TESTING AND COMMISSIONING PROCEDURE

AHU (AIR HANDLING UNIT) AHU system must be in operation before the test Program the start time for the supply fan observe and monitor the start time. Ensure that the "on" status appeared correctly. Program the start time for the supply fan observe and monitor the start time. Ensure that the "off" status appeared correctly. Verify that the start and stop time response to the actual operation of the equipment Set the equipment in manual mode operation and verify that it shows in manual to the workstation and ensure that it can start and stop manually . Set it in auto mode operation and verify that it shows auto in workstation and ensure that it can controlled by the workstation. Verify that the air flow switch indicates flow and clean when the equipment is on if not check the device installed or the operation of the equipment . Ensure that the sensor for the supply air temperature provides an accurate reading of temperature set point to the workstation. Ensure that the sensor for the return air temperature provides an accurate reading of temperature to the workstation and verify that it can control the opening of control valve in proportion to the cooling demand. Ensure that the air static pressure transmitter provides an accurate reading to the workstation , Air static pressure is based upon on the temperature set point and speed of variable frequency drive (VFD). Check the duct smoke detector using magnetic device to verify that it will indicate alarm in the workstation and ensure that it will shut down the AHU and provide signal Fire Alarm. Control the fresh air damper and the return air damper as open & close in the workstation and verify the actual response of the damper if it followed the command of the program. Ensure that the carbon dioxide sensor provides a reading not exceeding of 700ppm .Verify that the alarm will indicate in the workstation whenever the carbon dioxide exceeds from its maximum ppm. Ensure that the damper is open based on the CO2 level.

chiller plant Program the start time observe and monitor the start time. Verify that the "on" status appeared correctly to the workstation. Program the start time observe and monitor the start time. Verify that the "off" status appeared correctly to the workstation. Verify the start time and stop time response to the actual operation of the equipment. Ensure that the water flow switch indicates flow when the equipment is on if not check the device installed or the operation of the equipment. Ensure that the well temperature sensor provides an accurate reading of chilled water supply temperature set point to the workstation. Ensure that the well temperature sensor provides an accurate reading of chilled water return temperature set point to the workstation. Ensure that the well temperature sensor provides an accurate reading of condenser water supply &return temperature to the workstation. Ensure that the flow meter sensor provides an accurate reading of water flow to the workstation. Verify that a trip alarm will indicate in the workstation whenever a short circuit happened check the fault immediately to normalize the system.

chilled and condenser water mains Ensure that the water differential pressure switch provides an accurate reading of chilled water differential pressure measure on the workstation. Ensure that the water differential pressure switch provides an accurate reading of condenser water differential pressure measure on the workstation. Ensure that the water flow sensor provides an accurate reading of chilled water supply and return flow on the workstation. Ensure that the water flow sensor provides an accurate reading of condenser water supply and return flow on the workstation. Ensure that well temperature sensor provides an accurate reading of chilled water supply and return temperature to the workstation. Ensure that well temperature sensor provides an accurate reading of condenser water supply and return temperature to the workstation.

FAN COIL UNIT (FCU) Program the fan start time ,observed and monitor the start time . Verify that the on status appeared correctly to the workstation. Program the fan stop time observe and monitor the stop time. Verify that the off status appeared correctly to the workstation. Verify that the start and stop time response to the actual operation of the equipment. Verify that the chilled water valve controlled as open when the equipment is on and when it is off the chilled water valve controlled as close. Set the equipment in manual mode operation and verify that it shows in manual to the workstation and ensure that it can start and stopped manually .Set it in auto mode operation and verify that it shows auto in the workstation and ensure that it can controlled by workstation. Verify that a trip alarm will indicate in the workstation whenever a short circuit happened check the fault immediately to normalize the system.

You might also like