Task

Start Date Duration End Date


Planning Meeting
12/29/1997
1 ########
Develop Questionnaire
12/30/1997
11 1/9/1998
Print and Mail Questionnaire
1/13/1998
9 1/21/1998
Receive Responses
1/16/1998
15 1/30/1998
Data Entry
1/16/1998
18 2/2/1998
Data Analysis
2/3/1998
4 2/6/1998
Write Report
2/9/1998
12 2/20/1998
Distribute Draft Report
2/23/1998
1 2/23/1998
Solicit Comments
2/24/1998
4 2/27/1998
Finalize Report
3/2/1998
5 3/6/1998
Distribute to Board
3/9/1998
1 3/9/1998
Board Meeting
3/17/1998
1 3/17/1998

Planning Meeting
Develop Questionnaire
Print and Mail Questionnaire
Receive Responses
Data Entry
Data Analysis
Write Report
Distribute Draft Report
Solicit Comments
Finalize Report
Distribute to Board
Board Meeting

12/29 1/5

Project Schedule

1/5

1/12 1/19 1/26

2/2

2/9

2/16 2/23

3/2

3/9

3/16