Professional Documents
Culture Documents
Planet Earth
TUNNELING
Merits
Tunnels prove to be more economical than the open
cuts beyond certain depths.
Tunnels avoid disturbing and interfering with surface life
and traffic during construction
Tunnels prove to be better protected than bridges
during war times and bombing operations.
Tunnels prove to be cheaper for carrying water, sewage, gas,
etc as compared to their being taken in open cuts.
Tunnels do not occupy any space on the surface.
demerits of tunnels
The construction of tunnels is a costly process
It requires skilled labour and technical supervision.
Tunneling requires specialized and sophisticated equipment.
The excavation of tunnels takes long period.
D Shape Section
This is usually adopted in rocks, where unlined tunnels
are proposed to be constructed. Such a section has an
arch roof and straight vertical sides. The arch roof can
easily take vertical loads and transfer them to the
sides. The sides may be constructed in R.C.C (Roller
Compacted Concrete) in case of soft soils. This section
is suitable for subways and for navigation tunnels.
This section has a nearly flat invert, which provided
additional working floor space, helpful during driving
and a flat floor for moving equipment. These are the
principal advantages for this section and make it the
usually adopted section for highway and railway
tunnels (subways)
Fig 1: D- Shape
Fig 2: circular shape
Types of tunnels
Depending upon their use, the tunnels
may be classified into the following
groups;a) Traffic tunnels
b) Hydropower tunnels
c) Public utility tunnels
Classical methods
Mechanical drilling/cutting
Cut-and-cover
Immersed tunnels
Fig 4 showing steps involved in the conventional bottom-up construction. This is a type of the
Bored Tunneling
Bored tunneling by using a Tunnel Boring Machine
(TBM) is often used for excavating long tunnels. An
effective TMB method requires the selection of
appropriate equipment for different rock mass and
geological conditions. The TBM may be suitable for
excavating tunnels which contain competent rocks
that can provide adequate geological stability for
boring a long section tunnel without structural
support.
However, extremely hard rock can cause significant
wear of the TBM rock cutter and may slow down
the progress of the tunneling works to the point
where TBM becomes inefficient and uneconomical
and may take longer time than the drill-and-blast
tunneling method.
Environmental Disadvantages
of Cut and Cover Tunneling
More dust and noise impact may arise,
though these can be mitigated through
implementation of sufficient control
measures;
Temporary decks are often installed before
bulk excavation to minimize the associated
environment impacts;
Larger quantity of C&D (Construction and
Demolition) materials would be generated
from the excavation works, requiring
proper handling and disposal.
DIS- BENEFITS
Potential hazard
associated with
establishment of a
temporary magazine
site for overnight
storage of explosives
shall be addressed
through avoiding
populated areas in the
site selection process.
Environmental Benefits of
Bored Tunneling
Potential environmental impacts in terms of
noise, dust and visual on sensitive receives are
significantly reduced and are restricted to
those located near the launching and retrieval
shafts;
Compared with the cut-and-cover approach,
disturbance to local traffic and associated
environmental impacts would be much
reduced;
Compared with the cut-and-cover approach,
quantity of C&D materials generated would be
much reduced;
DIS - BENEFITS
As the method is
relatively slow,
duration of potential
environmental
impacts would be
longer than that of the
other methods.
Site Investigation
Selection of the alignment, cross section and
construction methods is influenced by the geological and
geotechnical conditions, as well as site constraints. Thus,
good knowledge of the expected geological conditions is
essential.
Geotechnical issues such as the soil or rock properties,
ground water regime, ground cover over the tunnel, the
presence of contaminants along the alignment, presence
of underground utilities and obstructions such as
boulders or buried objects and the presence of sensitive
surface facilities should be taken into consideration when
evaluating tunnel alignment.
Tunnel alignment is sometimes changed based on the
results of the geotechnical in order to minimize
construction cost or reduce risk.