Professional Documents
Culture Documents
ON
TECHNICAL EXAMINATION
OF
CHP PACKAGE
04/17/24
04/17/24
04/17/24
04/17/24
04/17/24
04/17/24
04/17/24
Major Areas/Items of CHP
Civil Works:
Track hopper & tunnel up to pent house
Foundation works
Structural Works:
Conveyor gallery & its supports/trestles
Technological structure
Conveyor belts
Idlers/Rollers
Skirt boards/chutes
04/17/24
Mechanical Works – Major equipments
Wagon tipplers
Trippers
04/17/24
04/17/24
04/17/24
04/17/24
Electrical Works
LT Cables
Belt protections
Lighting
04/17/24
Scope of work in the package
04/17/24
Use of unapproved make structural steel:
Structural steel sections without manufacturer stamp were
used by the contractor for fabrication work.
04/17/24
Width of conveyor walkway not as per the
specifications
04/17/24
A cable tray of size 150 mm X 75 mm was found
erected in the side walkway along with the supports
of the conveyor throughout gallery leaving the
clearance less by 75 mm than the stipulated figure.
This arrangement was found to be as per drawing
which is in deviation to the requirement of the
specification.
In order to accommodate the cable trays for control
cables of conveyor protection in the walkways, width
of the walkways should have been designed
accordingly so that a clear walkway of 800 mm could
have been maintained as per the specification
requirements.
As the deviation applies to the full length of the
conveyor system of the CHP, it had a substantial
cost implication.
04/17/24
Discrepancies in cable laying
The following were observed -
1. Cable 3C X 150 sq mm of length 1900 mtrs was laid
without cable tray.
2. Tagging of cables was not done.
3. Dressing of the cables was not done and cables were
hanging from the supports and the trays at many
places.
At location TR-2 trestle (400 mtrs) - earthing was not
done.
At location TR-28 TR 01 A/3 (40 mtrs) - earthing was
not done.
At location TR-18 to TR-8 (40 mtrs) - earthing not
done
04/17/24
Non-conformance to the drawing for pre-cast
slabs of cable trench
04/17/24
Non Conformance to the specification for
painting
04/17/24
Non-conformance to the specification for Dust
Suppression System on Stacker-Reclaimer
04/17/24
Reduction in scope of the work of road, road light
and drains
04/17/24
04/17/24