Written dimensions on these drawings shall have precedence over scaled dimensions.

Contractor shall verify and be responsible for all dimensions and conditions on the job. OB+Architecture Inc. must be notified immediately in writing of any variation from the dimensions and conditions shown on these drawings. Field verify all conditions prior to laying out or fabricating associated work. Bring to the architect's attention any deviation from designed conditions and field conditions prior to ordering
materials and installing work, and cooperate with architect to modify such conditions at no additional cost to the owner, architect or architect's consultants. Shop details must be submitted to the architect's office and reviewed by the architect prior to ordering materials, fabrication and delivery to the job site, unless otherwise provided for under the specific contractual agreement between the architect and client. OB+Architecture Inc. expressly reserves its common law copyright and other

HVAC KEY NOTES :

M1: PROVIDE AND INSTALL NEW STORM PROOF ALUMINUM OUTDOOR AIR LOUVER (MIN. 55% FREE
AREA) WITH AN ALUMINUM BIRD SCREEN. SIZE OF LOUVER, ELEVATION, AND CFM INDICATED ON
PLAN. PRIME FOR PAINTING BY GC. SELECTION OF COLOR BY OWNER.

M2: PROVIDE AND INSTALL NEW RUSKIN OR EQUAL GALVANIZED STEEL 2 POSITION OPEN CLOSED
MOTOR OPERATED DAMPER. 120 VAC. SIZE TO MATCH LOUVER OPENING AS NOTED ON PLAN.
INTERLOCK BOTH DAMPERS, EF-1, AND EF-2 WITH WALL SWITCH AS SHOWN ON PLAN.

M3: PROVIDE WALL SWITCH LABELED FAN AND T'STAT LABELED AC-3 ADJACENT TO EACH OTHER.
property rights in these documents. These documents are not to be reproduced, changed, or copied in any form or manner whatsoever, nor are they to be assigned to a third party without first obtaining the written permission and written consent of OB+Architecture Inc. In the event of unauthorized use of these documents by a third party, the third party shall hold OB+Architecture Inc. harmless and agrees to remunerate OB+Architecture Inc.

PROVIDE ADJACENT PERMANENT WEATHER PROOF WALL SIGNAGE TO READ " DO NOT OPERATE
VENTILATION FANS AND AIR CONDITIONING AT THE SAME TIME." NOTE: INTERLOCK BOTH MOTOR
OPERATED DAMPERS, EF-1, AND EF-2 WITH WALL SWITCH.

M4: PROVIDE AND INSTALL SOLVENT WELDED SCHEDULE 40 PVC CONDENSATE PIPE WITH A 4" P
TRAP AND CLEANOUT AT AC UNIT AND ROUTE TO DRYWELL. PIPE SIZE IS NOTED.

M5: PROVIDE AND INSTALL A 24" DIA. AND 24" HIGH DRYWELL WITH PEA GRAVEL FILL ACCEPTABLE
TO THE AHJ.

M6: PROVIDE EXPANDED METAL GALVANIZED STEEL SCREEN OVER OPENING.

M7: MIN. 4" THICK CONCRETE PAD BELOW AC UNIT AND DUCTWORK. COORDINATE SIZES WITH
ACTUAL EQUIPMENT PURCHASED.

M8: ROUTE CONDENSATE PIPING FROM AHU DOWN IN WALL, OUT WALL AND BELOW GRADE, AND
TERMINATE IN DRYWELL.

M9: INSTALL 4" DRYER EXHAUST CAP WITH DAMPER AND WITHOUT SCREEN. PREFAB LISTED
DRYER WALL CAP FOR USE WITH RESIDENTIAL ELECTRIC CLOTHES DRYER INSTALLED APPROX. .
9'4" TO TOP OF CAP. ROUTE 4" GALV. STEEL ELECTRIC CLOTHES DRYER VENT DUCT (WITH NO
PROTRUDING FASTENERS AND WITH OVERLAPPED JOINTS THAT PREVENT LINT BUILD UP FROM
CLOTHES DRYER TO WALL CAP) FROM RESIDENTIAL ELECTRIC CLOTHES DRYER TO WALL CAP.
MAX. LENGTH OF STRAIGHT DUCT SHALL BE 15' WITH MAX. OF 2 ELBOWS TO MEET. SECTION 504
OF 2004 FMC.

M10: ROUTE REF. TUBES FROM INDOOR TO OUTDOOR UNITS IN 4" PVC CONDUIT BELOW GRADE.
issued: ADVANCE REVIEW 21 JULY 2008

revised:

GENERAL MECHANICAL NOTES :


1. THE DRAWINGS DEPICT THE REQUIRED HVAC SCOPE OF WORK. ALL WORK IS ASSOCIATED
WITH NEW CONSTRUCTION.

2. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE 2004 FLORIDA MECHANICAL AND
BUILDING CODES; NFPA 90A AND 101; ASHRAE; SMACNA; NEC; AND AUTHORITY HAVING
JURISDICTION (AHJ).

3. CONTRACTOR SHALL OBTAIN THE NECESSARY PERMITS AND PAY THE ASSOCIATED FEES.

4. COORDINATE ALL WORK WITH THE OWNER AND ALL TRADES. WORK SHOWN IS DIAGRAMMATIC.
PROVIDE ADDITIONAL FITTINGS, SUPPORTS, MATERIAL AND LABOR TO THE APPROVAL OF THE AHJ
AT NO ADDITIONAL COST. INFORM ARCHITECT AND ENGINEER OF DISCREPANCIES AND WAIT FOR
WRITTEN DIRECTIVE PRIOR TO PROCEEDING.

5. ALL NEW RIGID AND SQUARE/ RECTANGULAR SUPPLY AIR, RETURN AIR, AND TRANSFER AIR
DUCTWORK INSIDE THE BUILDING SHALL BE GALV. STEEL EXTERNALLY WRAPPED WITH 2" THICK
R-6 FIBERGLASS INSULATION WITH GLASS FAB AND MASTIC JOINTS. PROVIDE COST DEDUCT CENTRAL
FLORIDA
ALTERNATE FOR SAME DUCTWORK WITH 1.5" THICK ANTIMICROBIAL FIBERGLASS DUCTBOARD
WITH A MIN. R VALUE OF R-6.0. ALL NEW RIGID EXHAUST AND OUTDOOR AIR DUCTWORK SHALL BE
G-90 GALVANIZED STEEL. ALL DUCTBOARD AND INSULATION JOINTS SHALL BE MADE WITH GLASS
FAB AND APPROVED MASTIC. ALL NEW SUPPLY AIR AND RETURN AIR DUCTWORK LOCATED
OUTSIDE THE BUILDING SHALL BE DOUBLE WALL G-90 GALVANIZED STEEL WITH A PAINT GRIP
FINISH AND WITH 2" THICK R-8 INSTALLED FIBERGLASS DUCT LINER. PAINT THE EXTERIOR OF
THE DUCTWORK WHICH IS EXPOSED WITH 2 COATS OF MARINE BASED PAINT. THE TOP COAT
COLOR SHALL BE SELECTED BY THE OWNER OR ARCHITECT. THE PAINTGRIP DUCT SHALL BE
ATTACHED TO PT LUMBER AND WITHIN 5" OF THE EQUIPMENT SLAB. THE DUCTWORK AND THE PT
LUMBER SHALL BE RIGIDLY ATTACHED TO THE SLAB TO MEET 2004 FLORIDA BUILDING CODE WIND
LOAD REQS. FABRICATE AND SUPPORT ALL DUCTWORK IN ACCORDANCE WITH SMACNA. DUCT
DIMENSIONS REFERENCED ARE CLEAR INSIDE DIMENSIONS. ALL NEW FLEXIBLE SUPPLY AIR AND
RETURN AIR DUCTWORK SHALL BE CONSTRUCTED TO SMACNA STANDARDS WITH AN INTEGRAL
VAPOR BARRIER AND A MIN. R VALUE OF R-6.0. ALL DUCTWORK, MASTICS, ETC. SHALL HAVE MAX.
25 FLAME SPREAD AND MAX. 50 SMOKE DEVELOPED RATINGS. PROVIDE DOUBLE THICKNESS
ANIMAL
TURNING VANES IN ALL 90 DEGREE ELBOWS. PROVIDE VENTFABRICS 25/ 50 CANVAS DUCT
CONNECTORS AT DUCT CONNECTION BETWEEN AIR MOVING EQUIP. AND GALV. STEEL
DUCTWORK. DUCTWORK IS SHOWN DIAGRAMMATICALLY. ADDITIONAL FITTINGS AND OFFSETS
WILL BE REQUIRED. CONTRACTOR MAY SUBSTITUTE DUCT SIZES WITH EQUIVALENT AREAS.
HOSPITAL
6. AIR DISTRIBUTION TEST AND BALANCE SHALL BE DONE IN ACCORDANCE WITH NEBB OR AABC
address: 1201 ALAFAYA TRAIL
REQUIREMENTS BY INDIVIDUALS FAMILIAR WITH THE PROCEDURES AND PRACTICES INVOLVED.
BALANCE TO WITHIN 5% OF SPECIFIED CAPACITIES AND HAVE REPORT ON JOB SITE PRIOR TO
APPROPRIATE INSPECTIONS. OVIEDO, FLORIDA

7. PROVIDE THE OWNER 3 COPIES OF ALL EQUIPMENT GUARANTEES, WARRANTEES, PARTS LISTS, 32765
ETC. SCHEDULE A MINIMUM OF 3 HOURS AT THE PROJECT SITE TO FAMILIARIZE THE TENANT'S
DESIGNATED REPS. WITH THE WAYS IN WHICH THE SYSTEMS ARE OPERATED AND MAINTAINED.
PROVIDE PRODUCT SUBMITTALS AND SHOP DRAWINGS FOR REVIEW PRIOR TO COMMENCEMENT
OF WORK. project
number: 2007-12
8. HEIGHTS OF ALL THERMOSTATS AND SWITCHES SHALL CONFORM TO ADA REQS.

9. PROVIDE PROPER ACCESS FOR ALL MECHANICAL EQUIPMENT COMPONENTS REQUIRING


SERVICE, ACCESS, INSPECTION, AND USE IN ACCORDANCE WITH THE MANUFACTURER'S
RECOMMENDATIONS, FMC, AND AHJ.
for such use in an amount equal to the original fee for the original documents, plus legal fees, court costs, collection fees and other costs.

10. APPLY 2.2" THICK 3/4 POUND DENSITY FIBERGLASS INSULATION WITH AN FSK VAPOR BARRIER
AND GLASS FAB AND MASTIC TO THE TOP OF THE NEW SUPPLY AIR DIFFUSERS AND REGISTERS.
MECHANICAL ENGINEER
11. SEE ELECTRICAL PLANS FOR LOCATIONS OF WP 115 V CONVENIENCE OUTLETS PER FMC AND A. PETER TANKEL, P.E.
NEC WITHIN 25' OF HVAC EQUIPMENT.
702 DENTON ROAD
12. ALL OUTDOOR AIR COMPLIES WITH ASHRAE STANDARD 62 AND THE 2004 FMC. SEE WINTER PARK, FL 32792
VENTILATION TABLE ON PLANS. NOTE: ALL WATER CLOSETS, MOP SINKS, AND SHOWER HEADS PE 41231
ARE EXHAUSTED AT MIN. 50 CFM PER FIXTURE.

13. SUBMIT DUCTWORK SHOP DRAWINGS AND PRODUCT SUBMITTALS FOR REVIEW PRIOR TO
COMMENCEMENT OF WORK. COORDINATE ALL DUCT ROUTING WITH STRUCTURE AND OTHER
TRADES. SUBSTITUTE DUCT SIZES WITH DUCTS OF EQUAL INSIDE AREA WHERE REQUIRED TO
AVOID CONFLICTS.
title:

14. ALL CONDENSATE PIPING SHALL BE S-40 PVC WITH SOLVENT WELDED FITTINGS AND
SUPPORTED PER THE 2004 FMC. ALL INTERIOR CONDENSATE PIPING SHALL BE INSULATED WITH
HVAC
1/2" THICK ARMAFLEX. ABBREVIATIONS
15. ONLY AC-2 HAS A CFM CAPACITY EXCEEDING 2000 CFM REQUIRING A DUCT SMOKE DETECTOR.
AC-2 HAS BEEN SCHEDULED TO BE FURNISHED WITH A SUPPLY AIR UNIT MOUNTED SMOKE
& LEGENDS
DETECTOR. ELECTRICAL TRADE SHALL PROVIDE RELAYS, WIRING, CONDUIT, ETC, TO CONNECT drawn:
JLP
SMOKE DETECTOR TO BUILDING'S FIRE ALARM CONTROL PANEL. INSTALLATION, ANNUNCIATION,
TESTING, ETC. SHALL COMPLY WITH NFPA 72 AND 90A, 2004 FMC, AND AHJ. reviewed:
OB / RG
date:
21 JULY 2008
lman:
PS-M1.1
sheet setup:
MOJA-HVAC
sheet
number:

M1.1