Professional Documents
Culture Documents
Construction of Concrete Pavement in Packages II-A, II-B and II-C (World Bank Project) at Kanpur - A Case Study
NH-2, Highway Section from Km.393 (Sikandra) to Km.115 (Khaga) Totaling a length of 190 Kms
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
SRINAGAR DELHI
SILCHAR PORBANDAR
1. The length of Golden Quadrilateral > Delhi-KolkataChennai-MumbaiDelhi = Km. 5,846 The length of Eastwest-North-South Corridor = Km. 7,300
KOLKATTA
2.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
INTRODUCTION
NATIONAL HIGHWAYS DEVELOPMENT PROJECT (NHDP), the largest infrastructure development project undertaken in independent India, envisages development of 14,000 Km of world class 4/6 lane highways connecting all corners of the country. It includes:
The Golden Quadrilateral: Comprising the metros DelhiKolkata-Chennai-Mumbai-Delhi circuit of 5,846 Km length. Project Cost: over Rs. 25,050 crore. North-South & East-West Corridors : Involving a distance of 7,300 km and costing over Rs. 30,000 crore, connecting Kashmir with Kanyakumari and Silchar with Porbandar.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
The project Road is part of NH-2 (Delhi Calcutta), which forms part of the Golden quadrilateral
The designer has designed the rigid pavement for a design life of 30 years. The PCA method (The Portland Cement Association) has been used for thickness design of new rigid pavement.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Package II-A
MORT&H and Addendum 79.80 Km. 8.75 m 320-330 mm 4.5m C/C 450 mm, 36 mm dia (MS bar), 300 mm C/C 450 mm, 12 mm deformed, 350 mm C/C 125 Micron Thick Polythene Sheet 300 m C/C or at end of days work (Now eliminated) Flexural Strength of beam - 4 Mpa (min), Target Mean strength 5MPa
Package II-B
MORT&H and Addendum 19.86 Km. 8.75 m 330 mm 4.5m C/C 450 mm, 36 mm dia (MS bar), 300 mm C/C 600mm, 12mm deformed, 500 mm C/C 125 Micron Thick Polythene Sheet 300 m C/C or at end of days work Flexural Strength of beam - 4 Mpa (min), Target Mean strength 5MPa
Package IIC
MORT&H and Addendum 93.87 Km. 8.75 m 330 mm 4.5m C/C 450 mm, 36 mm dia (MS bar), 300 mm C/C 450mm, 12mm deformed, 350 mm C/C 125 Micron Thick Polythene Sheet 300 m C/C or at end of days work (Now eliminated) Flexural Strength of beam - 4 Mpa (min), Target Mean strength 5MPa
Specified Strength
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Item Slip Form Paver with Automatic Dowel bar & Tie Bar inserter Kerbs Batch Plant
Package II-A Wirtgen SP 850 (2 Nos.) Slip Form - Separate Steelfield 250 m3 / hr
Package II-B Wirtgen SP 850 (1 Nos.) Slip Form Separate Stetter (2 Nos.) each of 120 m3 / hr
Package IIC
Gomaco GHP 2800 Slip Form Separate Stetter each of 120 m3 /hr
Tippers
Average Production Rate
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
75 : 25 828 Kg
56 : 44
2300 ml
185 ml
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Cement Content Water Content Water Cement Ratio Coarse Aggregate (20 mm) Coarse Aggregate (10 mm) Coarse Aggregate Ratio (20/12.5) Fine Aggregate CA / FA Ratio Admixture : Plasticizer SP 430 A1 (PQC) Air Entrainer: AEA
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Key Points
1. During initial trials excessive bleeding, resulted in development of shrinkage cracks. It was controlled by introduction of Air Entraining Agent. Fresh concrete deposited over the filler board due to incorrect installation at construction joints and got in touch with old concrete face. This resulted in spalling of concrete at joints. Correct depth of joint filler board is to be maintained. Exposure of construction joints to local traffic before filling of joint sealant, got partially damaged at transverse edges. Any type of traffic should not be allowed before filling of sealant in all type of joints.
2.
3.
4.
Brush finish done in some reach reflected low durability after opening to traffic. Tine finish is substituted for better durability of roughness.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
CC Shoulder
4500
4500
Longitudinal Joint
3 mm wide
Transverse Joint
8-10 mm wide
4500
Median Side
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
4500
(@300 mm C/C)
Tie Bar (600 mm long), Tor Steel
4500
4500
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
A.
Inflow of Material 1. 2. 3. 4. 5.
Material
Selection of Quarry / Beds / Physical Properties Production Pattern of Stone Crushing Plants - Jaws; Cone; Impact; Roller. Feed to Crusher/Production/Storage Production Pattern Inflow to Construction Camps/Sites
B.
C.
Finished Product / Services 1. 2. Method of Delivery from Stack Yards to Plant & Site Execution Activities related to Concrete Mix
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Paving screed 9M wide by 0.35M thick. Paving speed 0.5 to 1.5M per min.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
The loaded dumpers to have the priority of movement. Good maintenance of Service Roads and Sprinkling of water
Bucket door to be properly locked during transportation to avoid leakage of slurry. Mirrors to be installed on left & right of the vehicle. Proper lights during night operation.
The cover need to protect the bucket from sun and dust on the way back to the batching plant.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
The Surface of Drainage Layer (Sub-base for rigid pavement) to remain moist before laying of DLC (the base-course layer of rigid pavement).
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Moisture loss to be minimized during haulage and laying of Dry Lean Concrete.
Uninterrupted running of DLC Paver minimize cold joints and surface cracks. Minimum 7days curing by gunny bags / Hessian cloth and sprinkling of water.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
752
DLC DL
DLC
Open Vibration Close Vibration
Vibration starts from lower end, covering entire width in each pass with offsets
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
DLC COMPACTION
Starting from lower edge towards upper edge Vibration in forward direction with plain pass in reverse. Controlled speed in forward and reverse movements. No stoppage of roller on the green Bed
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Any foreign material / loose aggregates to be cleaned before spreading the sheet. Wrinkles are avoided during placing Longitudinal overlaps to start from higher end of DLC towards lower end Sheet to be secured by umbrella cap GI Pins
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Paving unit to be cleaned free of any remaining concrete of previous day operation. All Grade and Steering sensors to be installed correctly All inbuilt vibrator needles to be checked for their function All reservoirs for water, fuel, hydraulic oils etc. to be sufficient for days work.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
PQC Laying
Unloading Concrete
Use of higher capacity dumpers to
minimize movement on Ploythene Sheets. Dumpers equipped with acoustic warning signals. Caution on Super elevated portions to avoid overturning. Dumping in two rows by Dumpers to facilitate even distribution by bucket spreader. Care taken not to damage the Polythene Sheet during movement of equipments
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Inbuilt Concrete Vibrators in PQC Paver are regularly checked for vibration
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Dowel Bar Magazine & conveyor Dowel Bars to be cut correct in length and alignment and properly fitted in PVC Caps. All slots of trolley conveyor to be
checked for proper functioning Sufficient stock of Dowel Bars for days work
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Making Texture on finished surface by TCM Texturing brush to be kept clean. Increased slump results in slurry deposition. Time gap is required before doing texturing which should be avoided Textures to be created normal to the edges of slab
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Correct vibration by inbuilt vibrators and smooth finish by masons behind Paver avoid the collapse of vertical edges.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
The shape and size of tent is so designed to avoid damage to the pavement It is preferable to have a length of tent protection for a three hours production length of slab by paver.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Initial cut upto 1/3rd depth to start just when the concrete has hardened, preferably after 6 to 8 hours of concrete laying. The generated dust during cutting is to be removed / washed away immediately by pressure jets.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Widening of Joints
Widening of transverse Joints up to 8 mm The generated dust during widening is to be removed / washed away immediately by pressure jets.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Joint Preparation
Cleaning of Joints with Air pressure if needed, thin brush is required to clean the vertical faces
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Joint Preparation
Top surface to be cleaned before application of Protection Tape for adequate adhesion. Sealant Primer not to spill out on protection tape and to be applied uniformly.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Joint Filling
The Concavity in the sealant material is accurately maintained by use of grooving tools.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Expanded closed cell 25-30 mm. d/3 Polyethylene Foam Backer Rod 3-4 mm. saw cut in green concrete
d/3
TRANSVERSE JOINT
PQC PQC
LONGITUDINAL JOINT
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
1.
2.
3.
4. 5. 6.
Use of Homogeneous Materials as specified for various layers. e.g. Sub Grade, Drainage Layer, Sub Base, Base Course and Bituminous layers for flexible pavement. Use of Well graded and Homogeneous Concrete Mixes for Rigid Pavements. Control in Compaction and thickness of individual layers. Control of levels and surface regularities. Proper Roads Signage with design speed. Plying within the specified design speed.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Longitudinal Length and Maximum 9 Nos. in 75M Longitudinal Length. 7mm : Maximum 2Nos. in 300M length and Maximum 1 No. in 75M length.
Transverse
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
PVC Caps
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Slump Testing
Slump Cone to be removed correctly to maintain accuracy
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
First stage of kerb casting in progress. Second stage of kerb laying to be done after initial hardening of first stage.
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
JOINTS IN KERB
Joint cutting in kerb is done when the concrete has just hardened
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
Construction of Concrete Pavement in Packages II-A, II-B & II-C of NHAI (World Bank Project) at Kanpur
3.
4. 5.
6.