Professional Documents
Culture Documents
Authorised By
SANTOSH BHARADWAJ REDDY
Email: help@matlabcodes.com
Engineeringpapers.blogspot.com
More Papers and Presentations available on above site
to be able to read and interpret the clues However, rules nearly always
correctly. The paper provides examples have exceptions! Look at figure 2. It is
of how do recognize these clues. It also another wave shape that exhibits voltage
gives guidelines for summarizing these notching, but this time the cause of the
results over a period of time. disturbance is very different. It was
caused by a faulty connection in a
Voltage Notching distribution transformer. Notice that the
notches in figure 2 are not at the same
Figure 1 shows a typical case of
angular location of the wave shape
voltage notching. This notching is caused
discussed previously in figure 1.
by the operation of a controlled rectifier
that commutates current from one
electrical phase to another during the
ordinary operation of the power
electronic drive. This action causes the
notching disturbance in the wave shape.
Generally these problems are solved by When the power quality
introducing inductance, such as with an engineers at the utility company first
isolation transformer or reactive choke, examined it, they were not sure at all.
into the circuit between the rest of the After a couple of days the loose
power source and the drive. In order to connection progressed further and the
recognize these clues we may decide to evidence was more convincing as shown
define a rule that declares that a wave in figure 3. Yet a day further and the
shape with notching is being affected by
transformer failed catastrophically due to If the disturbance in the voltage is
an internal loose lug connection. simultaneous with the zero crossing, then
this condition indicates the possibility of
a loose connection or open circuit. We
might modify this rule for a circuit with
lagging (leading) power factor to state
that the loose connection is indicated
Many times in power quality
when the voltage disturbance follows
monitoring, information about the cause
(leads) the zero crossing of the wave
of a voltage disturbance may be
shape.
determined from examination of current
Detecting Insulation Failures
in the circuit. In this case it was
particularly instructive. Figure 4 shows Let’s take a look at another
both the voltage and current wave shapes example. Figure 5 shows a wave shape
on the same plot. Notice that the voltage disturbance where the fault occurs at the
disturbance occurs at the time of the zero peak of the voltage. This particular
crossing of the current. This indicates disturbance was caused by a fault in an
that the current is tending to extinguish underground cable. Typically
itself (go to zero) at this zero crossing underground cable faults begin with
due to the loose circuit condition. In fact, small leakage currents and progress as
we can see that the current tends to be the insulation further deteriorates. This
zero for several degrees. Also, the process can take several days, as the
voltage is not disturbed at exactly its zero cable “cooks” the insulation until the
crossing because it is not in phase with failure is finally catastrophic. Our
the current due to a lagging power factor, experience at one utility shows us that
typical of an inductive load. this type of wave shape fault is very
typical with underground cable failures.
wave shape disturbance occurring at the
peak of the sine wave.
Capacitor Switching
Disturbances
perceptions of power quality. Most users between utilities and large customers
would prefer a summary that relates may well specify the number of voltage
BIBLIOGRAPHY
1. ELECTRICAL INDIA sept 2003,vol 43 no.12
Issn 0972-3277