37
24801
sub
24138 buses of 161 kV 3
28040 different 115 kV 68
15093
sub
24151
sub
voltage levels 92 kV 18
M M M
115 kV
22
Case A: fault POW at voltage zero crossing
Line to neutral voltages of bus 24151
SLG 1
Voltage (pu)
0.5
phase A
0 phase B
-0.5 phase C
-1
Voltage (pu)
0.5
phase A
0 phase B
-0.5 phase C
-1
Voltage (pu)
0.5
Vab
0 Vbc
-0.5 Vca
-1
0.5
phase A
Measurement 0 phase B
phase C
location
-0.5
-1
23
Case A: responses of A/C motors
phase A phase B phase C
0 0 0
0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6
Time (s) Time (s) Time (s)
A/C Motor Speed (pu)
0 0 0
0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6
Time (s) Time (s) Time (s)
15 15 15
Real and reactive
power (kW/kVar)
power (kW/kVar)
10 Reactive power 10 Reactive power 10 Reactive power
5 5 5
0 0 0
-5 -5 -5
0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6
Time (s) Time (s) Time (s)
Electrical/Mechanical
Electrical/Mechanical
Electrical/Mechanical
Electrical torqure Electrical torqure Electrical torqure
Torqure (N*m)
Torqure (N*m)
Torqure (N*m)
50 50 50
Mechanical torque Mechanical torque Mechanical torque
0 0 0
Voltage (pu)
1
phase A
0.5
phase B
phase C
0
0.6 0.8 1 1.2 1.4 1.6 1.8
Voltage (pu)
1 phase A
phase B
0.5 phase C
0
0.6 0.8 1 1.2 1.4 1.6 1.8
Voltage (pu)
1 Vab
Vbc
0.5 Vca
0
0.6 0.8 1 1.2 1.4 1.6 1.8
1 phase A
phase B
0.5 phase C
0
0.6 0.8 1 1.2 1.4 1.6 1.8
1 phase A
phase B
0.5 phase C
0
0.6 0.8 1 1.2 1.4 1.6 1.8
Time (s) 25
phase A phase B phase C
0 0 0
0.5 1 1.5 2 0.5 1 1.5 2 0.5 1 1.5 2
Time (s) Time (s) Time (s)
A/C motor speed (pu)
0 0 0
0.5 1 1.5 2 0.5 1 1.5 2 0.5 1 1.5 2
Time (s) Time (s) Time (s)
60 60 60
Real power Real power Real power
power (MW/MVar)
power (MW/MVar)
power (MW/MVar)
Real and reactive
20 20 20
0 0 0
0.5
Voltage (pu)
phase A
0 phase B
phase C
-0.5
-1
0.5
Voltage (pu)
phase A
0 phase B
phase C
-0.5
-1
0.5
Voltage (pu)
Vab
0 Vbc
Vca
-0.5
-1
0.5
Voltage (pu)
phase A
0 phase B
phase C
-0.5
-1
1 1 1
0 0 0
0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6
Time (s) Time (s) Time (s)
A/C Motor Speed (pu)
0 0 0
0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6
Time (s) Time (s) Time (s)
15 15 15
Real and reactive
power (kW/kVar)
power (kW/kVar)
Real power Real power Real power
10 Reactive power 10 Reactive power 10 Reactive power
5 5 5
0 0 0
-5 -5 -5
0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6 0.6 0.8 1 1.2 1.4 1.6
Time (s) Time (s) Time (s)
Electrical/Mechanical
Electrical/Mechanical
Electrical/Mechanical
Electrical torqure Electrical torqure Electrical torqure
Torqure (N*m)
Torqure (N*m)
Torqure (N*m)
50 Mechanical torque 50 Mechanical torque 50 Mechanical torque
0 0 0
0 0 0
0.5 1 1.5 2 0.5 1 1.5 2 0.5 1 1.5 2
Time (s) Time (s) Time (s)
A/C Motor Speed (pu)
0 0 0
0.5 1 1.5 2 0.5 1 1.5 2 0.5 1 1.5 2
Time (s) Time (s) Time (s)
60 60 60
power (MW/MVar)
power (MW/MVar)
power (MW/MVar)
Real and reactive
20 20 20
0 0 0
The responses of the A/C motors at the quarter length point of a feeder
with the fault POW as 90 degrees
29
Effect of Load Composition on AC Motor Stalling
Case Load composition (in terms of real power)
#
1 75% 1-Ф A/C compressor motor, 25% constant impedance
2 75% 1-Ф A/C compressor motor, 10% 3-Φ NEMA type B
induction motor, 15% constant impedance
3 70% 1-Ф A/C compressor motor, 15% 3-Ф NEMA type B
induction motor, 15% constant impedance
4 60% 1-Ф A/C compressor motor, 15% 3-Ф NEMA type B
induction motor, 25% constant impedance
30
Phase A Phase B Phase C
A/C motor speed (pu) A/C motor speed (pu) A/C motor speed (pu) A/C motor speed (pu)
1.5
1 Case 1
0.5
0
0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2
1.5
1 Case 2
0.5
0
0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2
1 Case 4
0.5
0
0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2
A/C motor speed (pu)
1.5
1 Case 5
0.5
0
0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2
Time (s) 31
Comparisons of the bus voltages for two different POW cases: (left)
case 5; (right) case 5A 32
Application of hybrid simulation to power systems interfaced with
a LCC-HVDC system
Test case: IEEE 39 Bus system with a LCC HVDC infeed
• HVDC system
CIGRE HVDC model ~ ~
30 37
Rated power: 1000 MW 25 26 28 29
The inverter is connected to bus 39 2 27 38
~
1
• EMT simulation 3 18 17
PSCAD 1 PSCAD
5
0 0.5
Vdc (pu)
0.3
2.95 3 3.05 3.1 3.15 3.2 0 0.2
10 0.1
EMT-TS
Phase B -0.5 0
Current(kA)
PSCAD
5
3.07 3.08 3.09
-1
0 2.95 3 3.05 3.1 3.15 3.2
(a)
4
2.95 3 3.05 3.1 3.15 3.2 EMT-TS
10 2 PSCAD
EMT-TS
Idc (pu)
Phase C
Current(kA)
PSCAD
5
0
0
-2
2.95 3 3.05 3.1 3.15 3.2 2.95 3 3.05 3.1 3.15 3.2
Time (s)
(b) Time(s)
Three phase current flowing into bus 39 The DC voltage (Vdc) and current
from the HVDC inverter (Idc) of the HVDC inverter
34
Application of hybrid simulation to power systems
interfaced with a LCC-HVDC system
EM T-TS PSCAD
5 1.5
Current (kA)
PSCAD
0
EMT-TS
1
-5
0.5 1.2
0
1
-5 0 0.8
2.95 3 3.05 3.1 3.15 3.2
10 0.6
Current (kA)
0
3 3.05 3.1 3.15
-0.5
3 3.2 3.4 3.6 3.8 4 4.2 4.4 4.6 4.8 5
-10
2.95 3 3.05 3.1 3.15 3.2 (a) time (s)
5 2
Current (kA)
0 1 PSCAD
EMT-TS
0.8
-5 Commutation 1.5
1 0.4
0
0
0
-5 3 3.2 3.4 3.6 3.8 4 4.2 4.4 4.6 4.8 5
2.95 3 3.05 3.1 3.15 3.2 time (s)
Time (s) (b)
• Time step : 5 µs 1
3 18 17
~
16
Hybrid simulation ~ 39
37
Applied to power systems interfaced with HVDC
1.1
0.7
bus 29 (AC bus of the rectifier) 0.95 1 1.05 1.1 1.15 1.2
0
rectifier to the fault: 0.95 1 1.05 1.1 1.15 1.2
DC Voltage (pu)
(b) Reactive power flowing into 1
EMT-TS
(d) DC current
DC current (pu)
1
EMT-TS
0 PSCAD
-1
0.95 1 1.05 1.1 1.15 1.2
Time (s)
38
EMT-TS
Volta
0.8 PSCAD
bus 8
Applied to power systems interfaced with HVDC
0.95 1 1.05 1.1 1.15 1.2
(b)
• Positive sequence
Voltage (pu)
1
EMT-TS
voltage of bus 25
PSCAD
(within the external 0.8
bus 25
system) 0.95 1 1.05 (c) 1.1 1.15 1.2
Time (s)
Computation times for a 2-second simulation
Computation
Simulation method time
39
Examining Impact of Utility Scale PV Plants
40
PV plant dynamic modeling
• Plant control and converter electric control [1] implemented in
PSCAD [2] and PSLF are logically the same
• REPC -- plant control
• REEC -- converter electrical control, i.e., power command to current
command
• Converter modeling:
• REGC (performance model in PSLF and PSS/E)
– converter current control, i.e., low voltage real power control and low/high voltage
reactive power control
– A simplified representation of complex and very fast controls of PV converters
• Detailed converter model in PSCAD
41
PV plant dynamic modeling
Positive sequence, generic PV Point-on-wave, detailed PV
plant model plant model
Basic assumptions • Dynamics of the DC side of the Standard PLL and PWM based
inverter are ignored converter
• Three phase balanced
• Fast dynamics of converter and
its controls are ignored
Existing models • 1st generation converter model: • Proprietary models
GEWTG developed by vendors
• WECC generic model: REPC_A • An open model developed
+ REEC_B + REGC_A by NREL (REEC_B +
REGC_A + PWM based
Converter)
Simulation PSS/E, PSLF, PowerWorld, … PSCAD, EMTP-RV,…
software
Main limitations • The effects of PLL and PWM • Not suitable for system level
controls are ignored study with a large number of
• Current injection model for PV plants, due to the very
interfacing with the network detailed modeling approach
solution
42
A comparison of detailed and generic
PV plant models
• Test system
System
equivalent PCC
Equivalent 34.5 kV/0.69 kV
bus 230 kV/ 34.5 kV 25 MW
feeder PF = 0.99
PV
R = 0.005 pu
Converter
R = 0.002 pu X = 0.06 pu
X = 0.05 pu X = 0.10 pu X = 0.02 pu
100 MVA 50 MVA 50 MVA
1000 MVA 50 MVA
43
Scenario 1: A 3-phase fault close to PCC
30
PV
Real power (MW)
power 20
detailed (PSCAD)
performance(PSLF)
output 10
0
0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
60
Reactive power (MVar)
detailed (PSCAD)
40 performance(PSLF)
20
-20
0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
Time (s) 44
Scenario 1: A 3-phase fault close to PCC
• Voltage dips to 0.3 pu at the PCC at 1.0 s, lasting 3 cycles
1.2
detailed (PSCAD)
1.1 performance(PSLF)
0.9
Voltage (pu)
0.8
0.7
0.6
0.5
0.4
0.3
0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
Time (s)
power 25
output 20
15
0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
20
Reactive power (MVar)
detailed (PSCAD)
performance(PSLF)
10
-10
0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
Time (s) 46
Scenario 2: A fault relatively far from PCC
• Voltage dips to 0.763 pu at the PCC at 1.0 s, lasting 3 cycles
• PV converter AC bus voltage magnitude
1.1
detailed (PSCAD)
1.05 performance(PSLF)
1
Voltage (pu)
0.95
0.9
0.85
0.8
0.75
0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
Time (s) 47
Single-Line Diagram of Area Around PV Plants
48
Case 1 Considered
49
The positive sequence voltage and power output of the
PV plant A with a normally-cleared SLG fault
50
The positive sequence voltage of three 500 kV substations, P 1, P2, and H2
in the study region with a normally-cleared SLG fault
51
Case 2 Considered
• In this test case, a SLG fault at the H1 end of the 500
kV H1-J1 transmission line is considered. Different
from the last case, in this case, the breaker CB5 (shown
in figure on the next slide ) is correctly tripped at 3
cycles after the fault, but the breaker CB2 gets stuck
and the fault cannot be cleared. After a delay interval of
10 cycles (i.e., the final tripping time is 13 cycles after
fault on), the neighboring breakers that back up the
stuck breaker are tripped to clear the fault
• Regarding the pole operation of the breakers, in this
study, it is assumed that the breakers operate with three-
pole operation, which means when one breaker is
switched off/on, all three phases are open/close
simultaneously
52
53
The positive sequence voltage and power output of the
PV plant A for a SLG fault with delayed clearing
54
The positive sequence voltage of three 500 kV substations, P 1, P2, and H2
in the study region for a SLG fault with delayed clearing
55
References