Professional Documents
Culture Documents
CONSTRUCTION
COMMISSIONING,
(SIMULTANEOUS
OPERATIONS)
Introductions
What is your name ?
• Training Sessions
• Toolbox Talks
• Pre-Task Discussions
• Method Statements
• Risk Assessments
• Inductions
Page 4 of 11
TOPIC FOR DISCUSSION
INTERFACE CONTRUCTION/COMMISSIONING
BARRIERS AND SIGNS
COMMISSIONING
TYPE OF ISOLATION
Page 5 of 11
BARRIERS & SIGNS
• Correct type of safety
tools
• Correct level of safety
(PPE, Tools to safely
execute the Scope of
Work)
• Full face shields during
chemical unloading
PERMIT TO WORK SYSTEM
• Hot Work naked Flame
• Spark Potential
• Cold work
• Confined Space - Stand by men
• Vehicle Entry (Diesel fueled
+ Flame arrestor)
• Equipment Disjointing
• Authorization / Training
CONTROL MEASURE?
TYPICAL CONTROL MEASURES
• Permit to Work • Emergency Preparedness
• /MOS/TRA (Task Risk (Shower, Eyewash
Assessment) Station)
• MOC (Management of • First Aid Kit
Change) • Detection System
• Barricades/Signs • Energy Isolation-LO/TO
• Communication • PPE
• Competent Personnel • Training
HIGH RISK OF SCOPE WORK INCLUDE
PRESSURE TESTING
LEAK TESTING
PRESSURE TESTING
Pneumatic testing and very high-
pressure hydro testing (HHP) –
• Conducted by Competent Person
• Only Authorized
Personnel in the
vicinity
HAZARDS OF NITROGEN
Ground Level
Beware of changing fittings on piping being purged with nitrogen, e.g., changing a valve,
turning a spectacle blind, etc.
ELECTRICAL ISOLATIONS/
RE-ENERGISATION
• Can only be carried out by Authorized Electrical
Person
• Only AEP can isolate/de-isolate electrical
equipment
• Task Supervisor to sign Electrical Isolation
Certificate and witness isolation
Page 9 of 11
Types of Lock Out Devices
Mechanical isolation used for gas, liquid or vapor:
Spade
Chemical Handling
Page 10 of 11
DO NOT OBSTRUCT
- Safety Equipment
Or
- Access/Egress
Page 11 of 11
ORGANIZATION SIMOPS
• Principle:
Construction, Commissioning, and
Production must run together Parallel
operation.
An awareness program on simultaneous
operations (SIMOPS) is crucial for
maintaining a high level of safety in site.
This program ensures that safety
Applied in a Procedure to fix:
measures and protocols are effectively
Responsibilities
implemented.
Coordination
Relationship between
all involved parties
SIMOPS - Introduction
• Simultaneous Operations (SIMOPS) is when more than one activity takes place in the
same location or area either of which have the potential to seriously / catastrophically
impact the other activities.
Activity # 1 Activity # 2
Risk Identified Risk Identified
Safeguards in place Safeguards in place
SIMOPS Responsibilities and Main Tasks
• HSE Plan for SIMOPS is required and shall define all
procedures and organization
• HAZID and consequence analysis to be performed
• Risk to be assessed and “Hazard and Risk Register &
Mitigation Plans” to be updated to reflect findings
• Proper Permitting and Control are KEY to Success –
Communicating and Planning (Use PTW to carry out the work)
SIMOPS Responsibilities and Main Tasks, Contd…
Electrical Isolation
Instrument Isolation
CONTROL PRINCIPLE
Training
TRAINING
TRAINING
Training helps Coordination of Activities
Work Permit
H2S
Hydrocarbon risks