You are on page 1of 11

Calculating Float

Activity Start D A F E G B H C End Start Start D, A D F, E F G H C, B Precedence Duration 0 4 6 7 8 5 5 7 8 0

BEST VIEWED IN SLIDE SHOW MODE


1. What is the duration of the critical path? A) 32 B) 33 C) 31 D) 35 2. What is the float of activity B? A) 0 B) 16 C) 10 D) 15 3. What is the float of Activity F? A) 0 B) 5 C) 13 D) 7

qvive.biz

Calculating Float

BEST VIEWED IN SLIDE SHOW MODE

Start

End

ES

EF

X
LS F LF

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

qvive.biz

Calculating Float

Start

End

ES

EF

X
LS F LF

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

qvive.biz

Calculating Float

Start

End

ES

EF

X
LS F LF

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

qvive.biz

Calculating Float
0+6=6 0 6 6

13

13

18

Start

End

12

13

18

18

25

25

33

The latest Late Finish of the preceding activities determines Early Start ES
D

EF LF

X
F

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

qvive.biz

Calculating Float

13

13

18

Start

End

12

13

18

18

25

25

33

The latest Early Finish of the preceding activities determines Critical Path ES
D

EF

X
LS F LF

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

qvive.biz

Calculating Float

13

13

18

Start

A
0

F
0

End

12

13

18

18

25

25

33

G
0

H
0

C
0

Activities on the Critical Path have Zero Float ES


D

EF

X
LS F LF

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

A B A

qvive.biz

Calculating Float

6 6

6 6

13 13

13

18

Start
0

A
0

F
0

End

12

13 13

18 18

18 18

25 25

25 25

33 33

G
0

H
0

C
0

Activities on the Critical Path have LS=ES and LF=EF ES


D

EF

X
LS F LF

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

A B A

qvive.biz

Calculating Float

6 6

6 6

13 13

13

18

Start
0

A
0

F
0

B
28 15 33 33 5 = 28 28 13 = 15 18 18
7

End

0 1

4 5

4 5

12 13

13 13

18 18

25 25

25 25

33 33

D
1

E
1

G
0

H
0

C
0

The earliest Late Start of the following activities determines Late Finish ES
D

EF

X
LS F LF

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

A B D A

qvive.biz

Calculating Float

6 6

6 6

13 13

13

18

Start
0

A
0

F
0

B
28 15 33

End

0 1

4 5

4 5

12 13

13 13

18 18

18 18

25 25

25 25

33 33

D
1

E
1

G
0

H
0

C
0

What else can we learn from this example?


ES
D

EF

X
LS F LF

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

A B D A

qvive.biz

Calculating Float

6 6

6 6

13 13

13

18

Start
0

A
0

F
0

B
28 15 33

End

0 1

4 5

4 5

12 13

13 13

18 18

18 18

25 25

25 25

33 33

D
1

E
1

G
0

H
0

C
0

Project has increased RISK because of a Near-Critical Path


ES
D

EF

X
LS F LF

1. Precedence Diagram 2. Durations 3. Forward Pass (ES EF) 4. Critical Path 5. Float of Critical Path Activities 6. Backward Pass (LF LS)

Q 1 2 3

A B D A

qvive.biz

You might also like