Professional Documents
Culture Documents
OF
TUNNELING
METHODS OF TUNNELING
2
OPEN CUT METHOD
Open cut method often refers to excavation with
battered sides such that no lateral support is required.
In its simplest form, a trench is excavated, the tunnel
structure is built, the trench is backfilled and the
surface is restored.
Precast tunnel units can also be employed to speed up
to construction process.
The major problem of this method is the procession of
land so that it is not too suitable in urban areas.
Moreover, it is only suitable for shallow tunnels only
because with increased depth, direct costs of trench
excavation and backfilling increase rapidly. 3
4
CUT AND COVER METHOD
The cut-and-cover method involves construction of a box
frame structure within a trench excavation that is
subsequently backfilled.
In urban settings the cut-and-cover method requires utility
relocation, traffic re-routing, and creates construction
impacts in the form of noise, dust, and traffic disruption.
Decking can be placed over the cut immediately following
the first lift of excavation to reduce traffic disruption.
The decking is removed and the surface restored at the end
of construction.
Temporary excavation support walls are installed before
significant excavation commences.
5
6
7
PRE-DECK METHOD
Same as the open-cut method, the pre-deck method is
suitable for low level tunnels.
The tunnel walls are constructed by the diaphragm walling
method first and then the upper surface of the ground is
removed.
The upper deck of the tunnel is cast supported on the
diaphragms.
It is then backfilled and the road surface is reinstalled.
Now the tunnel excavation can be started from both ends of
the tunnel without the fear of collapse and with minimum
disturbance to traffic and services.
8
9
SHIELD TUNNELLING METHOD
For small diameter pipes, bullet-shaped solid metal
heads are fixed to the leading end of the pipe, which is
jacked into the ground displacing the earth.
10
Contd..
When tunnelling in water bearing ground, ground
water infiltration will create problems.
15
Contd..
Bentonite Shield
A bentonite shield is equipped with a pressure bulkhead
and a chamber.
16
Contd..
Rock TBM
TBM excavate rock mass in a form of rotating and crushing
by applying enormous pressure on the face.
Large thrust forces while rotating and chipping with a
number of disc cutters mounted on the machine face.
The rock failure is actually by shear that occurs due to the
penetration of the cutter tip into the face.
The cutters are manufactured with hardened tool steel and
range in size of typically 300 to 500 mm in diameter.
The cutters are mounted on the cutterhead in a pattern and
number that will provide coverage over the entire face.
Design of disc cutters RPM, geometry, spacing, thrust level,
etc. depends upon the size of TBM. 17
18
19
CLASSIFICATION OF TBM
20
Contd..
There are three general types of TBMs suitable for rock
tunnelling including Open Gripper/Main Beam, Closed
Gripper/Shield, and Closed Segment Shield.
The open gripper/beam type of TBMs are best suited for stable to
friable rock with occasional fractured zones and controllable
groundwater inflows.
The closed shield type of TBMs are suitable for friable to unstable
rocks which cannot provide consistent support to the gripper
pressure.
The closed shield type of TBMs can either be advanced by
pushing against segment, or gripper.
Although these machines are classified as a closed type of
machine, they are not pressurized at the face of the machine thus
cannot handle high external groundwater pressure or water
inflows. 21
ADVANTAGES AND LIMITATION OF TBM
Fast rate of advance in producing a round, smooth &
un-shattered bores.
Over break is less than 5% which is much less than other
methods.
Eliminates the need of compressed air.
No risk of collapse of the excavation face.
Cost reduction for long tunnels (over 2 km).
22
Contd..
Limitations
High initial cost renders it expensive for short tunnels.
High cost for wear and tear when driving tunnels in hard
rock.
23
አመሰግናለሁ!!!!!!!!!!!
THANK YOU
24