Professional Documents
Culture Documents
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
CIVIL ( AIRSIDE )
Contract job No :
CCU-0084
Rev. :
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
SUMMARY
ITEM
NO.
RUNWAY
II
III
IV
9,597,797,928.52
959,779.79
A. TAXIWAY ( EXISTING )
116,162,637.67
11,616.26
B. TAXIWAY ( NEW )
691,085,214.77
69,108.52
A. APRON ( EXISTING )
836,145,010.32
83,614.50
B. APRON ( NEW )
4,084,422,442.94
408,442.24
TAX 10 %
1,532,561,323.42
153,256.13
16,858,174,557.64
1,685,817.46
TOTAL
Note :
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
CIVIL ( AIRSIDE )
RUNWAY
1
2
3
4
5
Tack Coat
Prime Coat
Asphalt Concrete
ATB
Aggregate Base Course ( CBR = 80 % )
QUANTITIES
97,500.00
19,500.00
292.50
292.50
2,925.00
Rev. :
UNIT
liter
liter
m3
m3
m3
RATE ( Rp )
75,810.00
7,875.00
2,135,804.88
519.49
488,166.00
RATE ( $ )
7.58
0.79
213.58
0.05
48.82
Sub Total I
II
A. TAXIWAY ( EXISTING )
1
2
Asphalt Concrete
ATB
54.38
54.38
m3
m3
2,135,804.88
519.49
213.58
0.05
Sub Total II
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
7,391,475,000.00
153,562,500.00
624,722,927.40
151,951.12
1,427,885,550.00
739,147.50
15,356.25
62,472.29
15.20
142,788.56
9,597,797,928.52
959,779.79
116,134,390.35
28,247.32
11,613.44
2.82
116,162,637.67
11,616.26
164,190,000.15
39,935.87
112,583,283.75
324,071,482.50
12,107,812.50
7,770,525.00
70,322,175.00
16,419.00
3.99
11,258.33
32,407.15
1,210.78
777.05
7,032.22
691,085,214.77
69,108.52
B. TAXIWAY ( NEW )
1
2
3
4
5
6
7
Asphalt Concrete
ATB
Aggregate Base Course ( CBR = 80 %)
Sub Base Course ( CBR = 35 % )
Prime Coat
Tack Coat
Soil Excavation
Sub Total III
76.88
76.88
230.63
922.50
1,537.50
102.50
1,153.13
m3
m3
m3
m3
liter
liter
m3
2,135,804.88
519.49
488,166.00
351,297.00
7,875.00
75,810.00
60,984.00
213.58
0.05
48.82
35.13
0.79
7.58
6.10
Dicipline No :
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
CIVIL ( AIRSIDE )
Contract job No :
CCU-0084
ITEM
NO.
III
A. APRON ( EXISTING )
1
2
3
Asphalt Concrete
ATB
Tack Coat
QUANTITIES
228.92
228.92
4,578.45
Rev. :
UNIT
m3
m3
liter
RATE ( Rp )
2,135,804.88
519.49
75,810.00
RATE ( $ )
213.58
0.05
7.58
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
488,933,792.64
118,923.18
347,092,294.50
48,893.38
11.89
34,709.23
836,145,010.32
83,614.50
838,410,205.64
203,926.19
595,184,310.00
61,826,625.00
574,888,689.90
1,654,819,648.20
359,089,038.00
83,841.02
20.39
59,518.43
6,182.66
57,488.87
165,481.96
35,908.90
Sub Total V
4,084,422,442.94
408,442.24
TAX 10 %
1,532,561,323.42
153,256.13
16,858,174,557.64
1,685,817.46
Sub Total IV
B. APRON ( NEW )
1
2
3
4
5
6
7
IV
Ashpalt Concrete
ATB
Tack Coat
Prime Coat
Aggregate Base Course ( CBR = 80 % )
Sub Base Course ( CBR = 35 % )
Soil Excavation
392.55
392.55
7,851.00
7,851.00
1,177.65
4,710.60
5,888.25
m3
m3
liter
liter
m3
m3
m3
2,135,804.88
519.49
75,810.00
7,875.00
488,166.00
351,297.00
60,984.00
213.58
0.05
7.58
0.79
48.82
35.13
6.10
TOTAL
Note :
Dicipline No :
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
CIVIL ( LANDSIDE )
Contract job No :
CCU-0084
Rev. :
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
SUMMARY
ITEM
NO.
ROAD CONSTRUCTION
PREPARATION
500,000,000.00
50,000.00
100,936,768.54
10,093.68
II
DRAINAGE WORK
5,477,417,641.45
547,741.76
III
TAX 10 %
607,881,641.00
60,788.16
6,686,698,050.99
668,669.81
TOTAL
Note :
Dicipline No :
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
CIVIL ( LANDSIDE )
Contract job No :
CCU-0084
ITEM
NO.
ROAD CONSTRUCTION
PREPARATION
1
2
Tools Mobilisation
Direction Keet & Others
QUANTITIES
1.00
1.00
Rev. :
UNIT
ls
ls
RATE ( Rp )
400,000,000.00
100,000,000.00
RATE ( $ )
40,000.00
10,000.00
Sub Total I
B
1
2
3
4
5
6
Soil Excavation
Prime Coat ( include construction cost )
Tack Coat ( include construction cost )
Asphalt Concrete
Crushed Aggregate Base Course ( CBR 80 % )
Sub Base course ( CBR min 35 % )
102.48
256.20
256.20
12.81
51.24
38.43
m3
liter
liter
m3
m3
m3
50,820.00
7,875.00
75,810.00
2,135,804.88
721,086.18
259,706.52
5.08
0.79
7.58
213.58
72.11
25.97
Sub Total II
II
DRAINAGE WORK
1
2
3
4
5
Soil Excavation
Compacted Sand t = 150
Lean Concrete t = 50
Reinforcement ( concrete )
Steel Grating
267.30
649.68
216.56
3,230.76
1.75
m3
m3
m3
m3
m2
50,820.00
364,596.00
135,900.00
1,608,764.57
264,000.00
5.08
36.46
13.59
160.88
26.40
TAX 10 %
TOTAL
Note :
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
400,000,000.00
100,000,000.00
40,000.00
10,000.00
500,000,000.00
50,000.00
5,208,033.60
2,017,575.00
19,422,522.00
27,359,660.51
36,948,455.86
9,980,521.56
520.80
201.76
1,942.25
2,735.97
3,694.85
998.05
100,936,768.54
10,093.68
13,584,186.00
236,870,729.28
29,430,504.00
5,197,532,222.17
462,000.00
1,358.42
23,687.07
2,943.05
519,753.22
46.20
5,477,879,641.45
547,787.96
607,881,641.00
60,788.16
6,686,698,050.99
668,669.81
Dicipline No :
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
ELECTRICAL WORKS ( AIRSIDE )
Contract job No :
CCU-0084
Rev. :
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
SUMMARY
ITEM
NO.
152,120,000.00
15,212.00
II
181,333,000.00
18,133.30
III
33,345,300.00
3,334.53
366,798,300.00
36,679.83
TOTAL
Note :
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
1
2
3
4
5
6
7
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
ELECTRICAL WORKS ( AIRSIDE )
II
1
2
QUANTITIES
Rev. :
UNIT
150.00
100.00
m
m
150.00
20.00
1.00
2.00
2.00
2.00
m
set
set
set
unit
set
150.00
150.00
m
m
16.00
1.00
unit
unit
RATE ( Rp )
RATE ( $ )
1.00
lot
AMOUNT ( Rp )
AMOUNT ( $ )
2.10
0.67
3,150,000.00
670,000.00
315.00
67.00
20,000.00
400,000.00
5,000,000.00
40,000,000.00
11,000,000.00
15,000,000.00
2.00
40.00
500.00
4,000.00
1,100.00
1,500.00
3,000,000.00
8,000,000.00
5,000,000.00
80,000,000.00
22,000,000.00
30,000,000.00
300.00
800.00
500.00
8,000.00
2,200.00
3,000.00
1,000.00
1,000.00
0.10
0.10
150,000.00
150,000.00
15.00
15.00
8,273,000.00
48,965,000.00
827.30
4,896.50
132,368,000.00
48,965,000.00
13,236.80
4,896.50
333,453,000.00
33,345.30
33,345,300.00
3,334.53
366,798,300.00
36,679.83
33,345,300.00
3,334.53
TOTAL
Note :
21,000.00
6,700.00
Sub Total
III
Page No:
R1
Dicipline No :
Doc. No :
900-EST-2121
ENGINEERING ESTIMATE
OF
BUILDING WORKS
Contract job No :
CCU-0084
Rev. :
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
SUMMARY
ITEM
NO.
STRUCTURE WORKS
313,285,625.70
31,328.56
ARCHITECTURE WORKS
1,086,239,934.30
108,623.99
MECHANICAL WORKS
189,681,250.00
18,968.13
ELECTRICAL WORKS
54,980,500.00
5,498.05
285,430,119.00
28,543.01
1,269,118,707.60
126,911.87
STRUCTURE WORKS
ARCHITECTURE WORKS
MECHANICAL WORKS
30,868,750.00
3,086.88
ELECTRICAL WORKS
59,633,750.00
5,963.38
3,289,238,636.60
328,923.86
TOTAL
Note :
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
STRUCTURAL WORKS
QUANTITIES
Rev. :
UNIT
RATE ( Rp )
RATE ( $ )
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
TERMINAL BUILDING
I
1
2
3
4
Preparation Works
Marking ( setting out )
Excavation foundation
Sand fill
Lean concrete t : 50 mm
78.00
8.70
1.21
12.10
m1
m3
m3
m3
69,000.00
51,000.00
396,600.00
981,000.00
6.90
5.10
39.66
98.10
5,382,000.00
443,700.00
479,886.00
11,870,100.00
538.20
44.37
47.99
1,187.01
II
1
2
3
4
5
Formworks
Footing Type F1
Pedestal Type C
Pedestal Type B
Tie Beam
Slab
10.00
3.60
0.54
6.60
15.98
m2
m2
m2
m2
m2
1,194,000.00
1,194,000.00
1,194,000.00
1,194,000.00
1,194,000.00
119.40
119.40
119.40
119.40
119.40
11,940,000.00
4,298,400.00
644,760.00
7,880,400.00
19,080,120.00
1,194.00
429.84
64.48
788.04
1,908.01
III
1
2
3
4
5
6
7
358.80
63.81
24.50
345.54
163.67
21.12
3.46
kg
kg
kg
kg
m2
kg
kg
21,900.00
21,900.00
21,900.00
21,900.00
81,000.00
21,900.00
21,900.00
2.19
2.19
2.19
2.19
8.10
2.19
2.19
7,857,720.00
1,397,439.00
536,550.00
7,567,326.00
13,257,270.00
462,528.00
75,774.00
785.77
139.74
53.66
756.73
1,325.73
46.25
7.58
IV
1
2
3
4
5
2.50
0.26
0.03
2.93
16.60
m3
m3
m3
m3
m3
1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00
117.00
117.00
117.00
117.00
117.00
2,925,000.00
304,200.00
35,100.00
3,428,100.00
19,422,000.00
292.50
30.42
3.51
342.81
1,942.20
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
VI
1
2
3
4
5
6
7
8
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
STRUCTURAL WORKS
QUANTITIES
1,065.60
1,628.00
1,124.80
2,298.45
388.34
28.04
65.04
1,009.47
Rev. :
UNIT
kg
kg
kg
kg
kg
kg
kg
kg
RATE ( Rp )
RATE ( $ )
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
2.55
2.55
2.55
2.55
2.55
2.55
2.55
2.55
TOTAL
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
27,172,800.00
41,514,000.00
28,682,400.00
58,610,475.00
9,902,670.00
715,020.00
1,658,520.00
25,741,367.70
2,717.28
4,151.40
2,868.24
5,861.05
990.27
71.50
165.85
2,574.14
313,285,625.70
31,328.56
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS
QUANTITIES
Rev. :
UNIT
RATE ( Rp )
RATE ( $ )
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
TERMINAL BUILDING
I
1
2
Demolition Works
Wall Cladding & frame
Toilet
55.25
10.80
m2
m2
6,900.00
71,550.00
0.69
7.16
381,225.00
772,740.00
38.12
77.27
II
1
2
90.05
6.25
m2
m2
204,000.00
192,900.00
20.40
19.29
18,370,200.00
1,205,625.00
1,837.02
120.56
3
4
5
6
7
8
21.60
80.42
9.50
12.36
25.28
5.78
m2
m2
m2
m2
m2
m2
195,000.00
1,105,500.00
635,490.00
1,290,000.00
486,000.00
888,000.00
19.50
110.55
63.55
129.00
48.60
88.80
4,212,000.00
88,904,310.00
6,037,155.00
15,944,400.00
12,286,080.00
5,132,640.00
421.20
8,890.43
603.72
1,594.44
1,228.61
513.26
96.30
m2
240,000.00
24.00
23,112,000.00
2,311.20
10
11
12
3.00
3.00
2.00
unit
unit
unit
6,952,800.00
5,563,950.00
4,610,655.00
695.28
556.40
461.07
20,858,400.00
16,691,850.00
9,221,310.00
2,085.84
1,669.19
922.13
13
14
15
16
17
18
1.00
1.00
2.00
1.00
0.00
1.00
unit
unit
unit
unit
unit
unit
5,679,360.00
6,205,680.00
3,818,880.00
12,252,240.00
1,958,400.00
391,680.00
567.94
620.57
381.89
1,225.22
195.84
39.17
5,679,360.00
6,205,680.00
7,637,760.00
12,252,240.00
0.00
391,680.00
567.94
620.57
763.78
1,225.22
0.00
39.17
19
100.80
m2
2,200,200.00
220.02
221,780,160.00
22,178.02
20
21
10.50
31.20
m'
m'
163,500.00
249,000.00
16.35
24.90
1,716,750.00
7,768,800.00
171.68
776.88
22
23
Canopy Roof
Metal fascia (h : 300mm)
45.13
13.00
m2
m'
467,700.00
124,500.00
46.77
12.45
21,104,962.50
1,618,500.00
2,110.50
161.85
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS
QUANTITIES
Rev. :
UNIT
RATE ( Rp )
RATE ( $ )
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
24
24.1
24.2
24.3
24.5
VIP toilet
Closet
Washtafel + mirror
Jet shower
Floo drain
1.00
1.00
1.00
2.00
unit
unit
unit
unit
6,475,500.00
5,450,400.00
1,320,000.00
450,000.00
647.55
545.04
132.00
45.00
6,475,500.00
5,450,400.00
1,320,000.00
900,000.00
647.55
545.04
132.00
90.00
25
25.1
25.2
Janitor
Faucet
Floor drain
1.00
1.00
unit
unit
345,000.00
450,000.00
34.50
45.00
345,000.00
450,000.00
34.50
45.00
III
1
2
54.00
10.00
m2
m2
204,000.00
192,900.00
20.40
19.29
11,016,000.00
1,929,000.00
1,101.60
192.90
3
4
5
6
7
35.40
90.48
20.52
4.77
16.06
m2
m2
m2
m2
m2
195,000.00
1,105,500.00
635,490.00
486,000.00
888,000.00
19.50
110.55
63.55
48.60
88.80
6,903,000.00
100,025,640.00
13,040,254.80
2,318,220.00
14,261,280.00
690.30
10,002.56
1,304.03
231.82
1,426.13
64.00
m2
882,000.00
88.20
56,448,000.00
5,644.80
9
10
11
2.00
1.00
2.00
unit
unit
unit
6,952,800.00
4,610,655.00
3,616,065.00
695.28
461.07
361.61
13,905,600.00
4,610,655.00
7,232,130.00
1,390.56
461.07
723.21
12
13
14
0.00
5.00
2.00
unit
unit
unit
3,889,080.00
5,783,760.00
391,680.00
388.91
578.38
39.17
0.00
28,918,800.00
783,360.00
0.00
2,891.88
78.34
15
101.60
m2
2,200,200.00
220.02
223,540,320.00
22,354.03
16
17
10.00
40.30
m'
m'
163,500.00
249,000.00
16.35
24.90
1,635,000.00
10,034,700.00
163.50
1,003.47
18
19
Canopy Roof
Metal fascia (h : 300mm)
60.96
24.19
m2
m'
467,700.00
124,500.00
46.77
12.45
28,510,992.00
3,011,655.00
2,851.10
301.17
Dicipline No :
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS
Contract job No :
CCU-0084
ITEM
NO.
QUANTITIES
UNIT
Rev. :
RATE ( Rp )
RATE ( $ )
Page No:
R1
AMOUNT ( Rp )
AMOUNT ( $ )
20
20.1
20.2
20.3
20.4
20.5
Toilet
Closet
Washtafel + mirror
Jet shower
Urinal
Floor drain
2.00
2.00
2.00
1.00
5.00
unit
unit
unit
unit
unit
6,475,500.00
5,450,400.00
1,320,000.00
4,351,800.00
450,000.00
647.55
545.04
132.00
435.18
45.00
12,951,000.00
10,900,800.00
2,640,000.00
4,351,800.00
2,250,000.00
1,295.10
1,090.08
264.00
435.18
225.00
21
21.1
21.2
Janitor
Faucet
Floor drain
1.00
1.00
unit
unit
345,000.00
450,000.00
34.50
45.00
345,000.00
450,000.00
34.50
45.00
1,086,239,934.30
108,623.99
TOTAL
Note :
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
I
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
MECHANICAL WORKS
Rev. :
R1
QUANTITIES
UNIT
RATE ( Rp )
RATE ( $ )
AMOUNT ( Rp )
Page No:
10
AMOUNT ( $ )
IV - 1
Type : Wall Mounted Split
Cap : 18000 btuh
1.00
ser
5,150,000.00
515.00
5,150,000.00
515.00
IV - 2
Type : Wall Mounted Split
Cap : 18000 btuh
1.00
set
5,150,000.00
515.00
5,150,000.00
515.00
IV - 3
Type : Wall Mounted Split
Cap : 18000 btuh
1.00
set
5,150,000.00
515.00
5,150,000.00
515.00
IV - 4
Type : Wall Mounted Split
Cap : 18000 btuh
1.00
set
5,150,000.00
515.00
5,150,000.00
515.00
IV - 5
Type : Wall Mounted Split
Cap : 18000 btuh
1.00
set
5,150,000.00
515.00
5,150,000.00
515.00
IV - 6
Type : Wall Mounted Split
Cap : 18000 btuh
1.00
set
5,150,000.00
515.00
5,150,000.00
515.00
II
PLUMBING
20.00
10.00
m
m
3.00
1.75
600,000.00
175,000.00
60.00
17.50
30,000.00
17,500.00
Dicipline No :
Contract job No :
CCU-0084
III
Rev. :
R1
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
MECHANICAL WORKS
QUANTITIES
UNIT
RATE ( Rp )
RATE ( $ )
AMOUNT ( Rp )
Page No:
10
AMOUNT ( $ )
3/4 " CW
15.00
15,000.00
1.50
225,000.00
22.50
75.00
50.00
25.00
m
m
m
45,000.00
37,500.00
37,500.00
4.50
3.75
3.75
3,375,000.00
1,875,000.00
937,500.00
337.50
187.50
93.75
15.00
30,000.00
3.00
450,000.00
45.00
2.00
lot
4,000,000.00
400.00
8,000,000.00
800.00
50.00
2.00
2.00
6.00
4.00
m
unit
unit
unit
pcs
150,000.00
1,200,000.00
2,400,000.00
1,900,000.00
950,000.00
15.00
120.00
240.00
190.00
95.00
7,500,000.00
2,400,000.00
4,800,000.00
11,400,000.00
3,800,000.00
750.00
240.00
480.00
1,140.00
380.00
1.00
unit
96,000,000.00
9,600.00
96,000,000.00
9,600.00
17,243,750.00
1,724.38
189,681,250.00
18,968.13
IV
MISCELLANEOUS WORK
TAX 10 %
TOTAL
Note :
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
ELECTRICAL WORKS ( LANDSIDE )
Rev. :
R1
QUANTITIES
UNIT
RATE ( Rp )
RATE ( $ )
AMOUNT ( Rp )
Page No:
11
AMOUNT ( $ )
4
5
6
7
8
9
16.00
7.00
325.00
35.00
80.00
1.00
3.00
9.00
8.00
1.00
set
set
m
m
m
set
set
set
set
lot
370,000.00
41,000.00
6,100.00
16,700.00
57,500.00
22,500,000.00
54,500.00
39,500.00
125,000.00
10,000,000.00
37.00
4.10
0.61
1.67
5.75
2,250.00
5.45
3.95
12.50
1,000.00
5,920,000.00
287,000.00
1,982,500.00
584,500.00
4,600,000.00
22,500,000.00
163,500.00
355,500.00
1,000,000.00
10,000,000.00
592.00
28.70
198.25
58.45
460.00
2,250.00
16.35
35.55
100.00
1,000.00
150.00
36,000.00
3.60
5,400,000.00
540.00
325.00
35.00
80.00
31.00
m
m
m
set
1,000.00
1,000.00
2,500.00
52,500.00
0.10
0.10
0.25
5.25
325,000.00
35,000.00
200,000.00
1,627,500.00
32.50
3.50
20.00
162.75
54,980,500.00
5,498.05
TOTAL
Note :
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900-EST-2121
ENGINEERING ESTIMATE
OF
STRUCTURAL WORKS
Rev. :
R1
QUANTITIES
UNIT
RATE ( Rp )
RATE ( $ )
AMOUNT ( Rp )
Page No:
12
AMOUNT ( $ )
Preparation Works
Marking ( setting out )
Excavation foundation
Back filling
Sand fill
Lean concrete t : 50 mm
74.00
13.92
10.76
1.72
0.72
m1
m3
m3
m3
m3
69,000.00
51,000.00
30,000.00
396,600.00
981,000.00
6.90
5.10
3.00
39.66
98.10
5,106,000.00
709,920.00
322,800.00
682,152.00
706,320.00
510.60
70.99
32.28
68.22
70.63
II
1
2
3
4
5
Formworks
Footing Type F1
Pedestal section C
Edge of slab
Pedestal section A
Pedestal section D
14.40
4.32
16.00
0.18
0.18
m2
m2
m2
m2
m2
1,194,000.00
1,194,000.00
1,194,000.00
1,194,000.00
1,194,000.00
119.40
119.40
119.40
119.40
119.40
17,193,600.00
5,158,080.00
19,104,000.00
214,920.00
214,920.00
1,719.36
515.81
1,910.40
21.49
21.49
III
1
2
3
4
5
6
7
8
9
468.00
126.76
8.40
6.80
59.52
323.00
249.29
26.51
1.89
kg
kg
kg
kg
kg
kg
m2
kg
kg
21,900.00
21,900.00
21,900.00
21,900.00
21,900.00
21,900.00
81,000.00
21,900.00
21,900.00
2.19
2.19
2.19
2.19
2.19
2.19
8.10
2.19
2.19
10,249,200.00
2,776,044.00
183,960.00
148,920.00
1,303,488.00
7,073,700.00
20,192,490.00
580,569.00
41,391.00
1,024.92
277.60
18.40
14.89
130.35
707.37
2,019.25
58.06
4.14
IV
1
2
3
4
5
6
3.00
0.31
3.92
1.45
0.02
23.63
m3
m3
m3
m3
m3
m3
1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00
1,170,000.00
117.00
117.00
117.00
117.00
117.00
117.00
3,510,000.00
362,700.00
4,586,400.00
1,696,500.00
23,400.00
27,647,100.00
351.00
36.27
458.64
169.65
2.34
2,764.71
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
VI
1
2
3
4
5
6
7
8
9
10
Doc. No :
900-EST-2121
ENGINEERING ESTIMATE
OF
STRUCTURAL WORKS
Rev. :
R1
QUANTITIES
1,758.24
2,628.48
766.80
117.70
592.35
35.17
169.68
35.17
48.00
615.15
UNIT
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
RATE ( Rp )
RATE ( $ )
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
25,500.00
2.55
2.55
2.55
2.55
2.55
2.55
2.55
2.55
2.55
2.55
Total
Note :
AMOUNT ( Rp )
Page No:
12
AMOUNT ( $ )
44,835,120.00
67,026,240.00
19,553,400.00
3,001,350.00
15,104,925.00
896,835.00
4,326,840.00
896,835.00
1,224,000.00
15,686,325.00
4,483.51
6,702.62
1,955.34
300.14
1,510.49
89.68
432.68
89.68
122.40
1,568.63
285,430,119.00
28,543.01
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900-EST-2121
ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS
Rev. :
R1
QUANTITIES
UNIT
RATE ( Rp )
RATE ( $ )
AMOUNT ( Rp )
Page No:
13
AMOUNT ( $ )
Floor works
Floor hardener ( 5kg/ m2 )
Floor (ceramic tile 200x200mm)
Floor (ceramic tile 300x300mm)
187.20
12.00
84.80
m2
m2
m2
150,000.00
192,900.00
204,000.00
15.00
19.29
20.40
28,080,000.00
2,314,800.00
17,299,200.00
2,808.00
231.48
1,729.92
4
5
6
7
8
9
32.90
210.46
10.74
55.47
16.50
26.56
m2
m2
m2
m2
m2
m2
195,000.00
1,105,500.00
635,490.00
1,290,000.00
486,000.00
888,000.00
19.50
110.55
63.55
129.00
48.60
88.80
6,415,500.00
232,663,530.00
6,825,162.60
71,556,300.00
8,019,000.00
23,585,280.00
641.55
23,266.35
682.52
7,155.63
801.90
2,358.53
10
120.00
m2
882,000.00
88.20
105,840,000.00
10,584.00
11
12
13
14
3.00
1.00
2.00
1.00
unit
unit
unit
unit
5,772,450.00
9,542,310.00
4,610,655.00
3,616,065.00
577.25
954.23
461.07
361.61
17,317,350.00
9,542,310.00
9,221,310.00
3,616,065.00
1,731.74
954.23
922.13
361.61
15
16
17
18
2.00
1.00
1.00
3.00
unit
unit
unit
unit
3,818,880.00
5,679,360.00
2,839,680.00
391,680.00
381.89
567.94
283.97
39.17
7,637,760.00
5,679,360.00
2,839,680.00
1,175,040.00
763.78
567.94
283.97
117.50
19
299.50
m2
2,200,200.00
220.02
658,959,900.00
65,895.99
20
21
22
23
28.80
73.60
14.40
10.00
m'
m'
m'
m'
163,500.00
249,000.00
147,000.00
150,000.00
16.35
24.90
14.70
15.00
4,708,800.00
18,326,400.00
2,116,800.00
1,500,000.00
470.88
1,832.64
211.68
150.00
24
Toilet
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900-EST-2121
ENGINEERING ESTIMATE
OF
ARCHITECTURAL WORKS
Rev. :
R1
QUANTITIES
UNIT
RATE ( Rp )
RATE ( $ )
AMOUNT ( Rp )
Page No:
13
AMOUNT ( $ )
24.1
24.2
24.3
24.4
24.5
Closet
Washtafel + mirror
Jet shower
Urinal
Floor drain
1.00
1.00
1.00
1.00
3.00
unit
unit
unit
unit
unit
6,475,500.00
5,450,400.00
1,320,000.00
4,351,800.00
450,000.00
647.55
545.04
132.00
435.18
45.00
6,475,500.00
5,450,400.00
1,320,000.00
4,351,800.00
1,350,000.00
647.55
545.04
132.00
435.18
135.00
25
25.1
25.2
25.3
Pantry
Faucet
Kitchen sink
Concrete table + ceramic tile finish
1.00
1.00
2.15
unit
unit
m2
690,000.00
1,050,000.00
1,484,400.00
69.00
105.00
148.44
690,000.00
1,050,000.00
3,191,460.00
69.00
105.00
319.15
1,269,118,707.60
126,911.87
TOTAL
Note :
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
MECHANICAL WORKS
Rev. :
R1
QUANTITIES
UNIT
RATE ( Rp )
RATE ( $ )
AMOUNT ( Rp )
Page No:
14
AMOUNT ( $ )
IV - 1
Type : Wall Mounted Split
Cap : 9000 btuh
1.00
unit
4,750,000.00
475.00
4,750,000.00
475.00
IV - 2
Type : Wall Mounted Split
Cap : 18000 btuh
1.00
unit
5,150,000.00
515.00
5,150,000.00
515.00
IV - 3
Type : Wall Mounted Split
Cap : 9000 btuh
1.00
unit
4,750,000.00
475.00
4,750,000.00
475.00
II
III
150.00
15.00
20.00
m
m
m
30,000.00
17,500.00
15,000.00
3.00
1.75
1.50
4,500,000.00
262,500.00
300,000.00
450.00
26.25
30.00
25.00
50.00
m
m
45,000.00
37,500.00
4.50
3.75
1,125,000.00
1,875,000.00
112.50
187.50
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
MECHANICAL WORKS
Rev. :
R1
IV
TAX 10 %
QUANTITIES
UNIT
RATE ( Rp )
RATE ( $ )
AMOUNT ( $ )
45.00
30,000.00
3.00
1,350,000.00
135.00
1.00
lot
4,000,000.00
400.00
4,000,000.00
400.00
2,806,250.00
280.63
30,868,750.00
3,086.88
TOTAL
Note :
AMOUNT ( Rp )
Page No:
14
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
ELECTRICAL WORKS ( LANDSIDE )
Rev. :
R1
QUANTITIES
UNIT
RATE ( Rp )
RATE ( $ )
AMOUNT ( Rp )
Page No:
15
AMOUNT ( $ )
6
7
14.00
4.00
7.00
4.00
3.00
2.00
set
set
set
set
set
set
370,000.00
205,000.00
41,000.00
1,750,000.00
3,350,000.00
125,000.00
37.00
20.50
4.10
175.00
335.00
12.50
5,180,000.00
820,000.00
287,000.00
7,000,000.00
10,050,000.00
250,000.00
518.00
82.00
28.70
700.00
1,005.00
25.00
220.00
225.00
275.00
1.00
5.00
4.00
3.00
m
m
m
set
set
set
set
29,000.00
6,100.00
4,700.00
4,500,000.00
54,500.00
39,500.00
150,000.00
2.90
0.61
0.47
450.00
5.45
3.95
15.00
6,380,000.00
1,372,500.00
1,292,500.00
4,500,000.00
272,500.00
158,000.00
450,000.00
638.00
137.25
129.25
450.00
27.25
15.80
45.00
120.00
2.00
1.00
set
set
set
20,000.00
400,000.00
1,000,000.00
2.00
40.00
100.00
2,400,000.00
800,000.00
1,000,000.00
240.00
80.00
100.00
100.00
4.00
6.00
4.00
1.00
m
set
set
set
lot
20,000.00
250,000.00
400,000.00
400,000.00
5,000,000.00
2.00
25.00
40.00
40.00
500.00
2,000,000.00
1,000,000.00
2,400,000.00
1,600,000.00
5,000,000.00
200.00
100.00
240.00
160.00
500.00
54,212,500.00
5,421.25
5,421,250.00
542.13
59,633,750.00
5,963.38
Sub Total
VII
1.00
lot
5,421,250.00
542.13
TOTAL
Note :
Dicipline No :
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
NEW JETTY
Contract job No :
CCU-0084
Rev. :
Page No:
R1
16
AMOUNT ( Rp )
AMOUNT ( $ )
SUMMARY
ITEM
NO.
PREPARATION OF WORKS
II
PILING OF WORKS
III
CONCRETE OF WORKS
IV
VI
RECLAMATION OF WORK
VII
VIII
TAX 10 %
TOTAL
416,900,000.00
41,690.00
2,259,100,000.00
225,910.00
349,172,500.00
34,917.25
53,825,000.00
5,382.50
3,791,070,000.00
379,107.00
513,500,000.00
51,350.00
1,000,000,000.00
100,000.00
838,356,750.00
83,835.68
9,221,924,250.00
922,192.43
Dicipline No :
Contract job No :
CCU-0084
ITEM
NO.
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
NEW JETTY
Rev. :
R1
PREPARATION OF WORK
1
2
3
4
5
6
7
8
Mobilisation
Site Office
Radio Communication / HT
Rent of Survey Device
Photo Documentation Project
Shop Drawings
As Built Drawings
Progress Report
QUANTITIES
1.00
60.00
8.00
6.00
6.00
1.00
1.00
6.00
UNIT
RATE ( Rp )
ls
m2
set
month
month
ls
ls
month
200,000,000.00
2,500,000.00
2,500,000.00
5,000,000.00
250,000.00
5,000,000.00
5,000,000.00
900,000.00
RATE ( $ )
20,000.00
250.00
250.00
500.00
25.00
500.00
500.00
90.00
Sub Total I
II
PILING OF WORKS
1
2
3
4
5
Preparation of Works
Wrapping Piling 400 mm of Works
Piling 400 mm of Works
Joint Piling 400 mm @ 12000 mm
Shoes of Pile
1.00
108.50
538.00
18.00
31.00
ls
m'
m
nos
nos
25,000,000.00
500,000.00
4,000,000.00
600,000.00
550,000.00
2,500.00
50.00
400.00
60.00
55.00
Sub Total II
III
CONCRETE OF WORKS
1
2
3
4
Preparation of Works
Stater Bar of Pile
Pile Cap
Beam
Sub Total III
IV
1.00
32.67
15.60
28.05
ls
m3
m3
m3
10,000,000.00
4,250,000.00
4,750,000.00
4,500,000.00
1,000.00
425.00
475.00
450.00
AMOUNT ( Rp )
Page No:
17
AMOUNT ( $ )
200,000,000.00
150,000,000.00
20,000,000.00
30,000,000.00
1,500,000.00
5,000,000.00
5,000,000.00
5,400,000.00
20,000.00
15,000.00
2,000.00
3,000.00
150.00
500.00
500.00
540.00
416,900,000.00
41,690.00
25,000,000.00
54,250,000.00
2,152,000,000.00
10,800,000.00
17,050,000.00
2,500.00
5,425.00
215,200.00
1,080.00
1,705.00
2,259,100,000.00
225,910.00
10,000,000.00
138,847,500.00
74,100,000.00
126,225,000.00
1,000.00
13,884.75
7,410.00
12,622.50
349,172,500.00
34,917.25
Dicipline No :
Contract job No :
CCU-0084
Rev. :
R1
ITEM
NO.
1
2
3
Doc. No :
900 - EST - 2121
ENGINEERING ESTIMATE
OF
NEW JETTY
QUANTITIES
1.00
5.36
115.00
UNIT
ls
nos
nos
RATE ( Rp )
RATE ( $ )
5,000,000.00
7,500,000.00
75,000.00
500.00
750.00
7.50
Sub Total IV
V
1
2
3
4
5
Preparation of Work
Lean Concrete
Stone Masonry
Wet Stone
Geotextile
1.00
422.10
2,337.00
7,995.00
5,740.00
ls
m3
m3
m3
m2
2,500,000.00
1,200,000.00
500,000.00
250,000.00
20,000.00
250.00
120.00
50.00
25.00
2.00
Sub Total V
VI
RECLAMATION OF WORKS
1
2
3
Preparation of Works
Compacted Fill
Base Course CBR 80 %
1.00
5,700.00
1,900.00
ls
m3
m3
10,000,000.00
50,000.00
115,000.00
1,000.00
5.00
11.50
Sub Total VI
VII
VIII
TAX 10 %
Total
Note :
AMOUNT ( Rp )
Page No:
17
AMOUNT ( $ )
5,000,000.00
40,200,000.00
8,625,000.00
500.00
4,020.00
862.50
53,825,000.00
5,382.50
2,500,000.00
506,520,000.00
1,168,500,000.00
1,998,750,000.00
114,800,000.00
250.00
50,652.00
116,850.00
199,875.00
11,480.00
3,791,070,000.00
379,107.00
10,000,000.00
285,000,000.00
218,500,000.00
1,000.00
28,500.00
21,850.00
513,500,000.00
51,350.00
1,000,000,000.00
100,000.00
838,356,750.00
83,835.68
9,221,924,250.00
922,192.43