Professional Documents
Culture Documents
Though fundamental network of PERT and CPM are identical, there are certain
differences in details as per the chart given below:
PERT CPM
1 a 2 b 3
Where “a” & “b” are activities, this can be represented by the
Numbers of nodes like a = (1,2) b = (2,3)
AON SYSTEM : Activities are represented by circles or nodes and arrows are
used to show only dependency relationship between the activity nodes.
a b c
GRAPHS OF AOA & AON
10 days 8 days
1 2 3
AOA For showing needed time
a,10 b,8
DUMMY ACTIVITIES
3 d 5
a h
f
b
1 2 7
g
c i
4 e 6
“b” is common immediate predecessor of both “d” and
“e”, “a” is an immediate predecessor of “d” alone,
and “c” is one of “e”. Hence “f” and “g” are dummy jobs
introduced to indicate precedence relationship
c, 20 days
a, 10 days 2 3 e, 10 days
1 CRITICAL PATH 6
b, 10 days 4 5 f, 30 days
d, 60 days
Longest path in net work 1-4-5-6 (100) & 1-2-3-6 ( 40)
CRASHING CPM NETWORKS
Time estimates are developed under conditions of normal Working and known
as normal time estimates. It does not take into consideration overtime working
or use of Abnormal resources for completion of an activity.
STEP NO.1 :
Determine the time - cost ratio for each activity in the network
Identify activities on the critical path and select that activity on the critical
path which has the smallest time-cost ratio and crash that activity to the
extent possible.
STEP NO.3:
Observe whether there is any change in the critical path i.e. any other path
becomes critical. If so, calculate time-cost ratio for the activities in the new
critical path.
STEP NO.4:
Repeat step no.2 and 3, till activities are crashed to reduce the project
duration to the desired time period.
COMMONLY USED NETWORK SYMBOLS:
SYMBOL MEANING
• Activity
• Dummy activity
• Event
B
A • Activity “a” must be
1 2 3 completed before activity “b”
A can begin
1 C
3 4 • Activities “a” and “b” can
occur concurrently, but both
2 must be completed before
B
activity “c” can begin
1 4 • Activites “a” and “b” must
A C be completed before
activities “c” and “d” can
3 begin, but “c” can begin
independently of “d” and
2 B D 5 vice versa.
• Activities “a” and “b” can
A D occur concurrently, but both
must be completed before
activity “d” can begin. Activity
C “e” can occur only after
activity “b” is completed.
E Activity “c” (dotted line with
B arrow head) is a dummy
activity which shows a
precedence relationship but
has a zero time duration.
TERMS USED IN NETWORK BASED SCHEDULING TECHNIQUES
L M DUMMY ACTIVITY
1 2 3
P
N 4 5
13 Latest start The latest that an activity can start, from the
(ls) beginning of the project, without causing a
delay in the completion of the project.
14 Latest finish The latest that an activity can finish, from the
(lf) beginning of the project, without causing a
delay in the completion of the project.
*********************
CPM – TIME ANALYSIS
MODE OF REPRESENTATION
I j
Ei Lt Ej Lj
- It follows that activities with zero slack value represent activities on critical path
Time
Total float
D Free float
Independent float
(PART – I)
D
4 5
B F
A Dummy
1 2
activity 7 H
8
C
3 6 G
E
The dummy activity 3-4 has been introduced here because “b” and
“c” both precede activity d and activity “c” precedes activity “e”.
(PART – II)
3
E
20 22 5
(12)
B 34 34
H
(8) F
(18) (4)
1 A 2 C 4 7 J 8
0 0 (12) 12 12 (4) 16 16 38 38 (6) 44 44
G
(5) I
D
(3) 6 (9)
21 29
FORMULA : te = to +4tm+tp
6
to = Optimistic Time tm = Most likely Time tp = Pessimistic Time
1-4 4+4X19+28 = 18
6
1-5 5 + 4X11+17 = 11
6
2-3 3+3X9+27 = 11
6
2-6 3+4X6+15 = 7
6
3-6 2+4x5+14 = 6
6
4-6 3+4x4+7 = 7
6
5-7 1+4x4+7 = 4
6
5-8 2+4x5+14 = 6
6
7-8 2+4x5+8 = 5
6
Step No.2 DRAW PERT NETWORK DIAGRAM
5-7
5 7
(4) 7-8
11 30 5-8 15 34
(5)
1-5 (6)
8
(11)
39 39
1 1-4 4 4-6 6 6-8
0 0 18 18 25 25
(18) (7) (14)
(7)
2-3 3
2
5 8 16 19
(11)
CRITICAL PATH : 1-4 4-6 6-8
18 + 7 + 14 = 39 weeks
(B) Mean time for each activity expected time = te
Standard deviation for each activity = tp-to
ACTIVITY STANDARD DEVIATION (WEEKS) Z 6
1-2 8-2 = 1 7-8 8-2 = 1
6 6
*1-4 28-4 = 4 *4-6 15-3 =2
6 2
1-5 17-5 = 2
6
2-3 27-3 = 6
6
2-6 15-3 = 2
6
3-6 14-2 = 2
6
5-7 7-1 = 1
6
5-8 14-2 = 2
6
*5-8 30-6 = 4
6
(C) To determine std. deviation for critical path :
cp = 1
2
+ 2
2
+ 3
2
= 6 weeks
(D) Calculation of slacks for events :
(E) To calculate total float, free float and independent float for each activity
A 2000
B 3000
C 1000
D 1000
E 500
F 250
STEP 2 : DRAW NETWORK DIAGRAM
4
A
2
C
( ) Normal Time
(6) (3) F 4 Crash Time
3 (8)
B 3
(4) D (8)
E 6
(14)
NORMAL:
CRITICAL PATH B D F
DURATION 4 + 8 + 8 = 20 weeks
COST Rs. 36,000/-
CRASH:
CRITICAL PATH A C F
4 + 2 + 4 = 10 weeks
COST Rs. 54,000/-
B D F
3 + 3 + 4 = 10 weeks
Step : 3 Normal Cost Rs.36,000
Current
Activities
Project Critical Activities
which can Cost of Crashing Cost Total Cost Time
Completi Path (s) Selected
be Crashed
on Time
B-D-F B,D,F 3000, 1000 F
20 250 36,250 19
250
19 B-D-F B,D,F ------ “ ------ F 250 36,500 18
B-D-F B,D,F 3000,1000,250 F 250
18 37250 17
B-E B,E 3000,500 E 500
B-D-F B,D,F 3000,1000,250 F 250
17 38,000 16
B-E B,E 3000,500 E 500
B-D-F B,D 3000,1000 D 1000
16 39,500 15
B-E B,E 3000,500 E 500
B-D-F B,D 3000,1000 D 1000
15 41,000 14
B-E B,E 3000,500 E 500
B-D-F B,D 3000,1000 D 1000
14 42,500 13
B-E B,E 3000,500 E 500
B-D-F B,D 3000,1000 D 1000
13 44,000 12
B-E B,E 3000,500 E 500
B-D-F B,D 3000,1000 D 1000
12 45,500 11
B-E B,E 3000,500 E 500
B-D-F B 3000 - 500 46,000 10
11
B-E B,E 3000,500 E Cannot be crashed further
SUMMARY:
Overhead
Cost @ Total Cost
Project Time Direct Cost
Rs.1,000/- (Rs.)
per week
10 46,000 10,000 56,000
11 45,500 11,000 56,500
1-2 (A) 20
1-3 (B) 25
1-4 (C) 30
2-4 (D) 10
3-4 (E) 15
4-5 (F) 40
STEP : 2 NETWORK DIAGRAM
2
D 3 ( ) Normal Time
6
A
C 10
(5)
F
1 Crash Time
1 (15) 4 5
B 5 6 (2)
(8) E
(10)
3
NORMAL:
CRITICAL PATH B E F
DURATION 8 + 10 + 2 = 20 days
CRASH:
CRITICAL PATH B E F
5 + 6 + 1 = 12 days (Minimum)
STEP : 3 Project Crashing
Project Activities
Critical Cost of Activity
Completion which can be Cost Time
Path(s) crashing selected
Time (Days) crashed
L 20 B-E-F B,E,F 25,15,40 E 15 19
L-1 19 B-E-F B,E,F 25,15,40 E 15 18
L-2 18 B-E-F B,E,F 25,15,40 E 15 17
L-3 17 B-E-F B,E,F 25,15,40 E 15
16
C-F C,F 30,40 C 30
L-4 16 B-E-F B,F 25,40 B 25
C-F C,F 30,40 C 30 15
A-D-F A,D,F 20,10,40 D 10
L-5 15 A-D-F A,D,F 20,10,40 D 10
C-F C,F 30,40 C 30 14
B-E-F B,F 25,40 B 25
L-6 14 A-D-F A,F 20,40 A 20
C-F C,F 30,40 C 30 13
B-E-F B,F 25,40 B 25
L-7 13 A-D-F A,F 20,40 A 20
C-F C,F 30,40 C 30 12
B-E-F F 40 F 40
L-8 12 A-D-F A 20 A 20 11
C-F - - - -
B-E-F - - - -
(No further Crashing)
SUMMARY
Project Time Crashing Cost Overhead Total Cost
(Rs.) Cost @
Rs.60/- day
12 385 720 1105
11 405 660 1065
Optimal length schedule for each job
A 6 days
B 5 days
C 10 days
D 3 days
E 6 days
F 1 day