Project Schedule: Task Start Date Duration End Date
Project Schedule: Task Start Date Duration End Date
and Mail Questionnaire 1/13 9 1/21 Receive Responses 1/16 15 1/30 Data Entry 1/16 18 2/2 Data Analysis 2/3 4 2/6 Write Report 2/9 12 2/20 Distribute Draft Report 2/23 1 2/23 Solicit Comments 2/24 4 2/27 Finalize Report 3/2 5 3/6 Distribute to Board 3/9 1 3/9 Board Meeting 3/17 1 3/17
Planning Meeting Develop Questionnaire Print and Mail Questionnaire Receive Responses Data Entry Data Analysis Write Report Distribute Draft Report Solicit Comments Finalize Report Distribute to Board Board Meeting
Project Schedule
12/29 1/5
2/2
2/9
2/16 2/23
3/2
3/9
3/16