Professional Documents
Culture Documents
17 April 2009
Prepared by:
AKONAAY M.L. AKO
Senior Associate Consultant
(Environment and Natural Resource)
Mobile: +255 754 605 279 or +255 73 299 1845
E-mail: akonaay@yahoo.com
Scoping Report 17 April 2009
TABLE OF CONTENTS
1.0 INTRODUCTION................................................................................................................................................1
1.1 PROJECT BACKGROUND............................................................................................................................................1
1.2 ENVIRONMENTAL IMPACT ASSESSMENT REQUIREMENTS..................................................................................................2
2.0 PROJECT DESCRIPTION................................................................................................................................2
2.1 JUSTIFICATION FOR THE PROJECT...............................................................................................................................2
2.2 THE OBJECTIVE OF THE PROJECT..............................................................................................................................2
2.2 LOCATION.............................................................................................................................................................2
2.3PROJECT ACTIVITIES ................................................................................................................................................4
2.4 PROJECT DESIGN...................................................................................................................................................5
2.5 MATERIALS REQUIREMENTS......................................................................................................................................6
3.0 SCOPING METHODOLOGY...........................................................................................................................6
4.0 RESULTS OF PUBLIC / STAKEHOLDER CONSULTATIONS...................................................................7
5.0 IDENTIFICATION OF POTENTIAL POSITIVE AND NEGATIVE IMPACTS........................................8
5.1 POSITIVE IMPACTS..................................................................................................................................................8
5.2 NEGATIVE IMPACTS................................................................................................................................................8
6.0 STAKEHOLDER GROUPS IDENTIFIED AND THEIR INVOLVEMENT..............................................10
6.1 AUTHORITIES OR DECISION MAKERS........................................................................................................................10
6.2 DEVELOPER.........................................................................................................................................................10
6.3 AFFECTED PARTIES (DIRECTLY OR INDIRECTLY).........................................................................................................10
6.4 INTERESTED PARTIES.............................................................................................................................................11
7.0 PROJECT BOUNDARIES................................................................................................................................12
7.1 SPATIAL BOUNDARIES............................................................................................................................................12
7.2 TEMPORAL BOUNDARIES........................................................................................................................................12
7.3 INSTITUTIONAL BOUNDARIES..................................................................................................................................12
8.0 PROJECT ALTERNATIVES AND RECOMMENDATIONS ......................................................................13
8.1 NO PROJECT ALTERNATIVE....................................................................................................................................13
8.2 PROJECT ALTERNATIVE..........................................................................................................................................13
8.3 NO PROJECT ALTERNATIVE VERSUS PROJECT ALTERNATIVE........................................................................................13
9.0 TERMS OF REFERENCE................................................................................................................................15
APPENDICES..........................................................................................................................................................16
1.0 INTRODUCTION
2.2 Location
The project is located in the two districts of Kilombero and Ulanga in
Morogoro Region. The regional location of the project area is shown is Figure
2.1. Specifically the proposed bridge site is located about 5 Km from Ifakara
town. The bridge is connected by two approach roads, whereby one
approach road from Ifakara town in Kilombero District is about 5 Km and
the other one from Mahenge town in Ulanga District is about 6 Km long.
The road starts In Ifakara at Mlabani roundabout and ends up at Kivukoni
Village in Ulanga District, with a total length of about 11 Km. Location of the
proposed bridge and its approach roads is shown in Figure 2.2.
Figure 2.1: The location of the proposed bridge (red circle) and its approach roads
The approach roads will be built of bitumen standard and will have a width
of about 6.5 m and 1.5 m shoulder. The approach road from Ifakara side will
a length of about 5 Km and the other one from Mahenge side (Ulanga
District) will have a length of about 6 Km; hence forming a total length of
about 11 Km.
More details on the project design can be found in the Detailed Engineering
Design Report.
c) Sand:
o From Kilombero River Bed
d) Construction Water:
o From either Kilombero River or Lumemo River depending on the
distance from construction site.
e) Other materials:
Other required materials include:
o Cement
o Reinforced steel bars
o Steel beams
o Timber
o Gabions wire for protection of river banks.
6.2 Developer
The developer or project proponent is the Tanzania National Roads Agency
(TANROADS), which shall be responsible for project implementation on
behalf of the Government of Tanzania. The TANROADS Regional Manager
shall be responsible for project implementation at regional level on the
behalf of TANROADS Headquarters.
The indirectly affected parties are the local communities residing within the
area of influence (AI). The area of influence is considered to be the areas
beyond the direct impact zone (DIZ). Other indirectly affected parties
include:
♦ District Councils
♦ Village Governments
♦ Local NGOs and CBOs dealing with HIV / AIDS and environmental
conservation
TANROADS REGIONAL MANAGER 10 NIMETA CONSULT (T) LTD in
MOROGORO REGION association with
HOWRD HUMPREYS
Scoping Report 17 April 2009
The proposed bridge is expected to have a width of about 7.5 m and a total
clear span of about 360 m with guardrail protected footpaths of about 1.5 m
on both sides. The approach road between Mlabani Village and Kilombero
River extends for about 5 Km to the north and for about 6 Km between
Kilombero River and Kivukoni village to the south.
The NEMC and Vice-President’s Office (VPO) are responsible for overseeing
implementation of National Environment Policy (NEP) and Environmental
legislations.
The local authorities including the District Councils, Ward and Village
Councils are responsible for environmental monitoring during project
1
Feasibility Study and Preliminary Engineering Design of Kilombero Bridge and its Approach roads.
Environmental Impact Assessment Report. By Engineering Research Associates Ltd and Projects Inter
Design. June 2008.
TANROADS REGIONAL MANAGER 12 NIMETA CONSULT (T) LTD in
MOROGORO REGION association with
HOWRD HUMPREYS
Scoping Report 17 April 2009
TOTAL SCORE -3 +3
APPENDICES
♦ There should be a
programme to plant
ornamental trees species
long the approach roads to
improve the quality of
landscape.
Loss of soil from roadsides Land owners must be
and borrow pits. compensated for
extracted materials.
campaigns.
1. INTRODUCTION
This project involves construction of concrete piles bridge across Kilombero
River and its approach roads into bitumen standard. The proposed bridge is
expected to have 360 m span and 7.5 m width, with 1.5 m pedestrian
crossings on both sides. The two approach roads, one on the northern side
will be about 5 Km long and the other one on the south will be about 6 Km
long
It is expected that the construction of the proposed bridge shall provide
reliable crossing for pedestrians and vehicular traffic as well as non-
motorized traffic. It will also reduce if not eliminate risk of accidents, hence
loss to human life and properties. The reliable crossing will also increase
the number of tourists visiting the Selous Game Reserve.
The project is being financed and implemented by Tanzania National Roads
Agency (TANROADS) through Regional Manager, TANROADS – Morogoro.
However, before implementing the project it has been necessary to carry
out Environmental and Social Impact Assessment (ESIA) study in
accordance with the Environmental Impact Assessment and Audit
Regulations of 2005. The intention is to identify any adverse (negative)
environmental and social impacts associated with this project and
thereafter propose appropriate mitigation measures and incorporate them
into the design process.
Thus, on March 2009 Regional Manager, TANROADS – Morogoro (Hereinafter
referred to as the Client) commissioned NIMETA CONSULT LTD in association
with HOWARD HUMPHREYS (T) LTD (Hereinafter referred to as the
Consultant) to carry out Environmental and Social Impact Assessment
(ESIA) study. In this regards, the purpose of this Terms of Reference (TOR)
is to guide the Consultant to address relevant environmental and social
issues during the assessment process. Among others the ESIA study shall
be conducted in accordance with the requirements of the Environmental
Impact Assessment and Audit Regulations of 2005. The Consultant shall do
everything necessary to meet the objectives of the services and not less
than outlined tasks in the scope of work.
2. SCOPE OF WORK
The Executive Summary in English and Kiswahili versions and ESIA main
report should be submitted according to the requirements of Regulations 19
to 21 of the Environmental Impact Assessment and Audit Regulations of
2005.
4. STAFFING
The Consultant’s staffing shall be comprised of:
Environmental Impact Assessment Expert for conducting EIA study
and preparing ESIA report.
Sociologist for conducting SIA study and preparing RAP report.