You are on page 1of 1

MOHD ZAIERI ENGINEERING SDN BHD Issue No.: 1 Issued Date : 02-JUNE-2004 Section No.

QC PROCESS FLOW CHART


PAGE NO: 10 1 OF Revision No.: 1 1

10.0

QC PROCESS FLOW CHART 10.1 Process Description for Gas Piping (Reticulation) JKKP (DOSH) and Client Specifications Requirements (PTI )

Material Receiving/ Incoming Material Piping Pipe Fittings Structural for Pipe supports Welding Consumables

1st Initial Quality Check (IQC)


Stocks 2nd IQC for On/Off site Fabrication On/Off Site Installation

REFER TO SOP

Fabrication/Installation according to Standard Operating Procedure (SOP) Inspection and Test Plan (ITP)
PASS/OK

FAIL

Commissioning Application for PTO from DOSH Final Quality Check (FQC)

Rectify

Submission of Approved Documentation