EPCIC Process Flow
EPCIC Process Flow
PRE BID
ENGINEERING
PROCUREMENT
CONSTRUCTION
INSTALLATION
COMMISSIONING
CONTRACTORs Business Development Department invites New Clients to Pre-Qualify CONTRACTOR or to solicits for the coming tender from the existing Clients.
ENGINEERING
PROCUREMENT
CONSTRUCTION
INSTALLATION
COMMISSIONING
Business Development shall forward the Pre-Qualification request or Intent To Bid from Client to the Proposal Department. Proposal Department shall be the coordinator for the Pre-Qualification or Bidding of new project until contract been awarded by the Client
CONTRACTOR C L I E N T
Dept 1
PROPOSAL
Dept 2
PRE-QUALIFICATION
INTENT TO BID
(From CLIENT)
GET APPROVAL TO BID FROM BUSINES REVIEW COMMITTEE ASSIGN BID LEADER
BID SUBMISSION
TECHNICAL CLARIFICATION
PREPARE PROJECT MANAGEMENT TEAM (PMT) ORGANIZATION CHART, MANPOWER & EQUIPMENT LOADING
(Prepared by PMT & Human Resource)
TECHNO-COMMERCIAL
(If needed)
LETTER OF AWARD
(From CLIENT)
ENGINEERING
PROCUREMENT
CONSTRUCTION
INSTALLATION
COMMISSIONING
PROVISION OF ENGINEERING To work on the Conceptual, Front End and Detail engineering
DESIGN AND PREPARE PROJECT SPECIFIC PROCEDURE (PSP) PROVIDE TECHNICAL SUPPORT TO PROJECT MANAGEMENT TEAM
ENGINEERING
PROCUREMENT PROCUREMENT
CONSTRUCTION
INSTALLATION
COMMISSIONING
PROVISION OF PROCUREMENT
Purchasing of project materials and equipments are being centralized and organized by its Procurement Department.
In some cases, Client also purchased the tag items and delivered to CONTRACTOR within the agreed timing. This requirement shall be specified by Client during the Bidding.
PURCHASE REQUISITION
(from Engineering)
CUSTOM CLEARANCE ON DUTY & TAX DELIVER ITEM TO STORE INSPECT ITEMS AGAINST PURCHASE ORDER RELEASE OF GOODS INCOMING INSPECTION REPORT
START FABRICATION
(by Vendor)
INSPECTION
(by our Staff or 3rd party surveyor)
ENGINEERING
PROCUREMENT
CONSTRUCTION
INSTALLATION
COMMISSIONING
PROVISION OF CONSTRUCTION
Construction work of one project is handled by specific Project Management Team (PMT).
RECEIVE MATERIAL
INSPECTION ON ACCURACY
INSPECT MATERIAL
PAINTING
RELEASE GOODS INCOMING INSPECTION REPORT RELEASE MATERIAL TO PROJECT MANAGEMENT TEAM CHECK ERECTION SEQUENCE COATING (If needed)
CUTTING
ASSEMBLY
INSPECT DIMENSION
ON YARD COMMISSIONING
SHOP PRIME
WELDING
MARKING
INSPEC DIMENSION
ENGINEERING
PROCUREMENT
CONSTRUCTION
INSTALLATION
COMMISSIONING
PROVISION OF INSTALLATION To work on the logistic,marine fleets, installation window based on sea condition and the permit needed for the offshore installation
Derrick/Lay Barge
Utility Workboat/DSV
ENGINEERING
PROCUREMENT
CONSTRUCTION
INSTALLATION
COMMISSIONING
PROVISION OF COMMISSIONING
Commissioning Department (PMT) shall perform the testing and the pre-commissioning work onshore, hook up and commissioning activities offshore
FINISH PRE-COMMISSIONING
SET UP TEMPORARY FACILITIES COMPLETE HANDOVER OF THE TERMINAL TO CLIENT STARTS PRE-COMMISSIONING
End