You are on page 1of 26

Dicipline No :

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
CIVIL ( AIRSIDE )

Contract job No :
CCU-0084

Rev. :

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

SUMMARY

ITEM
NO.

WORK ITEM/ DESCRIPTION

RUNWAY

II

III

IV

9,597,797,928.52

959,779.79

A. TAXIWAY ( EXISTING )

116,162,637.67

11,616.26

B. TAXIWAY ( NEW )

691,085,214.77

69,108.52

A. APRON ( EXISTING )

836,145,010.32

83,614.50

B. APRON ( NEW )

4,084,422,442.94

408,442.24

TAX 10 %

1,532,561,323.42

153,256.13

16,858,174,557.64

1,685,817.46

TOTAL

Note :

Estimated exchange rates USD 1,00 = Rp. 10,000.00

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
CIVIL ( AIRSIDE )

WORK ITEM/ DESCRIPTION

RUNWAY

1
2
3
4
5

Tack Coat
Prime Coat
Asphalt Concrete
ATB
Aggregate Base Course ( CBR = 80 % )

QUANTITIES

97,500.00
19,500.00
292.50
292.50
2,925.00

Rev. :

UNIT

liter
liter
m3
m3
m3

RATE ( Rp )

75,810.00
7,875.00
2,135,804.88
519.49
488,166.00

RATE ( $ )

7.58
0.79
213.58
0.05
48.82

Sub Total I
II

A. TAXIWAY ( EXISTING )

1
2

Asphalt Concrete
ATB

54.38
54.38

m3
m3

2,135,804.88
519.49

213.58
0.05

Sub Total II

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

7,391,475,000.00
153,562,500.00
624,722,927.40
151,951.12
1,427,885,550.00

739,147.50
15,356.25
62,472.29
15.20
142,788.56

9,597,797,928.52

959,779.79

116,134,390.35
28,247.32

11,613.44
2.82

116,162,637.67

11,616.26

164,190,000.15
39,935.87
112,583,283.75
324,071,482.50
12,107,812.50
7,770,525.00
70,322,175.00

16,419.00
3.99
11,258.33
32,407.15
1,210.78
777.05
7,032.22

691,085,214.77

69,108.52

B. TAXIWAY ( NEW )
1
2
3
4
5
6
7

Asphalt Concrete
ATB
Aggregate Base Course ( CBR = 80 %)
Sub Base Course ( CBR = 35 % )
Prime Coat
Tack Coat
Soil Excavation
Sub Total III

76.88
76.88
230.63
922.50
1,537.50
102.50
1,153.13

m3
m3
m3
m3
liter
liter
m3

2,135,804.88
519.49
488,166.00
351,297.00
7,875.00
75,810.00
60,984.00

213.58
0.05
48.82
35.13
0.79
7.58
6.10

Dicipline No :

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
CIVIL ( AIRSIDE )

Contract job No :
CCU-0084

ITEM
NO.

WORK ITEM/ DESCRIPTION

III

A. APRON ( EXISTING )

1
2
3

Asphalt Concrete
ATB
Tack Coat

QUANTITIES

228.92
228.92
4,578.45

Rev. :

UNIT

m3
m3
liter

RATE ( Rp )

2,135,804.88
519.49
75,810.00

RATE ( $ )

213.58
0.05
7.58

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

488,933,792.64
118,923.18
347,092,294.50

48,893.38
11.89
34,709.23

836,145,010.32

83,614.50

838,410,205.64
203,926.19
595,184,310.00
61,826,625.00
574,888,689.90
1,654,819,648.20
359,089,038.00

83,841.02
20.39
59,518.43
6,182.66
57,488.87
165,481.96
35,908.90

Sub Total V

4,084,422,442.94

408,442.24

TAX 10 %

1,532,561,323.42

153,256.13

16,858,174,557.64

1,685,817.46

Sub Total IV
B. APRON ( NEW )
1
2
3
4
5
6
7

IV

Ashpalt Concrete
ATB
Tack Coat
Prime Coat
Aggregate Base Course ( CBR = 80 % )
Sub Base Course ( CBR = 35 % )
Soil Excavation

392.55
392.55
7,851.00
7,851.00
1,177.65
4,710.60
5,888.25

m3
m3
liter
liter
m3
m3
m3

2,135,804.88
519.49
75,810.00
7,875.00
488,166.00
351,297.00
60,984.00

213.58
0.05
7.58
0.79
48.82
35.13
6.10

TOTAL

Note :

Estimated exchange rates USD 1,00 = Rp. 10,000.00

Dicipline No :

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
CIVIL ( LANDSIDE )

Contract job No :
CCU-0084

Rev. :

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

SUMMARY

ITEM
NO.

WORK ITEM/ DESCRIPTION

ROAD CONSTRUCTION

PREPARATION

500,000,000.00

50,000.00

MATERIALS (INCLUDE CONSTRUCTION COST)

100,936,768.54

10,093.68

II

DRAINAGE WORK

5,477,417,641.45

547,741.76

III

TAX 10 %

607,881,641.00

60,788.16

6,686,698,050.99

668,669.81

TOTAL

Note :

Estimated exchange rates USD 1,00 = Rp. 10,000.00

Dicipline No :

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
CIVIL ( LANDSIDE )

Contract job No :
CCU-0084

ITEM
NO.

WORK ITEM/ DESCRIPTION

ROAD CONSTRUCTION

PREPARATION

1
2

Tools Mobilisation
Direction Keet & Others

QUANTITIES

1.00
1.00

Rev. :

UNIT

ls
ls

RATE ( Rp )

400,000,000.00
100,000,000.00

RATE ( $ )

40,000.00
10,000.00

Sub Total I
B

MATERIALS ( INCLUDE CONSTRUCTION COST )

1
2
3
4
5
6

Soil Excavation
Prime Coat ( include construction cost )
Tack Coat ( include construction cost )
Asphalt Concrete
Crushed Aggregate Base Course ( CBR 80 % )
Sub Base course ( CBR min 35 % )

102.48
256.20
256.20
12.81
51.24
38.43

m3
liter
liter
m3
m3
m3

50,820.00
7,875.00
75,810.00
2,135,804.88
721,086.18
259,706.52

5.08
0.79
7.58
213.58
72.11
25.97

Sub Total II

II

DRAINAGE WORK

1
2
3
4
5

Soil Excavation
Compacted Sand t = 150
Lean Concrete t = 50
Reinforcement ( concrete )
Steel Grating

267.30
649.68
216.56
3,230.76
1.75

m3
m3
m3
m3
m2

50,820.00
364,596.00
135,900.00
1,608,764.57
264,000.00

5.08
36.46
13.59
160.88
26.40

Sub Total III


III

TAX 10 %
TOTAL

Note :

Estimated exchange rates USD 1,00 = Rp. 10,000.00

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

400,000,000.00
100,000,000.00

40,000.00
10,000.00

500,000,000.00

50,000.00

5,208,033.60
2,017,575.00
19,422,522.00
27,359,660.51
36,948,455.86
9,980,521.56

520.80
201.76
1,942.25
2,735.97
3,694.85
998.05

100,936,768.54

10,093.68

13,584,186.00
236,870,729.28
29,430,504.00
5,197,532,222.17
462,000.00

1,358.42
23,687.07
2,943.05
519,753.22
46.20

5,477,879,641.45

547,787.96

607,881,641.00

60,788.16

6,686,698,050.99

668,669.81

Dicipline No :

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
ELECTRICAL WORKS ( AIRSIDE )

Contract job No :
CCU-0084

Rev. :

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

SUMMARY

ITEM
NO.

WORK ITEM/ DESCRIPTION

APRON FLOOD LIGHT

152,120,000.00

15,212.00

II

TAXIWAY AND APRON EDGE LIGHT

181,333,000.00

18,133.30

III

TESTING AND COMMISSIONING

33,345,300.00

3,334.53

366,798,300.00

36,679.83

TOTAL

Note :

Estimated exchange rates USD 1,00 = Rp. 10,000.00


All material base on Franco Jakarta

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

WORK ITEM/ DESCRIPTION

APRON FLOOD LIGHT

1
2
3

Power Cable NYFGBY 4 x 6 mm2 for Flood Light


NYY 3 x 2.5 mm
Grounding System
BC Cable 1 x 50 mm2
Cooper Rod 1 inchi 3 m
Accessories Grounding System
Flood Lighting 2 x 1000 watt HPS + Pole 11 m + Distribution Panel
Flood Lighting Installation
Lightning Arrester ( EF )
Installation
Power Cable NYFGBY 4 x 6 mm2 for Flood Light
BC Cable 1 x 50 mm2

4
5
6
7

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
ELECTRICAL WORKS ( AIRSIDE )

II

TAXIWAY AND APRON EDGE LIGHT

1
2

Corel Single Intensity Manual Contral ( Blue and Redlens )


COREL Battery Charger lb way

QUANTITIES

Rev. :

UNIT

150.00
100.00

m
m

150.00
20.00
1.00
2.00
2.00
2.00

m
set
set
set
unit
set

150.00
150.00

m
m

16.00
1.00

unit
unit

RATE ( Rp )

RATE ( $ )

TESTING AND COMMISSIONING

1.00

lot

Estimated exchange rates USD 1,00 = Rp. 10,000.00


All material base on Franco Jakarta

AMOUNT ( Rp )

AMOUNT ( $ )

2.10
0.67

3,150,000.00
670,000.00

315.00
67.00

20,000.00
400,000.00
5,000,000.00
40,000,000.00
11,000,000.00
15,000,000.00

2.00
40.00
500.00
4,000.00
1,100.00
1,500.00

3,000,000.00
8,000,000.00
5,000,000.00
80,000,000.00
22,000,000.00
30,000,000.00

300.00
800.00
500.00
8,000.00
2,200.00
3,000.00

1,000.00
1,000.00

0.10
0.10

150,000.00
150,000.00

15.00
15.00

8,273,000.00
48,965,000.00

827.30
4,896.50

132,368,000.00
48,965,000.00

13,236.80
4,896.50

333,453,000.00

33,345.30

33,345,300.00

3,334.53

366,798,300.00

36,679.83

33,345,300.00

3,334.53
TOTAL

Note :

21,000.00
6,700.00

Sub Total
III

Page No:
R1

Dicipline No :

Doc. No :
900-EST-2121

ENGINEERING ESTIMATE
OF
BUILDING WORKS

Contract job No :
CCU-0084

Rev. :

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

SUMMARY

ITEM
NO.

WORK ITEM/ DESCRIPTION


TERMINAL BUILDING

STRUCTURE WORKS

313,285,625.70

31,328.56

ARCHITECTURE WORKS

1,086,239,934.30

108,623.99

MECHANICAL WORKS

189,681,250.00

18,968.13

ELECTRICAL WORKS

54,980,500.00

5,498.05

285,430,119.00

28,543.01

1,269,118,707.60

126,911.87

FIRE FIGHTING AND RESCUE BUILDING


1

STRUCTURE WORKS

ARCHITECTURE WORKS

MECHANICAL WORKS

30,868,750.00

3,086.88

ELECTRICAL WORKS

59,633,750.00

5,963.38

3,289,238,636.60

328,923.86

TOTAL

Note :

Estimated exchange rates USD 1.00 = Rp 10,000 ,-

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
STRUCTURAL WORKS

WORK ITEM/ DESCRIPTION

QUANTITIES

Rev. :

UNIT

RATE ( Rp )

RATE ( $ )

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

TERMINAL BUILDING
I
1
2
3
4

Preparation Works
Marking ( setting out )
Excavation foundation
Sand fill
Lean concrete t : 50 mm

78.00
8.70
1.21
12.10

m1
m3
m3
m3

69,000.00
51,000.00
396,600.00
981,000.00

6.90
5.10
39.66
98.10

5,382,000.00
443,700.00
479,886.00
11,870,100.00

538.20
44.37
47.99
1,187.01

II
1
2
3
4
5

Formworks
Footing Type F1
Pedestal Type C
Pedestal Type B
Tie Beam
Slab

10.00
3.60
0.54
6.60
15.98

m2
m2
m2
m2
m2

1,194,000.00
1,194,000.00
1,194,000.00
1,194,000.00
1,194,000.00

119.40
119.40
119.40
119.40
119.40

11,940,000.00
4,298,400.00
644,760.00
7,880,400.00
19,080,120.00

1,194.00
429.84
64.48
788.04
1,908.01

III
1
2
3
4
5
6
7

Reinforcement Works ( U-39 )


Footing Type F1
Pedestal Type C
Pedestal Type B
Tie Beam
Slab ( Wiremesh M6-150)
Anchor for Footing M16
Anchor M16

358.80
63.81
24.50
345.54
163.67
21.12
3.46

kg
kg
kg
kg
m2
kg
kg

21,900.00
21,900.00
21,900.00
21,900.00
81,000.00
21,900.00
21,900.00

2.19
2.19
2.19
2.19
8.10
2.19
2.19

7,857,720.00
1,397,439.00
536,550.00
7,567,326.00
13,257,270.00
462,528.00
75,774.00

785.77
139.74
53.66
756.73
1,325.73
46.25
7.58

IV
1
2
3
4
5

Concrete Works ( K.250 )


Footing Type F1
Pedestal Type C
Pedestal Type B
Tie Beam
Slab

2.50
0.26
0.03
2.93
16.60

m3
m3
m3
m3
m3

1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00

117.00
117.00
117.00
117.00
117.00

2,925,000.00
304,200.00
35,100.00
3,428,100.00
19,422,000.00

292.50
30.42
3.51
342.81
1,942.20

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

VI
1
2
3
4
5
6
7
8

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
STRUCTURAL WORKS

WORK ITEM/ DESCRIPTION

Steel Structure Works


Column WF 250.125.6.9
Rafter WF 250.125.6.9
Ring Beam WF 250.125.6.9
Purlin C 150.65.20.2,3
Joint Plate
Sag Rod dia. 12mm
Sreel Angle 80.80.8
Steel pipe dia. 3"

QUANTITIES

1,065.60
1,628.00
1,124.80
2,298.45
388.34
28.04
65.04
1,009.47

Rev. :

UNIT

kg
kg
kg
kg
kg
kg
kg
kg

RATE ( Rp )

RATE ( $ )

25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00

2.55
2.55
2.55
2.55
2.55
2.55
2.55
2.55
TOTAL

Note : Estimated exchange rates USD 1.00 = Rp 10,000 ,-

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

27,172,800.00
41,514,000.00
28,682,400.00
58,610,475.00
9,902,670.00
715,020.00
1,658,520.00
25,741,367.70

2,717.28
4,151.40
2,868.24
5,861.05
990.27
71.50
165.85
2,574.14

313,285,625.70

31,328.56

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS

WORK ITEM/ DESCRIPTION

QUANTITIES

Rev. :

UNIT

RATE ( Rp )

RATE ( $ )

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

TERMINAL BUILDING
I
1
2

Demolition Works
Wall Cladding & frame
Toilet

55.25
10.80

m2
m2

6,900.00
71,550.00

0.69
7.16

381,225.00
772,740.00

38.12
77.27

II
1
2

Extension Terminal Building


Floor (ceramic tile 300x300mm)
Floor (ceramic tile 200x200mm)

90.05
6.25

m2
m2

204,000.00
192,900.00

20.40
19.29

18,370,200.00
1,205,625.00

1,837.02
120.56

3
4
5
6
7
8

Wall (ceramic tile 200x250mm)


Wall (corrugated metal sheet, teakwood formica finish & frame)
Wall (corrugated metal sheet, GRC board panel & frame)
Wall partition (teakwood with formica finish & frame)
Wall partition (GRC board panel & frame)
Wall partition (GRC board panel, teakwood frmica finish & frame)

21.60
80.42
9.50
12.36
25.28
5.78

m2
m2
m2
m2
m2
m2

195,000.00
1,105,500.00
635,490.00
1,290,000.00
486,000.00
888,000.00

19.50
110.55
63.55
129.00
48.60
88.80

4,212,000.00
88,904,310.00
6,037,155.00
15,944,400.00
12,286,080.00
5,132,640.00

421.20
8,890.43
603.72
1,594.44
1,228.61
513.26

Ceiling ( teakwood formica finish & wood frame )

96.30

m2

240,000.00

24.00

23,112,000.00

2,311.20

10
11
12

Glass door with aluminium frame (D1)


Wooden door with aluminium frame (D2)
Wooden door with aluminium frame (D3)

3.00
3.00
2.00

unit
unit
unit

6,952,800.00
5,563,950.00
4,610,655.00

695.28
556.40
461.07

20,858,400.00
16,691,850.00
9,221,310.00

2,085.84
1,669.19
922.13

13
14
15
16
17
18

Fixed glass window with aluminium frame (W2)


Fixed glass window with aluminium frame (W3)
Fixed glass window with aluminium frame (W4)
Fixed glass window with aluminium frame (W5)
Fixed glass window with aluminium frame (W6)
Fixed glass window with aluminium frame (W7)

1.00
1.00
2.00
1.00
0.00
1.00

unit
unit
unit
unit
unit
unit

5,679,360.00
6,205,680.00
3,818,880.00
12,252,240.00
1,958,400.00
391,680.00

567.94
620.57
381.89
1,225.22
195.84
39.17

5,679,360.00
6,205,680.00
7,637,760.00
12,252,240.00
0.00
391,680.00

567.94
620.57
763.78
1,225.22
0.00
39.17

19

100.80

m2

2,200,200.00

220.02

221,780,160.00

22,178.02

20
21

Main Roof (corrugated metal sheet, insulation, aluminium foil


& chicken wire mesh)
Metal ridge capping
Metal fascia (h : 600mm)

10.50
31.20

m'
m'

163,500.00
249,000.00

16.35
24.90

1,716,750.00
7,768,800.00

171.68
776.88

22
23

Canopy Roof
Metal fascia (h : 300mm)

45.13
13.00

m2
m'

467,700.00
124,500.00

46.77
12.45

21,104,962.50
1,618,500.00

2,110.50
161.85

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS

WORK ITEM/ DESCRIPTION

QUANTITIES

Rev. :

UNIT

RATE ( Rp )

RATE ( $ )

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

24
24.1
24.2
24.3
24.5

VIP toilet
Closet
Washtafel + mirror
Jet shower
Floo drain

1.00
1.00
1.00
2.00

unit
unit
unit
unit

6,475,500.00
5,450,400.00
1,320,000.00
450,000.00

647.55
545.04
132.00
45.00

6,475,500.00
5,450,400.00
1,320,000.00
900,000.00

647.55
545.04
132.00
90.00

25
25.1
25.2

Janitor
Faucet
Floor drain

1.00
1.00

unit
unit

345,000.00
450,000.00

34.50
45.00

345,000.00
450,000.00

34.50
45.00

III
1
2

New Terminal Building


Floor (ceramic tile 300x300mm)
Floor (ceramic tile 200x200mm)

54.00
10.00

m2
m2

204,000.00
192,900.00

20.40
19.29

11,016,000.00
1,929,000.00

1,101.60
192.90

3
4
5
6
7

Wall (ceramic tile 200x250mm)


Wall (corrugated metal sheet, teakwood formica finish & frame)
Wall (corrugated metal sheet, GRC board panel & frame)
Wall partition (GRC board panel & frame)
Wall partition (GRC board panel, teakwood frmica finish & frame)

35.40
90.48
20.52
4.77
16.06

m2
m2
m2
m2
m2

195,000.00
1,105,500.00
635,490.00
486,000.00
888,000.00

19.50
110.55
63.55
48.60
88.80

6,903,000.00
100,025,640.00
13,040,254.80
2,318,220.00
14,261,280.00

690.30
10,002.56
1,304.03
231.82
1,426.13

Ceiling ( teakwood formica finish & wood frame )

64.00

m2

882,000.00

88.20

56,448,000.00

5,644.80

9
10
11

Glass door with aluminium frame (D1)


Wooden door with aluminium frame (D3)
Wooden door with aluminium frame (D4)

2.00
1.00
2.00

unit
unit
unit

6,952,800.00
4,610,655.00
3,616,065.00

695.28
461.07
361.61

13,905,600.00
4,610,655.00
7,232,130.00

1,390.56
461.07
723.21

12
13
14

Fixed glass window with aluminium frame (W1)


Fixed glass window with aluminium frame (W2)
Fixed glass window with aluminium frame (W7)

0.00
5.00
2.00

unit
unit
unit

3,889,080.00
5,783,760.00
391,680.00

388.91
578.38
39.17

0.00
28,918,800.00
783,360.00

0.00
2,891.88
78.34

15

101.60

m2

2,200,200.00

220.02

223,540,320.00

22,354.03

16
17

Roof (corrugated metal sheet, insulation, aluminium foil &


chicken wire mesh)
Metal ridge capping
Metal fascia (h : 600mm)

10.00
40.30

m'
m'

163,500.00
249,000.00

16.35
24.90

1,635,000.00
10,034,700.00

163.50
1,003.47

18
19

Canopy Roof
Metal fascia (h : 300mm)

60.96
24.19

m2
m'

467,700.00
124,500.00

46.77
12.45

28,510,992.00
3,011,655.00

2,851.10
301.17

Dicipline No :

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS

Contract job No :
CCU-0084

ITEM
NO.

WORK ITEM/ DESCRIPTION

QUANTITIES

UNIT

Rev. :

RATE ( Rp )

RATE ( $ )

Page No:
R1

AMOUNT ( Rp )

AMOUNT ( $ )

20
20.1
20.2
20.3
20.4
20.5

Toilet
Closet
Washtafel + mirror
Jet shower
Urinal
Floor drain

2.00
2.00
2.00
1.00
5.00

unit
unit
unit
unit
unit

6,475,500.00
5,450,400.00
1,320,000.00
4,351,800.00
450,000.00

647.55
545.04
132.00
435.18
45.00

12,951,000.00
10,900,800.00
2,640,000.00
4,351,800.00
2,250,000.00

1,295.10
1,090.08
264.00
435.18
225.00

21
21.1
21.2

Janitor
Faucet
Floor drain

1.00
1.00

unit
unit

345,000.00
450,000.00

34.50
45.00

345,000.00
450,000.00

34.50
45.00

1,086,239,934.30

108,623.99

TOTAL

Note :

Estimated exchange rates USD 1.00 = Rp 10,000 ,-

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.
I

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
MECHANICAL WORKS

Rev. :
R1

WORK ITEM/ DESCRIPTION

QUANTITIES

UNIT

RATE ( Rp )

RATE ( $ )

AMOUNT ( Rp )

Page No:
10

AMOUNT ( $ )

AIR CONDITION AND VENTILATION


Supply Main Equipment Complete with Ref Pipe
Hauger and Accessories

IV - 1
Type : Wall Mounted Split
Cap : 18000 btuh

1.00

ser

5,150,000.00

515.00

5,150,000.00

515.00

IV - 2
Type : Wall Mounted Split
Cap : 18000 btuh

1.00

set

5,150,000.00

515.00

5,150,000.00

515.00

IV - 3
Type : Wall Mounted Split
Cap : 18000 btuh

1.00

set

5,150,000.00

515.00

5,150,000.00

515.00

IV - 4
Type : Wall Mounted Split
Cap : 18000 btuh

1.00

set

5,150,000.00

515.00

5,150,000.00

515.00

IV - 5
Type : Wall Mounted Split
Cap : 18000 btuh

1.00

set

5,150,000.00

515.00

5,150,000.00

515.00

IV - 6
Type : Wall Mounted Split
Cap : 18000 btuh

1.00

set

5,150,000.00

515.00

5,150,000.00

515.00

II

PLUMBING

Installation Clean Water Complete With Accessories


PVC Pipe Class AW
2 " CW
1 " CW

20.00
10.00

m
m

3.00
1.75

600,000.00
175,000.00

60.00
17.50

30,000.00
17,500.00

Dicipline No :

Contract job No :
CCU-0084

III

Rev. :
R1

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
MECHANICAL WORKS

WORK ITEM/ DESCRIPTION

QUANTITIES

UNIT

RATE ( Rp )

RATE ( $ )

AMOUNT ( Rp )

Page No:
10

AMOUNT ( $ )

3/4 " CW

15.00

15,000.00

1.50

225,000.00

22.50

Installation Sewage Water Complete With Accessories


PVC Pipe Class AW
4 " SW
3 " SW
3 " WW

75.00
50.00
25.00

m
m
m

45,000.00
37,500.00
37,500.00

4.50
3.75
3.75

3,375,000.00
1,875,000.00
937,500.00

337.50
187.50
93.75

Installation Vent Pipe


PVC Pipe Class AW
2"V

15.00

30,000.00

3.00

450,000.00

45.00

2.00

lot

4,000,000.00

400.00

8,000,000.00

800.00

50.00
2.00
2.00
6.00
4.00

m
unit
unit
unit
pcs

150,000.00
1,200,000.00
2,400,000.00
1,900,000.00
950,000.00

15.00
120.00
240.00
190.00
95.00

7,500,000.00
2,400,000.00
4,800,000.00
11,400,000.00
3,800,000.00

750.00
240.00
480.00
1,140.00
380.00

1.00

unit

96,000,000.00

9,600.00

96,000,000.00

9,600.00

17,243,750.00

1,724.38

189,681,250.00

18,968.13

Installation of Septic Tank


Dimention 2 m x 3 m x 2 m
FIRE FIGHTING
Installation Fire Pipe
4 " BSP SCH 40
OHB ( Hydrant Box )
Pillar Hydrant
Fire Extinghuisher Cap 5 kg
Gate Valve 4 "

IV

MISCELLANEOUS WORK

Supply and Install Baggage Coveyor Electric Power, W : 900 mm,


L : 8000 mm, H : 600 mm.

TAX 10 %
TOTAL

Note :

Estimated exchange rates USD 1,00 = Rp. 10,000.00

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
ELECTRICAL WORKS ( LANDSIDE )

Rev. :
R1

WORK ITEM/ DESCRIPTION

QUANTITIES

UNIT

RATE ( Rp )

RATE ( $ )

AMOUNT ( Rp )

Page No:
11

AMOUNT ( $ )

INSTALLATION NEW TERMINAL & BOAT RECEPTION ROOM


1
2
3

4
5
6
7

8
9

Fluorescent Lamp, 2 x 36 watt 220 Volt


Socket Outlet Single Phase
Cable NYY 3 x 2.5 mm2
Cable NYY 4 x 4 mm2
NYFGBY 4 x 25 mm2
Panel Distribution 80 x 60 x 30 cm
Switch 2 Pole
Switch 1 Pole
Incandenscent Lamp 60 watt Down Light, E 27
Accessories for Installations
Cable Gland
Tape Insulation
Screw
Cable Marker
Junction Box
Cable Trench Size 1
Installation
Cable NYY 3 x 2.5 mm2
Cable NYY 4 x 4 mm2
NYFGBY 4 x 25 mm2
Lamps and Socket Outlet

16.00
7.00
325.00
35.00
80.00
1.00
3.00
9.00
8.00
1.00

set
set
m
m
m
set
set
set
set
lot

370,000.00
41,000.00
6,100.00
16,700.00
57,500.00
22,500,000.00
54,500.00
39,500.00
125,000.00
10,000,000.00

37.00
4.10
0.61
1.67
5.75
2,250.00
5.45
3.95
12.50
1,000.00

5,920,000.00
287,000.00
1,982,500.00
584,500.00
4,600,000.00
22,500,000.00
163,500.00
355,500.00
1,000,000.00
10,000,000.00

592.00
28.70
198.25
58.45
460.00
2,250.00
16.35
35.55
100.00
1,000.00

150.00

36,000.00

3.60

5,400,000.00

540.00

325.00
35.00
80.00
31.00

m
m
m
set

1,000.00
1,000.00
2,500.00
52,500.00

0.10
0.10
0.25
5.25

325,000.00
35,000.00
200,000.00
1,627,500.00

32.50
3.50
20.00
162.75

54,980,500.00

5,498.05

TOTAL

Note :

Estimated exchange rates USD 1,00 = Rp. 10,000.00


All material base on Franco Jakarta

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900-EST-2121

ENGINEERING ESTIMATE
OF
STRUCTURAL WORKS

Rev. :
R1

WORK ITEM/ DESCRIPTION

QUANTITIES

UNIT

RATE ( Rp )

RATE ( $ )

AMOUNT ( Rp )

Page No:
12

AMOUNT ( $ )

FIRE FIGHTING & RESCUE BUILDING


I
1
2
3
4
5

Preparation Works
Marking ( setting out )
Excavation foundation
Back filling
Sand fill
Lean concrete t : 50 mm

74.00
13.92
10.76
1.72
0.72

m1
m3
m3
m3
m3

69,000.00
51,000.00
30,000.00
396,600.00
981,000.00

6.90
5.10
3.00
39.66
98.10

5,106,000.00
709,920.00
322,800.00
682,152.00
706,320.00

510.60
70.99
32.28
68.22
70.63

II
1
2
3
4
5

Formworks
Footing Type F1
Pedestal section C
Edge of slab
Pedestal section A
Pedestal section D

14.40
4.32
16.00
0.18
0.18

m2
m2
m2
m2
m2

1,194,000.00
1,194,000.00
1,194,000.00
1,194,000.00
1,194,000.00

119.40
119.40
119.40
119.40
119.40

17,193,600.00
5,158,080.00
19,104,000.00
214,920.00
214,920.00

1,719.36
515.81
1,910.40
21.49
21.49

III
1
2
3
4
5
6
7
8
9

Reinforcement Works ( U-39 )


Footing Type F1
Pedestal section C
Pedestal section A
Pedestal section D
Tie beam section D
Edge of slab
Slab ( Wiremesh M6-150)
Anchor for Footing M16 L : 350mm
Anchor for Footing M16 L : 300mm

468.00
126.76
8.40
6.80
59.52
323.00
249.29
26.51
1.89

kg
kg
kg
kg
kg
kg
m2
kg
kg

21,900.00
21,900.00
21,900.00
21,900.00
21,900.00
21,900.00
81,000.00
21,900.00
21,900.00

2.19
2.19
2.19
2.19
2.19
2.19
8.10
2.19
2.19

10,249,200.00
2,776,044.00
183,960.00
148,920.00
1,303,488.00
7,073,700.00
20,192,490.00
580,569.00
41,391.00

1,024.92
277.60
18.40
14.89
130.35
707.37
2,019.25
58.06
4.14

IV
1
2
3
4
5
6

Concrete Works ( K.250 )


Footing Type F1
Pedestal Type C
Tie beam section A
Tie beam section D
Pedestal A & D
Slab

3.00
0.31
3.92
1.45
0.02
23.63

m3
m3
m3
m3
m3
m3

1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00

117.00
117.00
117.00
117.00
117.00
117.00

3,510,000.00
362,700.00
4,586,400.00
1,696,500.00
23,400.00
27,647,100.00

351.00
36.27
458.64
169.65
2.34
2,764.71

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

VI
1
2
3
4
5
6
7
8
9
10

Doc. No :
900-EST-2121

ENGINEERING ESTIMATE
OF
STRUCTURAL WORKS

Rev. :
R1

WORK ITEM/ DESCRIPTION

Steel Structure Works


Column WF 250.125.6.9
Rafter WF 250.125.6.9
Ring Beam WF 200.100.5,5
Column C150.65.20.2,3
Horizontal wall frame C.150.65.20.2,3
Purlin C.150.65.20.3,2
Sreel Angle 80.80.6
Sag rod dia .12mm
Wind bracing with turn buckle dia. 13mm
Stiffner

QUANTITIES

1,758.24
2,628.48
766.80
117.70
592.35
35.17
169.68
35.17
48.00
615.15

UNIT

kg
kg
kg
kg
kg
kg
kg
kg
kg
kg

RATE ( Rp )

RATE ( $ )

25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00

2.55
2.55
2.55
2.55
2.55
2.55
2.55
2.55
2.55
2.55
Total

Note :

Estimated exchange rates USD 1.00 = Rp 10,000 ,-

AMOUNT ( Rp )

Page No:
12

AMOUNT ( $ )

44,835,120.00
67,026,240.00
19,553,400.00
3,001,350.00
15,104,925.00
896,835.00
4,326,840.00
896,835.00
1,224,000.00
15,686,325.00

4,483.51
6,702.62
1,955.34
300.14
1,510.49
89.68
432.68
89.68
122.40
1,568.63

285,430,119.00

28,543.01

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900-EST-2121

ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS

Rev. :
R1

WORK ITEM/ DESCRIPTION

QUANTITIES

UNIT

RATE ( Rp )

RATE ( $ )

AMOUNT ( Rp )

Page No:
13

AMOUNT ( $ )

FIRE FIGHTING AND RESCUE BUILDING


I
1
2
3

Floor works
Floor hardener ( 5kg/ m2 )
Floor (ceramic tile 200x200mm)
Floor (ceramic tile 300x300mm)

187.20
12.00
84.80

m2
m2
m2

150,000.00
192,900.00
204,000.00

15.00
19.29
20.40

28,080,000.00
2,314,800.00
17,299,200.00

2,808.00
231.48
1,729.92

4
5
6
7
8
9

Wall (ceramic tile 200x250mm)


Wall (corrugated metal sheet, teakwood formica finish & frame)
Wall (corrugated metal sheet, GRC board panel & frame)
Wall partition (teakwood with formica finish & frame)
Wall partition (GRC board panel & frame)
Wall partition (GRC board panel, teakwood frmica finish & frame)

32.90
210.46
10.74
55.47
16.50
26.56

m2
m2
m2
m2
m2
m2

195,000.00
1,105,500.00
635,490.00
1,290,000.00
486,000.00
888,000.00

19.50
110.55
63.55
129.00
48.60
88.80

6,415,500.00
232,663,530.00
6,825,162.60
71,556,300.00
8,019,000.00
23,585,280.00

641.55
23,266.35
682.52
7,155.63
801.90
2,358.53

10

Ceiling ( teakwood formica finish & wood frame )

120.00

m2

882,000.00

88.20

105,840,000.00

10,584.00

11
12
13
14

Wooden door with aluminium frame (D1A)


Wooden door with aluminium frame (D2A)
Wooden door with aluminium frame (D3A)
Wooden door with aluminium frame (D4A)

3.00
1.00
2.00
1.00

unit
unit
unit
unit

5,772,450.00
9,542,310.00
4,610,655.00
3,616,065.00

577.25
954.23
461.07
361.61

17,317,350.00
9,542,310.00
9,221,310.00
3,616,065.00

1,731.74
954.23
922.13
361.61

15
16
17
18

Fixed glass window with aluminium frame (W1A)


Fixed glass window with aluminium frame (W2A)
Fixed glass window with aluminium frame (W3A)
Fixed glass window with aluminium frame (W4A)

2.00
1.00
1.00
3.00

unit
unit
unit
unit

3,818,880.00
5,679,360.00
2,839,680.00
391,680.00

381.89
567.94
283.97
39.17

7,637,760.00
5,679,360.00
2,839,680.00
1,175,040.00

763.78
567.94
283.97
117.50

19

299.50

m2

2,200,200.00

220.02

658,959,900.00

65,895.99

20
21
22
23

Roof (corrugated metal sheet, insulation, aluminium foil &


chicken wire mesh)
Metal ridge capping
Metal fascia (h : 600mm)
Metal gutter
PVC down pipe dia 4"

28.80
73.60
14.40
10.00

m'
m'
m'
m'

163,500.00
249,000.00
147,000.00
150,000.00

16.35
24.90
14.70
15.00

4,708,800.00
18,326,400.00
2,116,800.00
1,500,000.00

470.88
1,832.64
211.68
150.00

24

Toilet

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900-EST-2121

ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS

Rev. :
R1

WORK ITEM/ DESCRIPTION

QUANTITIES

UNIT

RATE ( Rp )

RATE ( $ )

AMOUNT ( Rp )

Page No:
13

AMOUNT ( $ )

24.1
24.2
24.3
24.4
24.5

Closet
Washtafel + mirror
Jet shower
Urinal
Floor drain

1.00
1.00
1.00
1.00
3.00

unit
unit
unit
unit
unit

6,475,500.00
5,450,400.00
1,320,000.00
4,351,800.00
450,000.00

647.55
545.04
132.00
435.18
45.00

6,475,500.00
5,450,400.00
1,320,000.00
4,351,800.00
1,350,000.00

647.55
545.04
132.00
435.18
135.00

25
25.1
25.2
25.3

Pantry
Faucet
Kitchen sink
Concrete table + ceramic tile finish

1.00
1.00
2.15

unit
unit
m2

690,000.00
1,050,000.00
1,484,400.00

69.00
105.00
148.44

690,000.00
1,050,000.00
3,191,460.00

69.00
105.00
319.15

1,269,118,707.60

126,911.87

TOTAL

Note :

Estimated exchange rates USD 1.00 = Rp 10,000 ,-

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
MECHANICAL WORKS

Rev. :
R1

WORK ITEM/ DESCRIPTION

QUANTITIES

UNIT

RATE ( Rp )

RATE ( $ )

AMOUNT ( Rp )

Page No:
14

AMOUNT ( $ )

SUUPLY AND INSTALL OF AIR CONDITION SYSTEM FOR


FIRE FIGHTING AND RESQUE BUILDING
COMPLETE WITH ACCESSORIES AND REFRIGERANT

IV - 1
Type : Wall Mounted Split
Cap : 9000 btuh

1.00

unit

4,750,000.00

475.00

4,750,000.00

475.00

IV - 2
Type : Wall Mounted Split
Cap : 18000 btuh

1.00

unit

5,150,000.00

515.00

5,150,000.00

515.00

IV - 3
Type : Wall Mounted Split
Cap : 9000 btuh

1.00

unit

4,750,000.00

475.00

4,750,000.00

475.00

II

SUPPLY AND INSTALL CLEAN WATER PIPE FOR


FIRE FIGHTING AND RESQUE BUILDING
COMPLETE WITH ACCESSORIES
PVC Pipe Class AW
2"
1"
3/4 "

III

150.00
15.00
20.00

m
m
m

30,000.00
17,500.00
15,000.00

3.00
1.75
1.50

4,500,000.00
262,500.00
300,000.00

450.00
26.25
30.00

25.00
50.00

m
m

45,000.00
37,500.00

4.50
3.75

1,125,000.00
1,875,000.00

112.50
187.50

SUPPLY AND INSTALL SEWAGE WATER PIPE FOR


FIRE FIGHTING AND RESQUE BUILDING
COMPLETE WITH ACCESSORIES
PVC Pipe Class AW
4"
3"

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
MECHANICAL WORKS

Rev. :
R1

WORK ITEM/ DESCRIPTION


2"

IV

SUPPLY AND INSTALL SEPTIC TANK FOR


FIRE FIGHTING AND RESQUE BUILDING
COMPLETE WITH ACCESSORIES

TAX 10 %

QUANTITIES

UNIT

RATE ( Rp )

RATE ( $ )

Estimated exchange rates USD 1,00 = Rp. 10,000.00

AMOUNT ( $ )

45.00

30,000.00

3.00

1,350,000.00

135.00

1.00

lot

4,000,000.00

400.00

4,000,000.00

400.00

2,806,250.00

280.63

30,868,750.00

3,086.88

TOTAL

Note :

AMOUNT ( Rp )

Page No:
14

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
ELECTRICAL WORKS ( LANDSIDE )

Rev. :
R1

WORK ITEM/ DESCRIPTION

QUANTITIES

UNIT

RATE ( Rp )

RATE ( $ )

AMOUNT ( Rp )

Page No:
15

AMOUNT ( $ )

INSTALLATION NEW FIRE FIGHTING GARAGE


1
2
3
4
5

6
7

Fluorescent Lamp, 2 x 36 watt 220 Volt


1 x 36 watt 220 Volt
Socket Outlet Single Phase
Obstruction Light ( Red Glass )
Flood Light SHP 250 watt - 220 Volt
Incandescent Lamp 60 watt Down Light
Cable Power
NYGBY 4 x 10 mm2
NYY 3 x 2.5 mm2
NYY 3 x 1.5 mm2
Panel Distribution 50 x 40 x 30 completed MCCB, MCB, Metring contactor
Switch 2 pole
1 pole
1 pole ( Water Resistance )
Grounding System
BC Cable 1 x 50 mm2
Cooper Rod 1 inch 3 m
Accessories Grounding System
Lightning Arrester
Cable BC 50 mm2
Galvanish Pipe 1 inch 12 m
Air Terminal 1 inch
Cooper Rod 1 inch 3 m
Accessories Grounding System

14.00
4.00
7.00
4.00
3.00
2.00

set
set
set
set
set
set

370,000.00
205,000.00
41,000.00
1,750,000.00
3,350,000.00
125,000.00

37.00
20.50
4.10
175.00
335.00
12.50

5,180,000.00
820,000.00
287,000.00
7,000,000.00
10,050,000.00
250,000.00

518.00
82.00
28.70
700.00
1,005.00
25.00

220.00
225.00
275.00
1.00
5.00
4.00
3.00

m
m
m
set
set
set
set

29,000.00
6,100.00
4,700.00
4,500,000.00
54,500.00
39,500.00
150,000.00

2.90
0.61
0.47
450.00
5.45
3.95
15.00

6,380,000.00
1,372,500.00
1,292,500.00
4,500,000.00
272,500.00
158,000.00
450,000.00

638.00
137.25
129.25
450.00
27.25
15.80
45.00

120.00
2.00
1.00

set
set
set

20,000.00
400,000.00
1,000,000.00

2.00
40.00
100.00

2,400,000.00
800,000.00
1,000,000.00

240.00
80.00
100.00

100.00
4.00
6.00
4.00
1.00

m
set
set
set
lot

20,000.00
250,000.00
400,000.00
400,000.00
5,000,000.00

2.00
25.00
40.00
40.00
500.00

2,000,000.00
1,000,000.00
2,400,000.00
1,600,000.00
5,000,000.00

200.00
100.00
240.00
160.00
500.00

54,212,500.00

5,421.25

5,421,250.00

542.13

59,633,750.00

5,963.38

Sub Total
VII

TESTING AND COMMISSIONING

1.00

lot

5,421,250.00

542.13
TOTAL

Note :

Estimated exchange rates USD 1,00 = Rp. 10,000.00


All material base on Franco Jakarta

Dicipline No :

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
NEW JETTY

Contract job No :
CCU-0084

Rev. :

Page No:
R1

16

AMOUNT ( Rp )

AMOUNT ( $ )

SUMMARY

ITEM
NO.

WORK ITEM/ DESCRIPTION

PREPARATION OF WORKS

II

PILING OF WORKS

III

CONCRETE OF WORKS

IV

WOOD AND ANCHOR OF WORKS

RETAINING WALL OF WORKS

VI

RECLAMATION OF WORK

VII

PONTOON AND BRIDGE

VIII

TAX 10 %
TOTAL

Note : Estimated exchange rates USD 1.00 = Rp 10,000 ,-

416,900,000.00

41,690.00

2,259,100,000.00

225,910.00

349,172,500.00

34,917.25

53,825,000.00

5,382.50

3,791,070,000.00

379,107.00

513,500,000.00

51,350.00

1,000,000,000.00

100,000.00

838,356,750.00

83,835.68

9,221,924,250.00

922,192.43

Dicipline No :

Contract job No :
CCU-0084

ITEM
NO.

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
NEW JETTY

Rev. :
R1

WORK ITEM/ DESCRIPTION

PREPARATION OF WORK

1
2
3
4
5
6
7
8

Mobilisation
Site Office
Radio Communication / HT
Rent of Survey Device
Photo Documentation Project
Shop Drawings
As Built Drawings
Progress Report

QUANTITIES

1.00
60.00
8.00
6.00
6.00
1.00
1.00
6.00

UNIT

RATE ( Rp )

ls
m2
set
month
month
ls
ls
month

200,000,000.00
2,500,000.00
2,500,000.00
5,000,000.00
250,000.00
5,000,000.00
5,000,000.00
900,000.00

RATE ( $ )

20,000.00
250.00
250.00
500.00
25.00
500.00
500.00
90.00

Sub Total I
II

PILING OF WORKS

1
2
3
4
5

Preparation of Works
Wrapping Piling 400 mm of Works
Piling 400 mm of Works
Joint Piling 400 mm @ 12000 mm
Shoes of Pile

1.00
108.50
538.00
18.00
31.00

ls
m'
m
nos
nos

25,000,000.00
500,000.00
4,000,000.00
600,000.00
550,000.00

2,500.00
50.00
400.00
60.00
55.00

Sub Total II
III

CONCRETE OF WORKS

1
2
3
4

Preparation of Works
Stater Bar of Pile
Pile Cap
Beam
Sub Total III

IV

WOOD AND ANCHOR OF WORKS

1.00
32.67
15.60
28.05

ls
m3
m3
m3

10,000,000.00
4,250,000.00
4,750,000.00
4,500,000.00

1,000.00
425.00
475.00
450.00

AMOUNT ( Rp )

Page No:
17

AMOUNT ( $ )

200,000,000.00
150,000,000.00
20,000,000.00
30,000,000.00
1,500,000.00
5,000,000.00
5,000,000.00
5,400,000.00

20,000.00
15,000.00
2,000.00
3,000.00
150.00
500.00
500.00
540.00

416,900,000.00

41,690.00

25,000,000.00
54,250,000.00
2,152,000,000.00
10,800,000.00
17,050,000.00

2,500.00
5,425.00
215,200.00
1,080.00
1,705.00

2,259,100,000.00

225,910.00

10,000,000.00
138,847,500.00
74,100,000.00
126,225,000.00

1,000.00
13,884.75
7,410.00
12,622.50

349,172,500.00

34,917.25

Dicipline No :

Contract job No :
CCU-0084

Rev. :
R1

ITEM
NO.
1
2
3

Doc. No :
900 - EST - 2121

ENGINEERING ESTIMATE
OF
NEW JETTY

WORK ITEM/ DESCRIPTION


Preparation of Works
Iron Wood 50/200 & 100/200
Anchor Bolt 100

QUANTITIES
1.00
5.36
115.00

UNIT
ls
nos
nos

RATE ( Rp )

RATE ( $ )

5,000,000.00
7,500,000.00
75,000.00

500.00
750.00
7.50

Sub Total IV
V

RETAINING WALL OF WORKS

1
2
3
4
5

Preparation of Work
Lean Concrete
Stone Masonry
Wet Stone
Geotextile

1.00
422.10
2,337.00
7,995.00
5,740.00

ls
m3
m3
m3
m2

2,500,000.00
1,200,000.00
500,000.00
250,000.00
20,000.00

250.00
120.00
50.00
25.00
2.00

Sub Total V
VI

RECLAMATION OF WORKS

1
2
3

Preparation of Works
Compacted Fill
Base Course CBR 80 %

1.00
5,700.00
1,900.00

ls
m3
m3

10,000,000.00
50,000.00
115,000.00

1,000.00
5.00
11.50

Sub Total VI
VII

PONTOON AND BRIDGE

VIII

TAX 10 %
Total

Note :

Estimated exchange rates USD 1.00 = Rp 10,000 ,-

AMOUNT ( Rp )

Page No:
17

AMOUNT ( $ )

5,000,000.00
40,200,000.00
8,625,000.00

500.00
4,020.00
862.50

53,825,000.00

5,382.50

2,500,000.00
506,520,000.00
1,168,500,000.00
1,998,750,000.00
114,800,000.00

250.00
50,652.00
116,850.00
199,875.00
11,480.00

3,791,070,000.00

379,107.00

10,000,000.00
285,000,000.00
218,500,000.00

1,000.00
28,500.00
21,850.00

513,500,000.00

51,350.00

1,000,000,000.00

100,000.00

838,356,750.00

83,835.68

9,221,924,250.00

922,192.43

You might also like